Picture of Kenmare Resources logo

KMR Kenmare Resources News Story

0.000.00%
gb flag iconLast trade - 00:00
Basic MaterialsSpeculativeSmall CapValue Trap

Q4 2024 Production Report and 2025 Guidance

For best results when printing this announcement, please click on link below:
https://newsfile.refinitiv.com/getnewsfile/v1/story?guid=urn:newsml:reuters.com:20250120:nGNE3WkH0h&default-theme=true


Kenmare Resources plc 
(“Kenmare” or the “Company” or “the Group”)

20 January 2025

Q4 2024 Production Report and 2025 Guidance

Kenmare Resources plc (LSE:KMR, ISE:KMR), one of the leading global producers
of titanium minerals and zircon, which operates the Moma Titanium Minerals
Mine (the "Mine" or "Moma") in northern Mozambique, is pleased to provide a
trading update for the full year 2024 and the fourth quarter ending 31
December 2024 (“Q4 2024”) and production and operating cost guidance for
2025.

Statement from Tom Hickey, Managing Director:

“Kenmare delivered a strong finish to 2024, exceeding the midpoint of our
production guidance for ilmenite and the upper end of the guidance ranges for
all other products. We also passed the milestone of two million hours worked
without a Lost Time Injury in late December. These achievements are testament
to the hard work and commitment of our team at site during a challenging
period.

In 2024 we paid $48 million in dividends and invested over $140 million in
capital programmes, primarily for the upgrade and transition of our largest
mining plant to Nataka. Our balance sheet remains strong and we expect our
full year 2024 dividend to be towards the upper end of our payout policy of
20-40% of profit after tax.”

Overview
* Lost Time Injury Frequency Rate (“LTIFR”) of 0.06 per 200,000 hours
worked to 31 December 2024 (31 December 2023: 0.15), with zero Lost Time
Injuries (“LTIs”) in Q4 2024
* Kenmare exceeded the midpoint of production guidance for ilmenite and the
upper end of the guidance range for primary zircon, rutile and concentrates in
2024
* Heavy Mineral Concentrate (“HMC”) production of 1,446,600 tonnes in
2024, broadly in line with 2023, due to record excavated ore tonnes offset by
lower ore grades
* Ilmenite production of 1,008,900 tonnes in 2024, a 2% increase year-on-year
(“YoY”), due to higher ilmenite content in the HMC and stronger recoveries
* Shipments of finished products of 1,088,600 tonnes in 2024, up 4% YoY.
Shipments in H2 2024 were significantly stronger than in H1, as expected, with
611,000 tonnes shipped
* Interim 2024 dividend of USc15.0 per share paid in October 2024 and full
year 2024 dividend expected to be at the upper end of the payout ratio of
20-40% of profit after tax
* Net debt of $24.8 million (2023: $20.7 million net cash) due to on-going
development capital expenditure
* Demand for all of Kenmare’s products remained robust in 2024 and sales are
expected to continue to exceed production in 2025
* Ilmenite production guidance for 2025 is 930,000 to 1,050,000 tonnes
* Expenditure on development projects and studies is expected to be
approximately $155 million in 2025. The Wet Concentrator Plant (“WCP”) A
project remains on budget, with a total cost estimate of $341 million
* The process for the renewal of Moma’s Implementation Agreement (“IA”)
continues to progress and the Government of Mozambique has confirmed that
Kenmare’s rights under the IA remain in place until the renewal is completed
* As previously announced, James McCullough has been appointed as Chief
Financial Officer and he will join Kenmare on 1 May 2025
Operations update

Operational results for the Moma Mine in Q4 and full year 2024 were as
follows:

                    Q4 2024     vs Q4 2023  vs Q3 2024  2024        vs 2023   
                    tonnes      % change    % change    tonnes      % change  
 Excavated ore (1)  10,333,000  11%         -7%         41,248,000  7%        
 Grade (1)          4.96%       3%          31%         4.17%       -5%       
 Production                                                                   
 HMC produced       432,300     8%          22%         1,446,600   0%        
 HMC processed      442,100     11%         24%         1,449,200   0%        
 Ilmenite           307,400     14%         19%         1,008,900   2%        
 Primary zircon     14,700      5%          1%          50,500      -1%       
 Rutile             2,900       38%         0%          9,800       17%       
 Concentrates (2)   11,200      7%          -17%        46,100      1%        
 Shipments          308,300     -5%         2%          1,088,600   4%        
1. Excavated ore and grade prior to any floor losses.
2. Concentrates include secondary zircon, mineral sands concentrate and a new
concentrates product.
Kenmare passed the milestone of two million hours worked without an LTI in
early January 2025. There were no LTIs in Q4. Two LTIs were recorded in the 12
months to 31 December 2024, compared to five in 2023, resulting in an improved
rolling 12-month LTIFR of 0.06 per 200,000 hours worked (31 December 2023:
0.15).

