Picture of Metals Exploration logo

MTL Metals Exploration News Story

0.000.00%
gb flag iconLast trade - 00:00
Basic MaterialsHighly SpeculativeMid CapNeutral

Metals Exploration - Quarterly Update to 31 December 2025

RNS Number : 6129Q

Metals Exploration PLC

28 January 2026

 

METALS EXPLORATION PLC

 

Quarterly Update to 31 December 2025

 

Metals Exploration plc (AIM: MTL) ("Metals Exploration", the "Company" or the "Group"), a gold production, development and exploration company with assets in the Philippines and Nicaragua, is pleased to announce its unaudited quarterly results for Q4 2025 (the "Quarter").

 

Finance

·      Record FY2025 positive free cash flow of US$115.3 million (FY2024: US$96.7 million).

·      Record FY2025 gold revenue of US$208.4 million (FY2024: US$191.1 million).

·      Q4 2025 positive pre-tax free cash flow of US$40 million (Q3 2025: US$4.5 million).

·      Q4 2025 gold revenue of US$63.9 million (Q3 2025: US$25.5 million).

·      Q4 2025 gold sales of 16,009 ounces ("oz") sold at an average realised gold price of US$3,995 per ounce ("/oz") (Q3 2025: 8,833 oz at an average US$2,889 /oz).

 

Runruno - Mining Operations

·      Q4 2025 mining production of ore and waste was 2.79 million tonnes ("Mt") (Q3 2025: 1.99 Mt), with a total of 710 thousand tonnes ("Kt") of ore mined in Q4 2025 (Q3 2025: 404 Kt).

 

Runruno - Processing Operations

·      Q4 2025 gold production of 15,156 oz (Q3 2025: 9,145 oz) recovered from 538 Kt at a head grade of 1.04 grammes per tonne ("g/t") (Q3 2025: 324 Kt at a head grade of 1.06 g/t).

·      Q4 2025 all-in-sustaining-cost ("AISC") of US$1,584 /oz (Q3 2025: US$1,923 /oz).

·      Q4 2025 gold recovery of 84.1% (Q3 2025: 83.3%).

 

FY2025/FY2026 Production Guidance

·      FY2025 gold production of 65,287 ounces was at the lower end of the revised FY2025 lower guidance forecast at an AISC of US$1,368 /oz, which was above the upper FY2025 guidance forecast range of US$1,275 /oz due to the lower ounces sold.

·      FY2026 gold production from Runruno forecast: 50,000 - 60,000 ounces.

·      FY2026 AISC forecast for Runruno gold production: US$1,400 - US$1,650 /oz.

·      No guidance is provided for the La India gold project which remains on track to commence gold production in Q4 2026.

Development - La India, Nicaragua

·      Overall construction continues to be within the revised budget and ahead of schedule at 33% complete.

·      Process plant foundations, general infrastructure and bulk earthworks are all progressing ahead of schedule.

·      Stockpiling of ore has begun.

Exploration - Dupax, Philippines

·      Drill programme continuing - limited drilling conducted during the Quarter with no near term production opportunity discovered to date.

Darren Bowden, CEO of Metals Exploration, commented:

 

"I am pleased to report a strong end to FY2025, culminating in record gold revenue for the year of US$208.4 million and record free cash flow of US$115.3 million. This record-breaking year was supported by the continued robust operational performance at Runruno, as well as the favourable gold price environment.

                                                                                                                      

"In Nicaragua, we have seen excellent momentum in the development of the La India Gold Project towards production, which remains on track for first gold in Q4 2026. Overall construction is ahead of schedule at 33%, and I look forward to providing further updates on progress throughout 2026. With an annual production target of 145,000 oz of gold, La India will serve to replace cash flow from Runruno as mining operations cease there.

