TOKYO, April 1 (Reuters) - Mitsui Mining and Smelting Co Ltd
5706.T , Japan's biggest zinc smelter, plans to produce 113,300
tonnes of refined zinc in the first half of the 2022/23
financial year, up 5.6% from a year earlier, it said on Friday.
The first half runs from April to September.
Zinc is used mainly as an anti-corrosive coating while
making galvanised steel.
Following are details of the company's output plan, with
comparisons against planned production in the second half of the
2021/22 financial year and actual production in the first half
of 2021/22.
(Zinc and lead in tonnes, gold and silver in kilograms):
H1 FY22/23 H2 FY21/22 H1 FY21/22
Zinc 113,300 110,800 107,300
Lead 35,400 34,400 34,700
Gold 2,700 3,000 3,100
Silver 94,000 71,100 75,200
(Reporting by Yuka Obayashi
Editing by Mark Potter)