Brief: Minbos Resources Says Cabinda Phosphate Project Update
Jan 29 (Reuters) - Minbos Resources Ltd MNB.AX :
* CABINDA PHOSPHATE PROJECT UPDATE
* CURRENT PLANT COMPLETION EXPECTED LATE AUGUST 2024 WITH
WET
COMMISSIONING EXPECTED LATE-JULY 2024