HMC production in Q4 2024 was 432,300 tonnes, an 8% increase YoY. This was due
to a 11% increase in excavated ore tonnes as a result of excellent throughputs
and operating time at WCP B and C, and a 3% increase in ore grades, however
partially offset by increased mining losses, as a result of higher slimes at
WCP A. This issue is expected to be resolved by the new WCP A upfront
desliming circuit, which is currently under construction. As expected, Q4 was
the strongest quarter of the year for ore grades, up 31% compared to Q3 2024,
due to WCP B mining an area of higher grade material.

HMC production in 2024 was 1,446,600 tonnes, broadly in line with 2023,
although with significantly improved production in H2 (787,600 tonnes versus
659,000 tonnes in H1 2024). 2024 represents a new annual record for excavated
ore volumes, which were up 7% YoY. This partially offset the 5% decrease in
ore grades YoY, as WCP A approaches the end of its mine path in Namalope.

Kenmare delivered significantly stronger production of all finished products
in Q4 2024 compared to Q4 2023. Ilmenite production was up 14% to 307,400
tonnes, benefitting from the 11% increase in HMC processed and higher ilmenite
content in the HMC. Primary zircon production was up 5% due to the higher HMC
processed partially offset by a build-up in intermediate stocks. Rutile
production was up 38% YoY, with December representing a new monthly record for
rutile production. Improvements through 2024 were due to circuit upgrades,
which have enabled increased recoveries. Concentrates production was up 7%,
with the increased HMC processed partially offset by the previously mentioned
stock build and stronger recovery to primary products.

Kenmare exceeded the midpoint of production guidance for ilmenite in 2024 and
the upper end of the guidance range for primary zircon, rutile and
concentrates. Total production of finished products was 1,115,300 tonnes, up
2% YoY (2023: 1,091,500 tonnes), despite flat HMC processed.

Ilmenite production was 1,008,900 tonnes in 2024, up 2% YoY, benefitting from
improved recoveries and higher ilmenite content in the HMC processed. Primary
zircon production was down 1% YoY due to a build-up of non-magnetic
intermediate stock in Q4, expected to be drawn down in 2025. Rutile production
was up 17% YoY due to improved recoveries following circuit improvements and
concentrates production was up 1%, benefitting from the production of a new
concentrates product that was sold on a trial basis in Q3. This product will
be sold on a commercial basis in 2025.

Q4 2024 was the strongest quarter of the year for shipments, with volumes of
308,300 tonnes. Shipments were down 5% YoY, although H2 2024 (611,000 tonnes)
was significantly stronger than H1 2024 (477,600 tonnes). Shipment volumes in
Q4 2024 comprised 261,300 tonnes of ilmenite, 30,300 tonnes of primary zircon,
3,700 tonnes of rutile and 13,000 tonnes of concentrates.

The product mix was higher value in H2 than H1, with 42,800 tonnes of primary
zircon shipped in H2 (H1: 8,800 tonnes) and 7,400 tonnes of rutile (H1: 0).
The product mix in H1 2024 was impacted by two high value zircon shipments
being delayed from June into July and no rutile was shipped in the first half
of the year.

Total shipments in 2024 were 1,088,600 tonnes, up 4% compared to 2023,
supported by increased production of finished products and benefitting from
consistently strong customer demand. Shipments during the year comprised
989,000 tonnes of ilmenite, 51,600 tonnes of primary zircon, 7,400 tonnes of
rutile and 40,600 tonnes of concentrates.

Closing stock of HMC at the end of 2024 was 14,100 tonnes, compared with
16,700 tonnes at the start of the year, due to a small amount of HMC in stock
being drawn down for processing during the year. Closing stock of finished
products at the end of 2024 was 287,200 tonnes, compared with 259,100 tonnes
at the end of 2023. Due to strong production in H2 2024 and high levels of
finished product stock at the end of the first half, Kenmare had higher than
usual levels of finished product stock at year-end. Shipments are expected to
exceed production in 2025 and drive a reduction in finished product stock
levels.

Capital projects update

WCP A upgrade and transition to Nataka

The WCP A project remains on budget, with upgrade works continuing to advance,
thereby progressively derisking the project. At the end of Q4, 75% of the
project budget had been committed, in line with expectations. WCP A is
currently mining an area 750 metres from the staging pond, which is on track
with the schedule for it to connect with the new module in Q3 2025.

