For best results when printing this announcement, please click on link below:
https://newsfile.refinitiv.com/getnewsfile/v1/story?guid=urn:newsml:reuters.com:20251015:nGNE7PHvKm&default-theme=true
This announcement contains inside information.
Kenmare Resources plc
(“Kenmare” or “the Company” or “the Group”)
15 October 2025
Q3 2025 Production Report
Kenmare Resources plc (LSE:KMR, ISE:KMR), one of the leading global producers
of titanium minerals and zircon, which operates the Moma Titanium Minerals
Mine (the "Mine" or "Moma") in northern Mozambique, is pleased to provide a
trading update for the quarter ending 30 September 2025 (“Q3 2025”).
Statement from Tom Hickey, Managing Director:
“Q3 was an important quarter for the Wet Concentrator Plant (WCP) A upgrade
project, with commissioning of the new dredges and new feed preparation module
commencing. The upgraded plant is on track to achieve its nameplate capacity
by the end of 2025.
We continue to expect to achieve our 2025 production and cost guidance,
subject to the ramp up of WCP A progressing to schedule. Ilmenite production
is now anticipated to be towards the lower end of the guidance range at
930,000-960,000 tonnes, which is due primarily to the upgrade work starting
later in Q3 than expected.
Global market conditions remain challenging and one of Kenmare’s customers
has indicated that it will be unable to take its contracted volumes in Q4.
Besides this, demand for our products remains in line with expectations, with
strong, high-value zircon sales volumes expected in Q4.”
Q3 2025 overview
* Improved Lost Time Injury Frequency Rate (“LTIFR”) of 0.02 per 200,000
hours worked for the 12 months to 30 September 2025 (30 September 2024: 0.06)
– Wet Concentrator Plant (“WCP”) A Projects team remains Lost Time
Injury (“LTI”)-free since the project’s commencement
* Kenmare continues to expect to achieve 2025 production and cost guidance,
although ilmenite production is expected to be towards the lower end of the
guidance range at 930,000 to 960,000 tonnes
* Heavy Mineral Concentrate (“HMC”) production of 298,400 tonnes in Q3
2025, down 16% year-on-year (“YoY”), due primarily to lower excavated ore
volumes related to WCP A’s production pause to allow upgrade work to take
place
* Ilmenite production of 209,000 tonnes in Q3 2025, down 19% YoY, and primary
zircon production of 12,300 tonnes, down 16% YoY, due to a 21% decrease in HMC
processed offset by processing of intermediate stockpiles
* Total shipments of finished products of 227,400 tonnes, down 25% YoY, due to
reduced shipping capacity because the Peg transshipment vessel was in dry dock
during Q3 but returned to Moma in late September
* Work on hiring a third transshipment vessel has been deferred due to reduced
short-term demand, following a customer in financial distress signalling that
it will be unable to take contracted volumes, but remains under consideration
for 2026
* Commissioning of WCP A is underway, following upgrade work that was
undertaken in Q3, in preparation for mining in the large Nataka ore zone –
the capital cost for the projects remains at $341 million
* Pricing for Kenmare’s products has continued to decline during the
quarter, as expected, as the market continues to be over-supplied, however
demand for Kenmare’s products was stable in Q3
* Discussions with the Government are continuing regarding the extension of
Moma’s Implementation Agreement (“IA”) - Kenmare remains focused on
bringing these discussions to a satisfactory conclusion
Operations update
Production from the Moma Mine in Q3 2025 was as follows:
Q3 2025 Q3 2024 Q3 2024 Q2 2025 Q2 2025
tonnes tonnes % variance tonnes % variance
Excavated ore (1) 8,979,000 11,089,000 -19% 9,119,000 -2%
Grade (1) 4.04% 3.80% 6% 4.45% -9%
Production
HMC production 298,400 355,400 -16% 358,300 -17%
HMC processed 282,800 356,000 -21% 360,900 -22%
Ilmenite 209,000 257,400 -19% 245,400 -15%
Primary zircon 12,300 14,600 -16% 13,100 -6%
Rutile 1,800 2,900 -38% 2,300 -22%
Concentrates (2) 21,300 13,500 58% 10,400 105%
Shipments 227,400 302,700 -25% 181,800 25%
1. Excavated ore tonnage and grade prior to any floor losses.
2. Concentrates include secondary zircon, mineral sands concentrate and a new
concentrates product called ZrTi.
Kenmare’s rolling 12-month LTIFR to 30 September 2025 was 0.02 per 200,000
hours worked (30 September 2024: 0.06), with one LTI incurred in mid-July.
Since then, the Moma team has achieved two million hours worked without an LTI
and the WCP A Projects team remains LTI-free since the project’s
commencement.
Sadly, a fatal incident involving a police officer occurred at Moma in late
September 2025, as previously announced. The incident appears to have been
motivated by theft, with the electrical cable that feeds the pump station
stolen. Kenmare continues to support an investigation by the Police of the
Republic of Mozambique and has increased security provision at Moma to allow
security personnel to work in pairs, where necessary.
