RNS Number : 0613A  Hummingbird Resources PLC  31 January 2022

Hummingbird Resources plc / Ticker: HUM / Index: AIM / Sector: Mining

31 January 2022

Hummingbird Resources plc

("Hummingbird" or the "Company")

Q4 2021 Operational Update and 2022 Outlook

 

Hummingbird Resources plc (AIM: HUM) provides an operational update for the
fourth quarter of 2021 ("Q4 2021") and its outlook for FY2022.

For the full release, including photos, please follow the link here:
http://www.rns-pdf.londonstockexchange.com/rns/0613A_1-2022-1-30.pdf
(http://www.rns-pdf.londonstockexchange.com/rns/0613A_1-2022-1-30.pdf)

Investors are welcome to join Senior Management on Thursday, 3 February 2022,
at 09:30 GMT for a retail investor webinar via the InvestorMeetCompany
platform. Information and registration details are provided below.

Q4 2021 updates:

·      18,181 ounces ("oz") of gold poured at Yanfolila in Q4 2021

o  FY2021 production of 87,558 oz, in line with the revised guidance range of
84,000 - 89,000 oz

·      18,489 oz of gold sold in Q4 2021 at an average realised price of
US$1,782 per oz

·      2,246 oz gold inventory at 31 December 2021, valued at c.US$4.1
million

·      All In Sustaining Costs ("AISC") of US$1,803 per oz for Q4 2021

o  FY2021 AISC of US$1,536 oz, in line with revised guidance of US$1,490 -
US$1,590 per oz

·      Company Reserves were updated,  increasing to 1.12 million oz at
3.03 g/t, including: Yanfolila, Mali to 705,800 oz at 2.57 g/t and a maiden
Reserve for Kouroussa, Guinea of 408,900 oz at 4.38 g/t

·      The Company successfully received an externally audited assurance
report for the World Gold Council ("WGC") Responsible Gold Mining Principles
("RGMPs") conformance for year two implementation and progress towards full
conformance in 2022

FY2022 Guidance:

·      FY2022 production guidance of 87,000 - 97,000 oz of gold, with an
AISC of US$1,300 - 1,450 per oz of gold

o  Q1 2022 is forecast to be a lower production quarter versus the remaining
quarters of 2022, with a ramp up from Q2 2022 expected, driven primarily by an
additional five excavators becoming increasingly operational during Q1

o  Further operational improvement measures at Yanfolila have been undertaken
to ensure 2022 guidance forecasts are met, as detailed below

Operational Updates:

Yanfolila, Mali

·      Operations have underperformed since September 2021, primarily
due to our mining contractor's excavator fleet not meeting the contracted
mining rates. The reduction in material movements have led to a lower grade
profile primarily due to lower grade sections of the orebody accessed during
this period. Mitigation measures that have been undertaken include:

o  Adding five additional excavators to the current fleet, with the
expectation that all will be fully operational during Q1 2022

o  Reinforcing our contract miners maintenance team to improve overall mining
fleet performance

o  Implementing several other operational workstreams at site, with the key
focus to improve: production performance and predictability; mill grade feed
profile; and departmental cost disciple

·      During the quarter c.12,800 meters ("m") of drilling assays were
analysed from the Sanioumale West ("SW") and greenfield deposits, Kama and
Diaban, highlighting significant grade and depth at the SW deposit and the
potential to establish new greenfield resources as detailed in the 20 December
2021 release

Kouroussa, Guinea

·      December 2021 saw the increased mobilisation of equipment and
personnel on site to enable construction, which began in early January as
detailed in the 10 January 2022 release. Civil engineering work is scheduled
to commence this quarter and the Company remains on track for first gold pour
by the end of Q2 2023

·      To fund construction, in late December 2021, the Company drew the
second of three tranches available from the Company financing facility
provided by Coris Bank International ("Coris Bank")

·      In Q4 2021 and in early January 2022, the Company released
approximately 7,700 m of infill drilling results, with multiple high-grade
intercepts received, including extremely encouraging results such as a 55 m
intercept at 35.72 grams a ton ("g/t"), strengthening the Company's knowledge
base and confidence in the Kouroussa asset which is situated in the highly
prospective Siguiri region

