For best results when printing this announcement, please click on link below:
https://newsfile.refinitiv.com/getnewsfile/v1/story?guid=urn:newsml:reuters.com:20260128:nRSb6129Qa&default-theme=true
RNS Number : 6129Q Metals Exploration PLC 28 January 2026
METALS EXPLORATION PLC
Quarterly Update to 31 December 2025
Metals Exploration plc (AIM: MTL) ("Metals Exploration", the "Company" or the
"Group"), a gold production, development and exploration company with assets
in the Philippines and Nicaragua, is pleased to announce its unaudited
quarterly results for Q4 2025 (the "Quarter").
Finance
· Record FY2025 positive free cash flow of US$115.3 million
(FY2024: US$96.7 million).
· Record FY2025 gold revenue of US$208.4 million (FY2024: US$191.1
million).
· Q4 2025 positive pre-tax free cash flow of US$40 million (Q3
2025: US$4.5 million).
· Q4 2025 gold revenue of US$63.9 million (Q3 2025: US$25.5
million).
· Q4 2025 gold sales of 16,009 ounces ("oz") sold at an average
realised gold price of US$3,995 per ounce ("/oz") (Q3 2025: 8,833 oz at an
average US$2,889 /oz).
Runruno - Mining Operations
· Q4 2025 mining production of ore and waste was 2.79 million
tonnes ("Mt") (Q3 2025: 1.99 Mt), with a total of 710 thousand tonnes ("Kt")
of ore mined in Q4 2025 (Q3 2025: 404 Kt).
Runruno - Processing Operations
· Q4 2025 gold production of 15,156 oz (Q3 2025: 9,145 oz)
recovered from 538 Kt at a head grade of 1.04 grammes per tonne ("g/t") (Q3
2025: 324 Kt at a head grade of 1.06 g/t).
· Q4 2025 all-in-sustaining-cost ("AISC") of US$1,584 /oz (Q3 2025:
US$1,923 /oz).
· Q4 2025 gold recovery of 84.1% (Q3 2025: 83.3%).
FY2025/FY2026 Production Guidance
· FY2025 gold production of 65,287 ounces was at the lower end of
the revised FY2025 lower guidance forecast at an AISC of US$1,368 /oz, which
was above the upper FY2025 guidance forecast range of US$1,275 /oz due to the
lower ounces sold.
· FY2026 gold production from Runruno forecast: 50,000 - 60,000
ounces.
· FY2026 AISC forecast for Runruno gold production: US$1,400 -
US$1,650 /oz.
· No guidance is provided for the La India gold project which
remains on track to commence gold production in Q4 2026.
Development - La India, Nicaragua
· Overall construction continues to be within the revised budget
and ahead of schedule at 33% complete.
· Process plant foundations, general infrastructure and bulk
earthworks are all progressing ahead of schedule.
· Stockpiling of ore has begun.
Exploration - Dupax, Philippines
· Drill programme continuing - limited drilling conducted during
the Quarter with no near term production opportunity discovered to date.
Darren Bowden, CEO of Metals Exploration, commented:
"I am pleased to report a strong end to FY2025, culminating in record gold
revenue for the year of US$208.4 million and record free cash flow of US$115.3
million. This record-breaking year was supported by the continued robust
operational performance at Runruno, as well as the favourable gold price
environment.
"In Nicaragua, we have seen excellent momentum in the development of the La
India Gold Project towards production, which remains on track for first gold
in Q4 2026. Overall construction is ahead of schedule at 33%, and I look
forward to providing further updates on progress throughout 2026. With an
annual production target of 145,000 oz of gold, La India will serve to replace
cash flow from Runruno as mining operations cease there.
"At Runruno, we achieved FY2025 gold production of 65,287 oz, within the
revised FY2025 lower guidance forecast of 65,000 oz. This revision came as a
result of production delays due to the Q3 2025 BIOX cyanide contamination
issue, which was subsequently resolved, and the impact of Super-typhoon Uwan
in Q4 2025, where mains power was restored earlier than forecasted. Our
production guidance for FY2026 at Runruno is 50,000 - 60,000 oz due to the
mine approaching the end of its life with the mine plan scheduling lower grade
material with slightly lower recovery performance, with AISC forecasted at
US$1,400 - US$1,650 /oz, and we look forward to continuing to capitalise on
the supportive gold price environment.