 

"At Runruno, we achieved FY2025 gold production of 65,287 oz, within the revised FY2025 lower guidance forecast of 65,000 oz. This revision came as a result of production delays due to the Q3 2025 BIOX cyanide contamination issue, which was subsequently resolved, and the impact of Super-typhoon Uwan in Q4 2025, where mains power was restored earlier than forecasted. Our production guidance for FY2026 at Runruno is 50,000 - 60,000 oz due to the mine approaching the end of its life with the mine plan scheduling lower grade material with slightly lower recovery performance, with AISC forecasted at US$1,400 - US$1,650 /oz, and we look forward to continuing to capitalise on the supportive gold price environment.

 

"Drilling at Dupax to date has indicated that the target ore zone is deeper than predicted. As a result, we have concluded that an economic resource at Dupax will not be able to be defined in time for Runruno's ore processing operations to be extended via the processing of Dupax ore. Accordingly, we are considering other options to repurpose the Runruno plant and will keep shareholders updated with any developments.

 

"Safety is at the heart of what we do, and I am pleased to report that the Company now has in excess of 2 million man-hours worked in the Philippines without an LTI. In Nicaragua, we have not recorded an LTI since Metals Exploration acquired La India.

 

"We finished FY2025 in a very strong position, with record revenue and free cash flow. The Company is debt free, and is targeting FY2026 gold production of 50,000 - 60,000 oz from Runruno. With La India due to start production in Q4 2026, I am optimistic about the Company's year ahead and look forward to updating shareholders with our progress."

 

 

 

Runruno Production and Finance Summary

 