Dugbe, Liberia

·      Earn-in partner Pasofino Gold Ltd ("Pasofino") updated Dugbe's
Mineral Resources Estimates ("MRE") in Q4 2021, totalling 4 million oz
("Moz"), with 3.4 Moz in the Measured and Indicated category, and remains on
track to deliver a Definitively Feasibly Study ("DFS") in Q2 2022. The Company
notes the investment in Pasofino in Q4 2021 by the ESAN group from Turkey

Dan Betts, CEO of Hummingbird, commented:

"Throughout 2021, the Company has made significant steps towards our strategic
goal of becoming a multi-asset, multi jurisdiction gold producer. Construction
at Kouroussa is ramping up and is on schedule for first gold by the end of Q2
2023 - taking the Company to being a +200,000 oz gold producer. The
feasibility study at Dugbe is coming together as per the schedule and we are
expecting robust and attractive economics which will provide additional
optionality for our portfolio of assets.  Further, we saw our Company
Reserves increase, adding mine life at Yanfolila, including maiden underground
Reserves and importantly adding maiden Reserves at Kouroussa. We expect that
trend to continue when our updated Company Resources and Reserves statement is
released in Q2 2022.

Clearly, this progress has been overshadowed by the operational
underperformance of Yanfolila in recent months. Whilst the operation has been
beset by a number of extraneous challenges, the overwhelming root cause for
this performance has been the under performance of the contract mining fleet
at site and the timeframes involved with bringing in extra capacity. As such,
we are putting significant focus on improving productivity and predictability
at the Yanfolila with several optimisation and mitigation workstream in train.
These plans have been actioned and are largely in place with our forward
looking 2022 guidance accommodating these challenges.

Following the release of our maiden underground Reserves at Yanfolila, we see
significant potential in the Komana East Underground, underpinning Yanfolila's
future production profile, with higher grade ore for many years to come. Our
team is currently finalising analysis of the optimal development route to then
put into our future mine plans. We are considering options to accelerate the
development of the underground project in order to bring the delivery of
higher-grade ore forward.

As we saw in 2021, this year we will once again further our ESG initiatives.
This includes the implementation of energy efficiency programmes at Kouroussa
and the continuing establishment of Single Mine Origin ("SMO") as an industry
platform for fully traceable precious metals to responsibly operated mines. I
believe that all of these actions will be key to delivering material long term
shareholder value."

Anthony Köcken, COO of Hummingbird, commented:

"As we move into 2022, we are focused on critical operational areas at both
Yanfolila and Kouroussa. At Yanfolila, these include amongst others: overall
better performance of the excavator fleet, which is in progress with
additional fleet ordered and becoming operational; optimisation of geological
control and ore management; wet weather planning and mitigation measures;
finalising underground analysis to then implement into our future mine plans;
and line management control improvements across each of the operational
departments. We are confident these measures and others will lead to an
overall improvement in production, cost management and performance
predictability at Yanfoliila.

For Kouroussa, the project has moved from the mobilisation phase to breaking
ground. We have commenced construction and key contracts for power generation
and mining are at advanced stages of discussion and finalisation. Our key
focus for Kouroussa remains to maintain our diligent approach to timelines,
capex management, positive community engagement and an overall quality build
process."

Retail Investor Webinar Details

The Company's senior management will be holding an investor webinar on
Thursday 3(rd) February 2022 at 09:30hr GMT via the Investor Meet Company
platform.

The event will be hosted by CEO Dan Betts, CFO Tom Hill, CSO Edward Montgomery
and COO Anthony Köcken. It is open to all existing and potential
shareholders. Investors are welcome to submit questions prior to the event
through the above link or by emailing HUM@Buchanan.uk.com
(mailto:HUM@Buchanan.uk.com) , or at any time during the event via the "Ask a
Question" function.

Investors can register to Investor Meet Company for free
via: https://www.investormeetcompany.com/hummingbird-resources-plc/register-investor
(https://www.investormeetcompany.com/hummingbird-resources-plc/register-investor)
 

Operational Update

                       Unit  YTD 2021     Q4 2021    Q3 2021    Q2 2021    Q1 2021
 Gold poured           oz       87,558    18,181     22,102     24,494     22,781
 Mined BCMs            bcms  9,554,326    1,920,311  2,095,935  2,672,788  2,865,292
 Ore mined             t     1,645,417    445,808    392,005    443,490    364,114
 Ore processed         t     1,404,982    341,936    326,020    391,652    345,374
 Avg. grade mill feed  g/t   2.09         1.79       2.27       2.14       2.16
 Recovery              %     92.26%       92.38%     91.95%     91.88%     92.97%
 Gold inventory        oz    2,246        2,246      2,769      1,972      2,596