The fabrication of the two new dredges continues to progress with the project
contractor in the Netherlands. The dredges are expected to be launched into
the water at the contractor’s docks over the coming weeks, with all
fabrication anticipated to complete in Q2. They will then be transported to
Moma by sea for commissioning in Q3.

All of the principal components of the new module for WCP A, which
incorporates 42 pontoons, a surge bin, an upfront desliming circuit, major
steelwork and screens, are now on site and construction is advancing to
schedule, with commissioning expected in Q3.

Construction of the Tailings Storage Facility has been impacted by permitting
delays associated with the Mozambique general election. Construction commenced
in mid-January, with commissioning scheduled for Q4. Management of slimes in
the interim period of Q3 has been accommodated within the mine plan.

Selective Mining Operation (“SMO”)

The introduction of a new small-scale dredge-mining and concentrating
operation, or SMO, will enable mining in peripheral areas of Mineral Resources
in the Pilivili high dunes and Namalope Flats at the Mine. These areas are low
in slimes, above average grade and not accessible by the larger WCPs or
existing dry mining operations that are limited by groundwater levels, which
prevent the extraction of ore below the water table. The SMO is expected to
produce approximately 50,000 tonnes of HMC per annum.

The SMO construction process is well advanced at Moma, with commissioning of
the first module of the plant expected to commence in late January and the
second part in February. The capital expenditure is anticipated to be less
than $6 million and the project remains on budget.

The introduction of the SMO supports Kenmare’s ability to deliver ilmenite
production in 2025 that is broadly in line with 2023 and 2024 levels, despite
the planned downtime for WCP A required to facilitate the replacement of the
dredges and the upgrade of the plant.

Finance and corporate update

Dividends and year-end cash and debt

On 11 October 2024, Kenmare paid its interim 2024 dividend of USc15.0 per
share, representing a total interim distribution of $13.4 million. The Company
expects total dividends in respect of 2024 to be at the upper end of
Kenmare’s dividend policy payout ratio of 20-40% of profit after tax.

Cash and cash equivalents were $56.9 million at year-end (2023: $71.0
million). Gross bank loans, including accrued interest, were $80.4 million
(2023: $48.8 million) and lease liabilities were $1.3 million (2023: $1.5
million). As a result, the Company had net debt of $24.8 million at year-end
(2023: $20.7 million net cash). Supported by on-going cash generation,
available current assets and its Revolving Credit Facility, Kenmare remains
well-capitalised to fund the WCP A capital project and its dividend programme.

Implementation Agreement

Kenmare has agreed in principle to certain modifications to the applicable
investment regime in connection with the renewal of rights under the IA and
the renewal and modifications are awaiting consideration at Ministerial level.
In the meantime, the Ministry of Industry and Commerce has provided
confirmation that Kenmare’s existing rights and benefits remain in full
force and effect pending conclusion of the process.

The original renewal date was 21 December 2024. However, due to delays
associated with the recent Mozambique general election, the renewal, along
with others of a similar nature, will be matters to be dealt with by the
incoming Government.

A further update on the renewal of the IA will be provided in due course.

Appointment of Chief Financial Officer

As announced on 20 December 2024, James McCullough has been appointed as
Kenmare’s Chief Financial Officer and he will join the Company on 1 May
2025. James brings extensive mining, strategic and financial experience to
Kenmare, having served for 14 years with Rio Tinto Plc, most recently as
General Manager - Group Strategy. James succeeds Tom Hickey, who was
previously Finance Director before being appointed as Managing Director in
August 2024.

Market update

Kenmare’s shipments increased by 4% in 2024, reflecting consistently strong
customer demand for Kenmare’s products. However, the average price received
decreased compared to 2023, as expected, due to increased supply outweighing
demand. Despite this, the Company believes the fundamentals for its products
are strong, due primarily to medium- and long-term supply constraints within
the titanium feedstocks industry and the favourable characteristics of its
products. Kenmare’s average price received was stronger in H2 than H1 due to
a higher value product mix in the second half as a result of two zircon
shipments being delayed from June to July.

Global demand for titanium feedstocks reached a record high during the year,
supported by strong demand from emerging markets such as South America and
Asia (excluding China). The titanium metal market also continued to consume
significant quantities of titanium feedstocks due to its growing production.

However, supply grew more strongly, with increased exports of Heavy Mineral
Concentrate to China from Mozambique, Sierra Leone, and Indonesia. This new
supply also more than compensated for the reduced production from mines
nearing the end of their lives.

Kenmare is well-positioned due to the flexible nature of its ilmenite product
suite and its ability to sell its products into multiple market segments. The
Company is a preferred supplier to the beneficiation market due to the high
quality, low impurity nature of its ilmenite, which achieves a premium in the
market. Most new supply is not suitable for this market segment, which
supports demand for Kenmare’s ilmenite, and it is growing faster than the
global titanium feedstocks market.