Kenmare continues to expect to achieve 2025 production and cost guidance,
subject to the ramp up of WCP A progressing to schedule. However, ilmenite
production is now expected to be towards the lower end of its guidance range
at 930,000 to 960,000 tonnes. This is due primarily to the commencement of the
production pause at WCP A to allow the upgrade work to take place starting
later in Q3 than expected and consequent lower HMC production. Zircon
production is not expected to be impacted due to the drawdown of intermediate
stockpiles and higher recoveries.
HMC production was 298,400 tonnes in Q3 2025, a 16% decrease YoY, due
primarily to a 19% decrease in excavated ore volumes, related to the scheduled
production pause at WCP A, but benefitting from a 6% increase in ore grades.
Additionally, mine recoveries were impacted by the WCP A project and increased
oversize material in the feed at WCP B. The downtime at WCP A was partly
offset by increased production from Selective Mining Operation (SMO) 1, which
is now operating at nameplate capacity.
Ilmenite production was 209,000 tonnes, down 19% YoY, primarily due to a 21%
decrease in HMC processed, and benefitting from the processing of intermediate
stockpiles. Primary zircon production was 12,300 tonnes, down 16% YoY, also
due to decreased HMC processed and benefitting from the drawdown of
intermediate stockpiles, which contained a higher proportion of zircon than
ilmenite. Rutile production was down 38% YoY to 1,800 tonnes, due to reduced
HMC processed and lower recoveries. Concentrates production was 21,300 tonnes,
up 58% YoY, benefitting from the first commercial shipment of ZrTi, which is a
tailings product so only recognised as production when shipped.
Total shipments in Q3 2025 were 227,400 tonnes, including a high-value zircon
and rutile shipment that was delayed from Q2 and shipped in early Q3.
Shipments were down 25% YoY due to Moma operating at 50% shipping capacity.
This was because of the temporary absence of one of Kenmare’s two
transshipment vessels, the Peg, which was undergoing maintenance work in its
five-yearly dry dock, and returned in late September. Shipments benefitted
from Kenmare’s other transshipment vessel, the Bronagh J, delivering a
strong performance. Shipments in Q3 2025 comprised 206,900 tonnes of ilmenite,
7,000 tonnes of primary zircon, 3,700 tonnes of rutile and 9,800 tonnes of
concentrates, principally comprising a ZrTi shipment.
In early September one of Kenmare’s customers announced that its corporate
group had initiated a restructuring or sales process. Consequently, a total
contracted volume of 65,000 tonnes of ilmenite, which was scheduled to be
shipped in H2 2025, is unlikely to be taken by the customer. Kenmare is
looking to place this volume into the market, but sales have not yet been
agreed. If the tonnage is not shipped in 2025, total shipments for the year
will be broadly in line with production.
Kenmare had been exploring an opportunity to rent a third transshipment
vessel, which would have the objective of supplementing shipment capacity over
the coming months. Due to the reduced short-term demand, the hiring of a third
transshipment vessel has been deferred, but it remains under consideration for
2026.
Closing stock of HMC at the end of Q3 2025 was 32,500 tonnes, compared to
16,900 tonnes at the end of Q2 2025, with the increase due to the reprocessing
of intermediate stockpiles in the quarter instead of HMC. HMC is expected to
be drawn down in Q4 2025. Closing stock of finished products at the end of Q3
2025 was 317,400 tonnes, compared to 300,100 tonnes at the end of Q2 2025, due
to production exceeding shipments in Q3 as a result of the lower shipping
capacity.
Capital projects update
WCP A upgrade project
During Q3 2025, significant work was undertaken to upgrade Kenmare’s largest
mining plant, WCP A, ahead of its transition to the Nataka ore zone. Nataka is
the largest ore zone in Moma’s portfolio, representing approximately 70% of
its Mineral Resources, and WCP A’s transition to this area is essential to
securing Kenmare’s production for decades to come. WCP A will mine in Nataka
for the remainder of its economic life, which is expected to exceed 20 years.
Several key milestones were achieved in relation to the WCP A upgrade project
in Q3 2025. In July, the two new, high-capacity dredges were safely landed on
the beach at Moma and transported by road to the staging pond. Assembly of the
new feed preparation module was completed and during a scheduled production
pause, WCP A’s existing dredges and feed preparation module were detached
from the plant, and the new dredges and new feed preparation module were
connected in their place. This process was completed safely and within the
expected timeframe and commissioning began on 2 October.
The plant will progressively ramp up production during Q4, with its nameplate
capacity of 3,500 tonnes per hour expected to be achieved by the end of 2025.
WCP A will complete its mine path in Namalope in Q2 2026 and will begin its
transition to Nataka from late Q2 2026, which is expected to take
approximately 18 months.
The capital cost estimate of the WCP A upgrade project and transition to
Nataka remains at $341 million, including a new Tailings Storage Facility and
infrastructure in Nataka. By the end of 2025, all of the core capital (80% of
the total) is expected to have been successfully incurred and deployed, and
the project is anticipated to be largely de-risked.