"Drilling at Dupax to date has indicated that the target ore zone is deeper
than predicted. As a result, we have concluded that an economic resource at
Dupax will not be able to be defined in time for Runruno's ore processing
operations to be extended via the processing of Dupax ore. Accordingly, we are
considering other options to repurpose the Runruno plant and will keep
shareholders updated with any developments.
"Safety is at the heart of what we do, and I am pleased to report that the
Company now has in excess of 2 million man-hours worked in the Philippines
without an LTI. In Nicaragua, we have not recorded an LTI since Metals
Exploration acquired La India.
"We finished FY2025 in a very strong position, with record revenue and free
cash flow. The Company is debt free, and is targeting FY2026 gold production
of 50,000 - 60,000 oz from Runruno. With La India due to start production in
Q4 2026, I am optimistic about the Company's year ahead and look forward to
updating shareholders with our progress."
Runruno Production and Finance Summary
Runruno Project Report Quarter Quarter FY 2025 FY 2024
FY 2025 Actual Actual Actual Actual
PHYSICALS Units Q4 2025 Q4 2024 12 Months 12 Months
Mining
Ore Mined Tonnes 709,920 283,862 2,142,187 2,055,871
Waste Mined Tonnes 2,077,887 2,418,510 8,557,364 9,293,694
Total Mined Tonnes 2,787,807 2,702,372 10,699,551 11,349,565
Au Grade Mined g/tonne 1.02 1.50 1.28 1.46
Strip Ratio 2.91 8.50 3.92 4.40
Processing
Ore Milled Tonnes 537,824 529,791 1,902,702 2,150,429
Au Grade g/tonne 1.04 1.17 1.21 1.34
S(2) Grade % 1.17 1.30 1.19 1.35
Au Milled (contained) Ounces 18,019 19,934 73,844 92,752
Recovery % 84.1 94.5 88.4 90.5
Au Recovered/Poured Ounces 15,156 18,829 65,287 83,897
Sales
Au Sold Ounces 16,009 19,144 66,082 82,676
Au Price US$/oz 3,995 2,481 3,154 2,312
FINANCIALS (Unaudited)
Revenue
Gold Sales (US$000's) 63,949 47,490 208,413 191,150
Operating Costs - Summary
Mining (US$000's) 4,794 4,868 19,506 18,879
Processing (US$000's) 7,882 8,139 32,692 34,919
G&A (US$000's) 2,783 2,569 13,086 11,649
Total Operating Costs (US$000's) 15,459 15,576 65,284 65,447
Excise Duty (US$000's) 2,572 1,913 8,365 7,668
UK/Philippine G&A (US$000's) 3,254 5,244 11,104 13,768
Total Direct Production Costs (US$000's) 21,285 22,733 84,753 86,882
Net Cash Income (US$000's) 42,664 24,757 123,661 104,267
Total Capital Costs (US$000's) 2,656 2,263 8,391 7,518
Total non-cash costs (US$000's) 15,769 13,110 111,062 69,794
Pre-tax Free Cashflow (US$000's) 40,008 22,494 115,270 96,749
Cash Cost / oz Sold - C1 US$/oz 1,126 797 979 785
Cash Cost / oz Sold - AISC(1) US$/oz 1,584 1,289 1,368 1,135
Note 1: AISC includes all UK Corporate costs. It excludes costs directly
related to the Nicaraguan assets.
Runruno Operations
In November 2025, processing operations were impacted by the loss of mains
power to site due to damage to the National power grid caused by Super-typhoon
Uwan. Production was paused for approximately seven days while repairs to the
power grid were conducted in various parts of the Nueva Viscaya province.
Back-up generators ensured no loss of BIOX bacteria. Mining operations were
also suspended for two days. Mains power was restored to the site, with
processing operations able to recommence, earlier than forecasted.
Annual gold production was 65,287 oz, at the lower end of the revised guidance
of 65,000-70,000 oz, having been impacted by both production delays due to
Super-typhoon Uwan and the Q3 2025 BIOX cyanide contamination issue.
Finance
FY2025 operations at Runruno produced record gold sales of US$208.4 million
(FY2024: US$191.1 million) resulting in a record US$115.3 million pre-tax free
cash flow (FY2024: US$96.7 million).