* Ore mined includes high grade, low grade, and marginal material. Ore
processed is a blend based on preferential feed of high-grade and low grade,
with marginal ore added as an incremental feed source

·      As detailed on 15 December, Q4 2021 production was impacted due
to disruptions caused by local unrest leading to the plant being offline for
approximately six days and the subsequent impacts of returning the mine back
into operation; and our mining contractor's excavator fleet failing to perform
consistently to the scheduled mining volume rates

o  Full year 2021 production of 87,558 oz, in line with the revised guidance
range of 84,000 - 89,000 oz

·      Grade mill feed for Q4 2021 averaged 1.79 g/t and totalled 2.09
g/t for the full year

o  Q4 2021's lower grade profile was primarily due to lower grade sections of
the orebody accessed during this period caused by reduced material movement
from an underperforming excavator fleet

o  Mined bank cubic meters ("BCMs") declined in Q4 2021 versus Q3 2021 being
1,920,311 and 2,095,935 million mined BCMs respectfully

·      Mill throughput and processing rates for Q4 2021 were broadly in
line with previous quarters (taking into account the impact of the wet season
on Q3 2021), with recoveries improving versus Q3 2021 levels to 92.38%, to
give a full year recovery rate of 92.26%

Post period updates for Yanfolila, Mali

Since September 2021, the operation of Yanfolila has underperformed primarily
due to our mining contractor excavator fleet not meeting contracted mining
rates. The Company has worked with the contractor to set in place mitigation,
including the following:

·      The Company has secured five excavators to be added to the
current fleet, with the first excavator delivered and operating. Two further
excavators are now on site and being assembled to be operational as soon as
practical and the final two are expected to be delivered and operational by
the end of Q1 2022. The current ECOWAS sanctions are not currently expected to
impact this timeline

·      Reinforcing our contract miners maintenance team, with the goal
to improve overall mining fleet performance

·      Implementing several other operational workstreams at site with
the key focus to improve: production performance and predictability; mill
grade feed profile; and departmental cost disciple, which includes:

o  Drill and blast improvements to minimise metal loss and dilution via
increased technical controls and optimised fragmentation

o  Cost and efficiency drive, including optimisation of mill grinding media,
review on all discretionary spending and regular departmental cost reviews

o  Planning and tactical improvements:  Full review of mine planning and
geological control and ore management programmes at a technical and execution
level

o  Processing and sampling improvements:  Independent reviews completed and
improvement programmes in progress

o  Mining contractor review: Additional equipment maintenance capacity on
site as noted above in Q1 2022

o  Security upgrades: In progress at Yanfolila and Kouroussa

o  Increased community engagement and investment in long term sustainable
initiatives in line with the WGC RGMPs

Furthermore, during Q1 2022 a longer than normal plant maintenance programme
has been planned, primarily to replace mill bearings, during which other plant
maintenance is being scheduled with the objective of reducing downtime later
in the year.

Given the above build-up of excavator availability and plant shut down, we
anticipate that quarterly production for Q1 2022 to be lower versus the
remaining quarters of 2022, with a ramp up in Q2 2022 and subsequent quarters
driven primarily by the five additional excavators becoming increasingly
operational, coupled with operational improvement strategies as detailed above
gaining traction.

Lastly, in relation to the underground mining potential at Yanfolila, we are
currently finalising our analysis of the optimal development route to then put
into our future mine plans. We are increasingly encouraged about the viability
of a low capex, low AISC (sub US$1,000 oz), long life, baseload production
profile underground mine at Yanfolila. We will provide more updates once our
analysis is completed.

Kouroussa, Guinea

Post the update on 10 January 2022 detailing the commencement of construction
at Kouroussa, the Company has further progressed the development with key
updates including:

·      Key contracts for power generation and mining are at advanced
stages of discussion and nearing finalisation

·      Groundwork clearing progress is continuing and we remain on
schedule to commence civil works this quarter

·      The scheduled timeline remains on track to achieve first gold
pour by the end of Q2 2023.

Dugbe, Liberia

In Q4 2021, the Company's earn-in partner, Pasofino Gold, released an updated
MRE for the Dugbe Gold Mine in Liberia in Q4 2021, totalling 4.0 Moz,
including 3.4 Moz of Measured and Indicated Resources. Further, during the
quarter, Pasofino announced the completion of a non-brokered private placement
of up to US$5.5 million to finalise the DFS, including the investment by the
ESAN group in Turkey. The DFS remains on track to be completed in Q2 2022.