Photographs of the WCP A upgrade work can be viewed at
www.kenmareresources.com/media/image-library/#projects.
Corporate update
Implementation Agreement
The IA governs the terms under which Kenmare conducts its mineral processing
and export activities. Although the IA’s original expiry date was 21
December 2024, the Ministry of Industry and Commerce provided confirmation
that Kenmare’s existing rights and benefits remain in full force and effect
pending conclusion of the extension process. Mining operations at Moma are
conducted under a separate regulatory framework, which is not impacted in any
way by the IA process.
Moma’s IA continues to be a key focus, with the prolonged renewal process
remaining a concern. Kenmare’s Managing Director, Tom Hickey, met with the
Minister for Mineral Resources and Energy in Q3 2025, following his meeting
with the President of Mozambique in Q2. Kenmare continues to engage with the
Government of Mozambique, while reserving the right to safeguard its
contractual entitlements, up to and including arbitration, if an agreement
cannot be reached.
Market update
Demand for Kenmare’s products was stable in Q3 2025, although globally,
demand for mineral sands products softened. Prices for all products weakened
compared to Q2 2025 due to supply outweighing demand.
Weaker global demand for titanium minerals reflected softer underlying end
markets, such as housing and construction, and this continues to weigh on
titanium dioxide pigment consumption. Pigment production rates in China were
lower in the summer months, while several pigment plants outside of China
curtailed or suspended output in response to weak market conditions.
Weak market conditions have affected one of Kenmare’s customers whose
corporate group has entered a restructuring and sales process. The customer
has indicated that it will not take delivery of contracted shipment volumes in
H2 2025 and therefore Kenmare is looking to redirect some product sales into
the market, with increased risk around pricing and volume. In consequence of
this customer’s restructuring and sales process, approximately $9.3 million
of invoices for shipments made by Kenmare in Q3 remain unpaid. Kenmare retains
title to all material pending payment and is pursuing all avenues to obtain
payment in respect of these invoices as well as to preserve its rights and
remedies under the contract for both non-payment and loss of contracted
volumes.
Elevated pigment inventories across the pigment supply chain led to pigment
producers reducing production, limiting demand for titanium feedstocks,
particularly in China. Pigment inventories in China gradually decreased
throughout the summer months and consequently Chinese pigment production and
prices have increased in recent weeks after inventories normalised. Demand for
titanium sponge, which is used to make titanium metal, remained relatively
stable throughout the quarter.
Supply of titanium feedstocks continues to exceed demand, negatively impacting
market pricing and putting pressure on producers. Domestic Chinese ilmenite
production and imports of concentrates remain the largest sources of new
supply. Several major producers are understood to be moderating production,
however there is less visibility on the response from the small-scale
concentrates producers.
The zircon market remained subdued in Q3 2025, with limited recovery in
end-market demand. In China, increased supply of lower-quality zircon
contained in concentrates, combined with a greater willingness among some
customers to accept these products, has negatively impacted prices for zircon.
However, demand for Kenmare’s high-grade zircon remained stable in China and
Europe and the Company continues to expect to sell all of its 2025 zircon
production and to finish the year with low zircon inventories.
Private investor webinar via Investor Meet Company
Kenmare will host a webinar for private investors via Investor Meet Company at
2:00pm UK time on 16 October 2025.
Questions can be submitted before the event via the Investor Meet Company
dashboard until 9:00am UK time on 15 October 2025 or at any time during the
live presentation.
Investors can sign up to Investor Meet Company for free and register for the
Kenmare webinar at:
https://www.investormeetcompany.com/kenmare-resources-plc/register-investor
Investors who already follow Kenmare on the Investor Meet Company platform
will automatically be invited.
For further information, please contact:
Kenmare Resources plc
Katharine Sutton
Investor Relations
ir@kenmareresources.com
Tel: +353 1 671 0411
Mob: +353 87 663 0875
Murray (PR advisor)
Paul O’Kane
pokane@murraygroup.ie
Tel: +353 1 498 0300
Mob: +353 86 609 0221
About Kenmare Resources
Kenmare Resources plc is one of the world's largest producers of titanium
minerals. Listed on the London Stock Exchange and Euronext Dublin, Kenmare
operates the Moma Titanium Minerals Mine in Mozambique. Moma's production
accounts for approximately 6% of global titanium feedstocks and the Company
supplies to customers operating in more than 15 countries. Kenmare produces
raw materials that are ultimately consumed in everyday quality-of life items
such as paints, plastics and ceramic tiles.
All monetary amounts refer to United States dollars unless otherwise
indicated.
Forward Looking Statements
This announcement contains some forward-looking statements that represent
Kenmare's expectations for its business, based on current expectations about
future events, which by their nature involve risks and uncertainties. Kenmare
believes that its expectations and assumptions with respect to these
forward-looking statements are reasonable. However, because they involve risk
and uncertainty, which are in some cases beyond Kenmare's control, actual
results or performance may differ materially from those expressed or implied
by such forward-looking information