Q4 2025 recorded gold sales of US$63.9 million (Q3 2025: US$25.5 million), at
an average realised gold price of US$3,995 /oz (Q3 2025: average gold price of
US$2,889 /oz); producing positive free cash flow of US$40.0 million (Q3 2025:
US$4.5 million).
The Company's cash holdings at 31 December 2025 were US$41.6 million (30
September 2025: US$28.3 million). The Group has no debt.
Mining Operations
Mining production of ore and waste for Q4 2025 was slightly below management's
forecast at 2.79 Mt (Q3 2025: 1.99 Mt). During Q4 2025, a total of 710 Kt of
ore was mined (Q3 2025: 404 Kt). The Company continues to forecast that mining
operations will cease in Q3-2026 due to depletion of ore but processing will
continue as detailed below.
Process Plant
Gold produced during Q4 2025 was 15,156 oz (Q3 2025: 9,145 oz) from ore milled
in Q4 2025 of 538 Kt (Q3 2025: 324 Kt), at an AISC of US$1,584 /oz (Q3 2025:
US$1,923 /oz). Head grade was lower than forecast at 1.04 g/t (Q3 2025: 1.06
g/t).
Average gold recovery rate for Q4 2025 was 84.1% (Q3 2025: 83.3%). Average
recoveries for FY2026 are expected to be approximately 82% due to a lower
average head grade and continued processing of lower recovery material. Gold
processing activities are expected to cease in late-2026 or early 2027.
Residual Storage Impoundment ("RSI")
During the Quarter, the Runruno mine received higher than normal rainfall as
numerous typhoons passed over/close to the mine site. Notwithstanding the high
rainfall, the RSI dam water freeboard remains well above design minimum
levels. Construction of the RSI final in-rock spillway continues.
Development
La India Gold Project
Progress of construction works at the La India mine site in Nicaragua has
progressed very satisfactorily during the Quarter with overall construction
remaining within the revised budget and slightly ahead of schedule, being 33%
complete, being fully funded to date from the Runruno gold mine cash flow. The
Company's ambition to produce gold during Q4 2026 remains intact. Highlights
for the Quarter include:
· No lost time injuries ("LTI").
· The processing plant throughput capacity design has been upgraded
to 1.8 million tonnes per annum ("mTpa") from 1.4 mTpa, in anticipation of
future growth opportunities.
· The on-site laboratory building is nearing completion and is
scheduled to be operational from February 2026.
· Bulk earthworks for the processing plant and technical services
area are complete. Pre-stripping of the open pit mining area is on schedule,
at approximately 19% complete.
· The run-of-mine ("ROM") pad is complete, and the first ore has
commenced stockpiling.
· The tailings storage facility access is complete.
· Construction of key infrastructure is progressing ahead of
schedule; with several camp accommodation buildings completed and operational.
· Exploration, geo-technical and infill resource extension drilling
for the Quarter totalled 4,676 metres.
Exploration - Philippines
Dupax Project
Limited drilling was undertaken during Q4 2025 due to the impact of
Super-typhoon Uwan combined with the Company managing local community access
issues. Drilling to date has indicated that the target ore zone is
significantly deeper than predicted, leading to the Company to conclude that
an economic resource at Dupax will not be able to be defined within a time
period such that the Runruno process plant can be converted to process Dupax
ore. As a result, other options to re-purpose the Runruno plant are being
considered.
Drilling results from this programme will be announced in due course.
Abra Project
Drill programmes on the Abra tenement remain on hold while the National
Commission for Indigenous Peoples ('NCIP') further advances its consultation
activities with the potentially impacted local communities. The Company's
expectation remains that drilling in the Abra project area will commence later
in FY2026.
ESG
Occupational Health & Safety
The Company completed the Quarter without an LTI. The Company now has in
excess of 2 million man-hours worked in the Philippines without an LTI. The
Company has recorded no LTI's at its operations in Nicaragua since commencing
operations in country.
Environment & Compliance
Compliance matters continue to be successfully monitored, and all operations
in both the Philippines and Nicaragua are compliant with no outstanding
material issues.
Community & Government Relations
The Company continues to receive strong support from local communities and
government agencies in both the Philippines and Nicaragua.
