Table: German hard coal power plant reductions

(Latest state of play)
       Oct 7 - The following table lists reductions in scheduled production at German hard
coal-fired power generation plants that have been necessitated by low water levels hampering
barge shipments of feedstock to the sites and logistics bottlenecks across transport systems,
that are now fast-tracking energy supply. urn:newsml:reuters.com:*:nL1N2ZG0L1 urn:newsml:reuters.com:*:nL8N3002HV
    Utility companies have been flagging problems about shallow water under rules of play set by
the power exchange EEX, where they released the information in the ad hoc section and on related
transparency sites, where plant data are presented long-term, reflecting all operational
planning details and incidents.
    The water problems have eased somewhat but could worsen again. urn:newsml:reuters.com:*:nL8N30916L
    New content is marked***
 PLANT NAME      CAPACITY   TIME PERIOD,         OPERATORS  LOCATION      DATE
                 CUT (MW)   DESCRIPTION OF                                ANNOUNCED
                            CURBS                                         
 CURRENT AND                                                              
 PLANNED LOAD                                                             
 DROPS                                                                    
 Heyden 4        875 MW     Oct 23-Nov 23 by up  Uniper     Petershagen   23/8
                            to 875 MW                                     
 GKM             2,200 MW   Message for Sep 21   RWE,       Mannheim      26/8
 Großkraftwerke             saying hard coal     EnBW, MVV                
 Mannheim                   supply affected                               
                            until further                                 
                            notice                                        
 HKW Heilbronn   778 MW     The supply of HKW 7  EnBW       Heilbronn     2/9
 Block 7                    is affected until                             
                            further notice,                               
                            issues in the                                 
                            logistic chain                                
                            cited                                         
                                                                          
 COMPLETED LOAD                                                           
 DROPS WITH                                                               
 REGARD TO                                                                
 RIVER LEVELS                                                             
 Luenen          750 MW     Aug. 28 by 50%, Sep  Trianel    Luenen        26/8
                            3, 4 potential for                            2/9
                            impairments in                                
                            generation due to                             
                            unforeseeable coal                            
                            delays                                        
 GKM             2,200 MW   affected Sep 1       RWE,       Mannheim      2/9
                                                 EnBW, MVV                
 Staudinger 5    510 MW     Irregular during     Uniper     Near Hanau    4/8
                            Aug 4-Sep 7                                   
 Datteln 4       1,100                           Uniper     Datteln       
                            Irregular output                               29/8
                            from Aug 4-Sep 30                             notice
                                                                          reaffirmed
                                                                          on Sep 15
                                                                          
 Heyden 4        875 MW     Aug 29-Sep 3         Uniper     Petershagen   23/8
                            temporary drop by                             
                            up to 325 MW                                  
 Source: https://www.eex-transparency.com/de/news/ad-hoc-ticker
    https://www.eex-transparency.com/power/de/production/availability
 (Reporting by Vera Eckert, editing by Krishna Chandra Eluri)