Drilling and Exploration

In Q4 2021, Company Reserves were updated for Yanfolila, Mali (705,800 oz at
2.57 grams per tonne ("g/t") and included a maiden Reserve for Kouroussa,
Guinea (408,900 oz at 4.38 g/t), with total Company Reserves increasing to
1.12 million oz at 3.03 g/t.

End of the quarter, the Company completed is extensive drilling campaign of
c.68,000 m at Yanfolila, Mali and Kouroussa, Guinea, as did our earn in
partners Pasofino at Dugbe, Liberia.

The 2021 c.68,000 m drilling campaigns assays once all received and analysed,
will feed into the Company's updated 2022 Resources and Reserves statement
scheduled for release in Q2 2022. Forecast exploration spend for 2022 is
detailed below.

Financial Summary:

                                               Unit   YTD 2021  Q4 2021  Q3 2021  Q2 2021  Q1 2021
 Gold sales                                    oz     87,553    18,489   22,255   24,790   22,019
 Avg. gold sale price                          $/oz   $1,788    $1,782   $1,782   $1,802   $1,788
 Operating cash costs                          $'000  $131,532  $32,486  $33,472  $33,986  $31,588
 AISC on gold sold                             $/oz   $1,536    $1,803   $1,520   $1,386   $1,494
 Net (debt) / cash                             $'m    ($25.0)   ($25.0)  ($5.9)   $9.0     $0.5
  Net (debt) / cash inc gold inventory value   $'m    ($21.0)   ($21.0)  ($1.0)   $12.4    $4.9
 Debt repayments                               $'m    $13.3     -        -        $4.7     $8.6

Q4 AISC of US$1,803 per oz was high driven primarily by lower ounces of gold
ounces poured during the quarter, with a full-year 2021 AISC of US$1,536 oz,
in line with revised guidance of US$1,490 - US$1,590 oz

·      Net debt position c.US$25 million as at the end of Q4 2021
(c.US$21 million including gold inventory value)

o  c.US$66 million (CFA38.5bn) loan now drawn from the Company financing
facility provided by Coris Bank, with c.US$20 million (CFA11.2bn) overdraft
facility remaining available

o  c.US$10 million of capital and exploration expenditure outside of AISC
during Q4 2021, including: c.US$7 million at Kouroussa; c.US$2 million on
exploration finalising our 2021 drilling campaigns; and c.US$1 million of
expansion capex relating to Gonka and Sanioumale West pit and haul road
preparations at Yanfolila, Mali.

o  Additionally, the Company reduced working capital by approximately US$10
million in the quarter largely through earlier payments to suppliers

2022 Guidance

Forecasting 2022 production guidance of 87,000 - 97,000 oz of gold, with an
AISC range of US$1,300 - 1,450 per oz of gold, noting the following:

·      The 2022 mine plan has been developed with a lowered average
daily mining volume rate than previous years to reduce the pressure on our
mining contractor who faced challenges meeting the 2021 contracted mining
volume rates

·      As detailed above, Q1 2022 is forecast to be a lower production
quarter versus the remaining quarters of 2022, with a ramp up from Q2 2022
expected, driven primarily by an additional five excavators becoming
increasingly operational during Q1. Furthermore, the Company continues to
implement several operational improvement programmes in 2022, with the overall
goal to provide improved production performance and predictability; mill grade
feed profile; and departmental cost disciple at Yanfolila in order to meet our
2022 guidance forecasts

·      AISC guidance has been set at US$1,300 - 1,450 per oz of gold,
with the prime driver to achieve a lower AISC profile being improved
production at Yanfolila, and improved departmental cost disciple, which is a
key focus area for the onsite teams

·      Exploration spend for 2022 is guided to be lower than spent in
2021 at c.US$2 million. The key focus for the geology team 1H 2022 is to
analyse and incorporate the extensive drilling completed in 2021 into our
updated Company Resources and Reserves statement due in Q2 2022, whilst
assessing potential targets and future exploration programmes. In H2 2022 we
will review our exploration spend in the light of operational and financial
performance

COVID-19

The Company notes that the local region around Yanfolila is currently
experiencing a higher-than-normal rate of COVID-19 infections. The new Omicron
variant has impacted our staff and employees however the medical teams at both
Yanfolila and Kouroussa, supported by our international recognised medical
provider (CCI), have limited any adverse health impacts and minimal
disruptions have been caused to operations.