This announcement contains inside information for the purposes of Article 7 of
EU Regulation 596/2014, which forms part of United Kingdom domestic law by
virtue of the European Union (Withdrawal) Act 2018 (as amended). Upon the
publication of this announcement, this inside information is now considered to
be in the public domain.
END
For further information, please contact or visit:
Metals Exploration PLC
Via BlytheRay +44 (0) 207 138 3204
Nominated & Financial Adviser: STRAND HANSON LIMITED
James Spinney, James Dance, Rob Patrick +44 (0) 207 409 3494
Joint Broker: HANNAM & PARTNERS
Matt Hasson, Franck Nganou +44 (0) 207 907 8500
Joint Broker: PANMURE LIBERUM
Amrit Mahbubani, Scott Mathieson, Zak Wadud +44 (0) 203 100 2112
Public Relations: BLYTHERAY
Megan Ray, Said Izagaren +44 (0) 207 138 3204
metalsexploration@blytheray.com
Web: www.metalsexploration.com
(http://www.metalsexploration.com)
X: @MTLexploration
(https://twitter.com/MTLexploration)
LinkedIn: Metals Exploration
(https://www.linkedin.com/company/metals-exploration-plc)
Competent Person's Statement
Mr Maxwell Donald Tuesley, BSc (Hons) Economic Geology, a member of the
Australasian Institute of Mining and Metallurgy (No 111470 and employee of
the Company, has compiled, read and approved the technical disclosure in
relation to the projects in this regulatory announcement in accordance with
the AIM Rules - Note for Mining and Oil & Gas Companies.
Forward Looking Statements
Certain statements relating to the estimated or expected future production,
operating results, cash flows and costs and financial condition of Metals
Explorations, planned work at the Company's projects and the expected results
of such work contained herein are forward-looking statementswhich are based on
current expectations, estimates and projections about the potential returns of
the Group, industry and markets in which the Group operates in, the Directors'
beliefs and assumptions made by the Directors. Forward-looking statements are
statements that are not historical facts and are generally, but not always,
identified by words such as the following: "expects", "plans", "anticipates",
"forecasts", "believes", "intends", "estimates", "projects", "assumes",
"potential" or variations of such words and similar expressions.
Forward-looking statements also include reference to events or conditions that
will, would, may, could or should occur. Information concerning exploration
results and mineral reserve and resource estimates may also be deemed to be
forward-looking statements, as it constitutes a prediction of what might be
found to be present when and if a project is actually developed.
These statements are not guarantees of future performance or the ability to
identify and consummate investments and involve certain risks, uncertainties
and assumptions that are difficult to predict, qualify or quantify. Among the
factors that could cause actual results or projections to differ materially
include, without limitation: uncertainties related to raising sufficient
financing to fund the planned work in a timely manner and on acceptable terms;
changes in planned work resulting from logistical, technical or other factors;
the possibility that results of work will not fulfil projections/expectations
and realize the perceived potential of the Company's projects; uncertainties
involved in the interpretation of drilling results and other tests and the
estimation of gold reserves and resources; risk of accidents, equipment
breakdowns and labour disputes or other unanticipated difficulties or
interruptions; the possibility of environmental issues at the Company's
projects; the possibility of cost overruns or unanticipated expenses in work
programs; the need to obtain permits and comply with environmental laws and
regulations and other government requirements; fluctuations in the price of
gold and other risks and uncertainties.
The Company expressly disclaims any obligation or undertaking to disseminate
any updates or revisions to any forward looking statements contained herein to
reflect any change in the Group's expectations with regard thereto or any
change in events, conditions or circumstances on which any such statements are
based unless required to do so by applicable law or the AIM Rules.
This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact
rns@lseg.com (mailto:rns@lseg.com)
or visit
www.rns.com (http://www.rns.com/)
.
RNS may use your IP address to confirm compliance with the terms and conditions, to analyse how you engage with the information contained in this communication, and to share such analysis on an anonymised basis with others as part of our commercial services. For further information about how RNS and the London Stock Exchange use the personal data you provide us, please see our
Privacy Policy (https://www.lseg.com/privacy-and-cookie-policy)
. END UPDDDLFLQFLFBBX
Copyright 2019 Regulatory News Service, all rights reserved