Runruno Project ReportQuarterQuarterFY 2025FY 2024
FY 2025ActualActualActualActual
PHYSICALSUnitsQ4 2025Q4 202412 Months12 Months
Mining
Ore MinedTonnes709,920283,8622,142,1872,055,871
Waste MinedTonnes2,077,8872,418,5108,557,3649,293,694
Total MinedTonnes2,787,8072,702,37210,699,55111,349,565
Au Grade Minedg/tonne1.021.501.281.46
Strip Ratio2.918.503.924.40
Processing
Ore MilledTonnes537,824529,7911,902,7022,150,429
Au Gradeg/tonne1.041.171.211.34
S2 Grade%1.171.301.191.35
Au Milled (contained)Ounces18,01919,93473,84492,752
Recovery%84.194.588.490.5
Au Recovered/PouredOunces15,15618,82965,28783,897
Sales
Au SoldOunces16,00919,14466,08282,676
Au PriceUS$/oz3,9952,4813,1542,312
FINANCIALS (Unaudited)
Revenue
Gold Sales(US$000's)63,94947,490208,413191,150
Operating Costs - Summary
Mining(US$000's)4,7944,86819,50618,879
Processing(US$000's)7,8828,13932,69234,919
G&A(US$000's)2,7832,56913,08611,649
Total Operating Costs(US$000's)15,45915,57665,28465,447
Excise Duty(US$000's)2,5721,9138,3657,668
UK/Philippine G&A(US$000's)3,2545,24411,10413,768
Total Direct Production Costs(US$000's)21,28522,73384,75386,882
Net Cash Income(US$000's)42,66424,757123,661104,267
Total Capital Costs(US$000's)2,6562,2638,3917,518
Total non-cash costs(US$000's)15,76913,110111,06269,794
Pre-tax Free Cashflow(US$000's)40,00822,494115,27096,749
Cash Cost / oz Sold - C1US$/oz1,126797979785
Cash Cost / oz Sold - AISC1US$/oz1,5841,2891,3681,135
  Note 1: AISC includes all UK Corporate costs. It excludes costs directly related to the Nicaraguan assets.   Runruno Operations   In November 2025, processing operations were impacted by the loss of mains power to site due to damage to the National power grid caused by Super-typhoon Uwan. Production was paused for approximately seven days while repairs to the power grid were conducted in various parts of the Nueva Viscaya province. Back-up generators ensured no loss of BIOX bacteria. Mining operations were also suspended for two days. Mains power was restored to the site, with processing operations able to recommence, earlier than forecasted.   Annual gold production was 65,287 oz, at the lower end of the revised guidance of 65,000-70,000 oz, having been impacted by both production delays due to Super-typhoon Uwan and the Q3 2025 BIOX cyanide contamination issue.   Finance   FY2025 operations at Runruno produced record gold sales of US$208.4 million (FY2024: US$191.1 million) resulting in a record US$115.3 million pre-tax free cash flow (FY2024: US$96.7 million).   Q4 2025 recorded gold sales of US$63.9 million (Q3 2025: US$25.5 million), at an average realised gold price of US$3,995 /oz (Q3 2025: average gold price of US$2,889 /oz); producing positive free cash flow of US$40.0 million (Q3 2025: US$4.5 million).   The Company's cash holdings at 31 December 2025 were US$41.6 million (30 September 2025: US$28.3 million). The Group has no debt.   Mining Operations   Mining production of ore and waste for Q4 2025 was slightly below management's forecast at 2.79 Mt (Q3 2025: 1.99 Mt). During Q4 2025, a total of 710 Kt of ore was mined (Q3 2025: 404 Kt). The Company continues to forecast that mining operations will cease in Q3-2026 due to depletion of ore but processing will continue as detailed below.   Process Plant   Gold produced during Q4 2025 was 15,156 oz (Q3 2025: 9,145 oz) from ore milled in Q4 2025 of 538 Kt (Q3 2025: 324 Kt), at an AISC of US$1,584 /oz (Q3 2025: US$1,923 /oz). Head grade was lower than forecast at 1.04 g/t (Q3 2025: 1.06 g/t).   Average gold recovery rate for Q4 2025 was 84.1% (Q3 2025: 83.3%). Average recoveries for FY2026 are expected to be approximately 82% due to a lower average head grade and continued processing of lower recovery material. Gold processing activities are expected to cease in late-2026 or early 2027.   Residual Storage Impoundment ("RSI")   During the Quarter, the Runruno mine received higher than normal rainfall as numerous typhoons passed over/close to the mine site. Notwithstanding the high rainfall, the RSI dam water freeboard remains well above design minimum levels. Construction of the RSI final in-rock spillway continues.   Development   La India Gold Project   Progress of construction works at the La India mine site in Nicaragua has progressed very satisfactorily during the Quarter with overall construction remaining within the revised budget and slightly ahead of schedule, being 33% complete, being fully funded to date from the Runruno gold mine cash flow. The Company's ambition to produce gold during Q4 2026 remains intact. Highlights for the Quarter include:   ·      No lost time injuries ("LTI"). ·      The processing plant throughput capacity design has been upgraded to 1.8 million tonnes per annum ("mTpa") from 1.4 mTpa, in anticipation of future growth opportunities. ·      The on-site laboratory building is nearing completion and is scheduled to be operational from February 2026. ·      Bulk earthworks for the processing plant and technical services area are complete. Pre-stripping of the open pit mining area is on schedule, at approximately 19% complete. ·      The run-of-mine ("ROM") pad is complete, and the first ore has commenced stockpiling. ·      The tailings storage facility access is complete. ·      Construction of key infrastructure is progressing ahead of schedule; with several camp accommodation buildings completed and operational. ·      Exploration, geo-technical and infill resource extension drilling for the Quarter totalled 4,676 metres.   Exploration - Philippines   Dupax Project   Limited drilling was undertaken during Q4 2025 due to the impact of Super-typhoon Uwan combined with the Company managing local community access issues. Drilling to date has indicated that the target ore zone is significantly deeper than predicted, leading to the Company to conclude that an economic resource at Dupax will not be able to be defined within a time period such that the Runruno process plant can be converted to process Dupax ore. As a result, other options to re-purpose the Runruno plant are being considered.   