ESG 2022 summary plans

Key focus of the ESG team for 2022 is to achieve the year three WGC RGMPs
limited assurance audit report, expected to be completed in Q4 2022. Further
details of some key ESG initiatives for 2022 are detailed below.

·      Covid-19: Maintain our diligence and protocols in order to
minimise health risks to our employees, contractors and local communities and
impacts from covid-19 on our operations in general

·      Hummingbird Tree Initiative: Planting of ~10,000 trees from the
Company's locally supported village nursery programmes was completed at
Yanfolila as part of the Company's yearly ~20-hectare rehabilitation programme
and to be maintained into 2022. This programme is also being considered for
implementation at Kouroussa

·      Finalise the Sanioumale East village resettlement plan at
Yanfolila

·      Community programmes: Maintain and continue to improve our
community programmes at Yanfolila and embed similar programmes into Kouroussa
such as: garden markets; poultry farm support; water infrastructure
improvements; honey manufacturing business education; local school education
support amongst others

·      Energy Efficiency: Deliver on low carbon emission initiatives
including a +7 megawatt ("Mw") solar power plant and energy saving waste heat
recovery systems at Kouroussa

·      Dugbe, Liberia: The DFS to include an internationally recognised
and independent high standard Environmental and Social Impact Assessment
("ESIA") study

Restricted share units and deferred shares

Further to the Company's announcement on 27 May 2021, the 2021 restricted
share units awarded to employees and Non-executive Director Deferred Share
Awards have now been issued as previously disclosed, with the exception of the
restricted share units being issued to other employees being a lower figure of
4,533,582 rather than the original 4,871,094.

Additionally, 1,565,000 share options issued in 2010, with exercise price of
£0.22 lapsed during 2021, which include 1,125,000 for Daniel Betts and 67,500
for Thomas Hill.

Notes to Editors:

Hummingbird Resources (AIM: HUM) is a multi-asset, multi-jurisdiction gold
production, development and exploration Company, a member of the World Gold
Council and a founding member of Single Mine Origin (singlemineorigin.com
(http://www.singlemineorigin.com/) ). The Company currently has two core gold
projects, the operational Yanfolila Gold Mine in Mali, and the Kouroussa
Gold Mine in Guinea, which will more than double current gold production
when in production, scheduled for first gold pour end of Q2 2023. Further, the
Company has a controlling interest in the Dugbe Gold
Project in Liberia that is being developed by Pasofino Gold Limited through
an earn-in agreement. Our vision is to continue to grow our asset base,
producing profitable ounces while placing our Environmental, Social &
Governance ('ESG') policies and practices at the heart of all we do.

For further information, please visit hummingbirdresources.co.uk
(https://www.hummingbirdresources.co.uk/)  or subscribe to our investor
releases via investor email alerts
(https://www.hummingbirdresources.co.uk/investors/regulatory-news-alerts/#subscribe)
 

 Daniel Betts, CEO                  Hummingbird Resources plc  Tel: +44 (0) 20 7409 6660

 Thomas Hill, FD

 Anthony Köcken, COO

 Edward Montgomery, CSO & ESG
 James Spinney                      Strand Hanson Limited      Tel: +44 (0) 20 7409 3494

 Ritchie Balmer                     Nominated Adviser

 James Asensio                      Canaccord Genuity Limited  Tel: +44 (0) 20 7523 8000

 Thomas Diehl                       Broker
 Bobby Morse                        Buchanan                   Tel:  +44 (0) 20 7466 5000

 Ariadna Peretz                     Financial PR/IR            Email: HUM@buchanan.uk.com (mailto:HUM@buchanan.uk.com)

 James Husband

 

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact
rns@lseg.com (mailto:rns@lseg.com)
 or visit
www.rns.com (http://www.rns.com/)
.

RNS may use your IP address to confirm compliance with the terms and conditions, to analyse how you engage with the information contained in this communication, and to share such analysis on an anonymised basis with others as part of our commercial services. For further information about how RNS and the London Stock Exchange use the personal data you provide us, please see our
Privacy Policy (https://www.lseg.com/privacy-and-cookie-policy)
.   END  UPDBMMLTMTAJBJT