Pigment production in China continued at high levels in 2024, despite proposed
anti-dumping duties from the European Commission. While these regulations
reduced Chinese exports to Europe, China increased its exports to other
regions, such as other Asian countries, largely offsetting this impact.
Pigment production in Europe increased significantly in 2024, as producers
responded to the reduced availability of Chinese pigment. Both trends also
supported demand for Kenmare’s ilmenite during the year.

2024 was a challenging year for the global zircon market, impacting
Kenmare’s received prices. Although there was a partial recovery in Q1,
underlying demand remained weak due to softness in China’s construction
sector.  

2025 guidance

2025 guidance for production and operating costs is as follows:

                                           Unit    2025 Guidance      2024 Actual  
 Production                                                                        
 Ilmenite                                  tonnes  930,000-1,050,000  1,008,900    
 Primary zircon                            tonnes  47,500-54,000      50,500       
 Rutile                                    tonnes  9,000-10,000       9,800        
 Concentrates (1)                          tonnes  63,000-69,000      46,100       
 Costs                                                                             
 Total cash operating costs                $m      228-252            N/R (2)      
 Cash costs per tonne of finished product  $/t     206-228            N/R (2)      
1. Concentrates include secondary zircon, mineral sands concentrate and 25,000
tonnes of a new concentrates product
2. To be reported in full year financial statements.
Ilmenite production in 2025 is expected to be between 930,000 and 1,050,000
tonnes, with HMC production at a consistent level throughout the year. Grades
are expected to be higher in H1 than H2, however excavated ore volumes are
expected to increase in H2, largely due to the commissioning of the new higher
capacity dredges at WCP A, offsetting the weaker grade. Finished product
production is expected to be boosted by the addition of 25,000 tonnes of a new
concentrates product, which is included in concentrates production guidance.

Shipments are forecast to exceed production in 2025, supported by high levels
of finished product stock.

Total cash operating costs for 2024 are anticipated to be towards the upper
end of guidance ($219-243 million). Full details of 2024 costs will be
provided with the 2024 Preliminary Results. Total cash operating costs in 2025
are anticipated to be broadly in line with 2024 at $228-252 million.

Expenditure on development projects and studies is expected to be
approximately $155 million in 2025, with $150 million relating to the WCP A
project. Kenmare guided in July 2024 that capital expenditure on the WCP A
project would be $128 million in 2025. The Company incurred less capital
expenditure than expected in 2024 so a portion of this was deferred to 2025.
The WCP A project remains on budget, with a total cost estimate of $341
million.

Improvement projects are expected to cost $7 million in 2025 and relate to a
number of initiatives, including studies relating to a potential Enterprise
Resource Planning system and upgrades to the Mineral Separation Plant.

Sustaining capital costs in 2025 are expected to be approximately $38 million.
Sustaining capital is typically approximately $30 million per annum but it is
elevated in 2025 due to the planned five-yearly dry dock of the Peg, one of
Kenmare’s transshipment vessels, and the anticipated purchase of a second
Selective Mining Operation.

Notice of 2024 Preliminary Results

Kenmare plans to release its 2024 Preliminary Results on Wednesday, 26 March
2025.

For further information, please contact:

Kenmare Resources plc
Jeremy Dibb / Katharine Sutton
Investor Relations
ir@kenmareresources.com
Tel: +353 1 671 0411
Mob: +353 87 943 0367 / +353 87 663 0875

Murray (PR advisor)

Paul O’Kane
pokane@murraygroup.ie
Tel: +353 1 498 0300
Mob: +353 86 609 0221

About Kenmare Resources

Kenmare Resources plc is one of the world's largest producers of mineral sands
products. Listed on the London Stock Exchange and the Euronext Dublin, Kenmare
operates the Moma Titanium Minerals Mine in Mozambique. Moma's production
accounts for approximately 7% of global titanium feedstocks and the Company
supplies to customers operating in more than 15 countries. Kenmare produces
raw materials that are ultimately consumed in everyday quality-of life items
such as paints, plastics and ceramic tiles.

All monetary amounts refer to United States dollars unless otherwise
indicated.

Forward Looking Statements

This announcement contains some forward-looking statements that represent
Kenmare's expectations for its business, based on current expectations about
future events, which by their nature involve risks and uncertainties. Kenmare
believes that its expectations and assumptions with respect to these
forward-looking statements are reasonable. However, because they involve risk
and uncertainty, which are in some cases beyond Kenmare's control, actual
results or performance may differ materially from those expressed or implied
by such forward-looking information

Recent news on Kenmare Resources

See all news