Drilling results from this programme will be announced in due course.     Abra Project   Drill programmes on the Abra tenement remain on hold while the National Commission for Indigenous Peoples ('NCIP') further advances its consultation activities with the potentially impacted local communities. The Company's expectation remains that drilling in the Abra project area will commence later in FY2026.   ESG   Occupational Health & Safety   The Company completed the Quarter without an LTI. The Company now has in excess of 2 million man-hours worked in the Philippines without an LTI. The Company has recorded no LTI's at its operations in Nicaragua since commencing operations in country.   Environment & Compliance   Compliance matters continue to be successfully monitored, and all operations in both the Philippines and Nicaragua are compliant with no outstanding material issues.   Community & Government Relations   The Company continues to receive strong support from local communities and government agencies in both the Philippines and Nicaragua.       This announcement contains inside information for the purposes of Article 7 of EU Regulation 596/2014, which forms part of United Kingdom domestic law by virtue of the European Union (Withdrawal) Act 2018 (as amended). Upon the publication of this announcement, this inside information is now considered to be in the public domain.   END          For further information, please contact or visit:  
Metals Exploration PLC
Via BlytheRay+44 (0) 207 138 3204
Nominated & Financial Adviser:STRAND HANSON LIMITED
James Spinney, James Dance, Rob Patrick+44 (0) 207 409 3494
Joint Broker:HANNAM & PARTNERS
Matt Hasson, Franck Nganou+44 (0) 207907 8500
Joint Broker:PANMURE LIBERUM
Amrit Mahbubani, Scott Mathieson, Zak Wadud+44 (0) 203 100 2112
Public Relations:BLYTHERAY
Megan Ray, Said Izagaren+44 (0) 207 138 3204
metalsexploration@blytheray.com
  Web:                      www.metalsexploration.com X:                            @MTLexploration LinkedIn:               Metals Exploration   Competent Person's Statement Mr Maxwell Donald Tuesley, BSc (Hons) Economic Geology, a member of the Australasian Institute of Mining and Metallurgy (No 111470  and employee of the Company, has compiled, read and approved the technical disclosure in relation to the projects in this regulatory announcement in accordance with the AIM Rules - Note for Mining and Oil & Gas Companies.   Forward Looking Statements Certain statements relating to the estimated or expected future production, operating results, cash flows and costs and financial condition of Metals Explorations, planned work at the Company's projects and the expected results of such work contained herein are forward-looking statementswhich are based on current expectations, estimates and projections about the potential returns of the Group, industry and markets in which the Group operates in, the Directors' beliefs and assumptions made by the Directors. Forward-looking statements are statements that are not historical facts and are generally, but not always, identified by words such as the following: "expects", "plans", "anticipates", "forecasts", "believes", "intends", "estimates", "projects", "assumes", "potential" or variations of such words and similar expressions. Forward-looking statements also include reference to events or conditions that will, would, may, could or should occur. Information concerning exploration results and mineral reserve and resource estimates may also be deemed to be forward-looking statements, as it constitutes a prediction of what might be found to be present when and if a project is actually developed.   These statements are not guarantees of future performance or the ability to identify and consummate investments and involve certain risks, uncertainties and assumptions that are difficult to predict, qualify or quantify. Among the factors that could cause actual results or projections to differ materially include, without limitation: uncertainties related to raising sufficient financing to fund the planned work in a timely manner and on acceptable terms; changes in planned work resulting from logistical, technical or other factors; the possibility that results of work will not fulfil projections/expectations and realize the perceived potential of the Company's projects; uncertainties involved in the interpretation of drilling results and other tests and the estimation of gold reserves and resources; risk of accidents, equipment breakdowns and labour disputes or other unanticipated difficulties or interruptions; the possibility of environmental issues at the Company's projects; the possibility of cost overruns or unanticipated expenses in work programs; the need to obtain permits and comply with environmental laws and regulations and other government requirements; fluctuations in the price of gold and other risks and uncertainties.   The Company expressly disclaims any obligation or undertaking to disseminate any updates or revisions to any forward looking statements contained herein to reflect any change in the Group's expectations with regard thereto or any change in events, conditions or circumstances on which any such statements are based unless required to do so by applicable law or the AIM Rules. This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com. RNS may use your IP address to confirm compliance with the terms and conditions, to analyse how you engage with the information contained in this communication, and to share such analysis on an anonymised basis with others as part of our commercial services. For further information about how RNS and the London Stock Exchange use the personal data you provide us, please see our Privacy Policy.   END     UPDDDLFLQFLFBBX

Recent news on Metals Exploration

See all news