For best results when printing this announcement, please click on link below:
http://newsfile.refinitiv.com/getnewsfile/v1/story?guid=urn:newsml:reuters.com:20240704:nGNE82lxSc&default-theme=true
Kenmare Resources plc
(“Kenmare” or “the Company”)
4 July 2024
Project Update
Kenmare Resources plc (LSE:KMR, ISE:KMR), one of the leading global producers
of titanium minerals and zircon, which operates the Moma Titanium Minerals
Mine (the "Mine" or "Moma") in northern Mozambique, is pleased to provide a
project update for the Wet Concentrator Plant (“WCP”) A upgrade and
transition to the Nataka ore zone.
Statement from Michael Carvill, Managing Director:
“The Board has approved the final part of the Definitive Feasibility Study
for the WCP A upgrade and transition to the Nataka ore zone, relating to the
infrastructure. The total capital costs for the project remain in line with
previous estimates. On-going detailed engineering and scheduling work has
resulted in lower expected capital expenditure in 2024.
Works are advancing well for the upgrade, with the fabrication of the two new
dredges and the upfront desliming circuit making encouraging progress. Nataka
represents over 70% of Moma’s Mineral Resources and unlocking this ore zone
secures production for decades to come, whilst maintaining Kenmare’s first
quartile position on the industry revenue to cost curve.”
Overview
Nataka is the largest ore zone in Kenmare’s portfolio, containing 6.4
billion tonnes of Moma’s 9.0 billion tonnes of Mineral Resources. WCP A is
the largest of Kenmare’s three mining plants, representing approximately 50%
of total mining capacity. WCP A will begin its transition from its current
mine path in Namalope, where it has mined for 17 years, to Nataka in late
2025. This is the only move of this kind that is required in WCP A’s
economic life, which is expected to extend beyond the existing mine plan that
runs to 2045.
Kenmare’s Board approved the initial three parts of WCP A’s Definitive
Feasibility Study (“DFS”) in 2023, while the DFS relating to
infrastructure was completed in Q2 2024. The Infrastructure DFS addresses four
key elements:
* Electricity supply – including a new 110kV overhead powerline from the
Mineral Separation Plant (“MSP”) to the Nataka substation
* Pumping and piping – allowing for transportation of slimes from WCP A to
the primary densification paddock and ultimately the Tailings Storage Facility
(“TSF”), as well as distributing water
* Heavy Mineral Concentrate (“HMC”) handling – including a new terrace
for stacking and storage of HMC. HMC will be pumped from WCP A to the
infrastructure terrace by pipeline and in the early years of operation,
transported to the MSP by road
* Other infrastructure – including the new Nataka electricity substation,
maintenance workshops for heavy mobile equipment, and offices
Capital costs
The total capital cost for the upgrade and transition of WCP A is expected to
be in line with previous estimates and totals $341 million. This includes $106
million in respect of WCP A infrastructure (including both base capital
expenditure of $88 million and $18 million of the overall project
contingency). Kenmare plans to fund the WCP A upgrade and transition from cash
flow and existing debt facilities.
The breakdown of the total capital costs remains similar to Kenmare’s
previous guidance, including contingency of $52 million. The breakdown is as
follows:
Component Cost estimate in July 2024 Cost estimate in December 2023
New dredges 65 65
Other WCP A upgrades (e.g. upfront desliming circuit) 100 100
TSF 36 36
Nataka infrastructure 88 98
Contingency 52 (1) 42
Total 341 341
1. A portion of contingency has been committed.
Kenmare began incurring capital expenditure for the WCP A upgrade and
transition in 2023, beginning with orders for key long lead time items, such
as the two new higher capacity dredges. The capital expenditure incurred to
date has been lower than expected and further detailed engineering and
scheduling work has deferred $38 million of expected capital expenditure from
2024 into subsequent years, in line with the expected mine plan.
Kenmare continues to expect to begin the transition of WCP A to the Nataka ore
zone in late 2025.
Capital expenditure schedule ($m) 2023 2024 2025 2026 2027 2028 Total
July 2024 11 141 128 40 4 17 341
December 2023 11 179 121 20 10 - 341
Project status update
The WCP A upgrade and transition project consists of three key components, in
addition to the infrastructure included in the WCP A Infrastructure DFS, and
their current status is as follows:
1. New more powerful dredges – the fabrication of two new higher capacity
dredges is progressing with Kenmare’s contractor in the Netherlands
2. Upfront desliming circuit to more effectively manage slimes at Nataka –
the fabrication of pontoons and surge bin (parts of the desliming circuit) is
underway and the earth works for the starter pond are also in progress
3. Introduction of a TSF to replace the current paddock system – the
detailed design of the TSF is progressing well and on schedule for completion
in Q3 2024. Construction is expected to begin in Q4 2024
Other capital projects
Work continues on both the DFS for the WCP B upgrade, which is expected to
increase WCP B’s capacity by over 40%; and the Pre-Feasibility Study for the
Congolone ore zone, which is a potential future growth opportunity for the
Company. Kenmare expects to provide an update on both studies with the
Company’s Interim Results, which will be announced on 14 August 2024.
The Company will announce its Q2 and H1 2024 Production Update on 17 July
2024.
For further information, please contact:
Kenmare Resources plc
Jeremy Dibb / Katharine Sutton / Michael Starke
Investor Relations
ir@kenmareresources.com
Tel: +353 1 671 0411
Mob: + 353 87 943 0367 / + 353 87 663 0875
Murray (PR advisor)
Paul O’Kane
pokane@murraygroup.ie
Tel: +353 1 498 0300
Mob: +353 86 609 0221
About Kenmare Resources
Kenmare Resources plc is one of the world's largest producers of mineral sands
products. Listed on the London Stock Exchange and the Euronext Dublin, Kenmare
operates the Moma Titanium Minerals Mine in Mozambique. Moma's production
accounts for approximately 7% of global titanium feedstocks and the Company
supplies to customers operating in more than 15 countries. Kenmare produces
raw materials that are ultimately consumed in everyday quality-of-life items
such as paints, plastics and ceramic tiles.
All monetary amounts refer to United States dollars unless otherwise
indicated.
Forward Looking Statements
This announcement contains some forward-looking statements that represent
Kenmare's expectations for its business, based on current expectations about
future events, which by their nature involve risks and uncertainties. Kenmare
believes that its expectations and assumptions with respect to these
forward-looking statements are reasonable. However, because they involve risk
and uncertainty, which are in some cases beyond Kenmare's control, actual
results or performance may differ materially from those expressed or implied
by such forward-looking information