Greece advances Cyprus power link, grants permits for surveys and cable works
Greece advances Cyprus power link, grants permits for surveys and cable works Nov 6 (Reuters) - Greece has completed the licensing procedures required for survey and cable-laying work linked to the planned Great Sea Interconnector, the country's foreign ministry said on Friday, advancing a long-delayed project opposed by Turkey.
The ministry said Greek authorities had finalized the approval process after French cable maker Nexans NEXS.PA, acting on behalf of project company GSI, applied for permits covering seabed surveys and cable-laying operations.
Foreign Minister George Gerapetritis signed the decision authorising the work following a positive recommendation from the inter-ministerial committee responsible for marine research permits, the ministry said. A research vessel involved in the project subsequently requested and received a NAVTEX notice to mariners for the operations.
The €1.9 billion ($2.1 billion) project, being developed by Greece's power grid operator IPTO ADMr.AT, aims to link the power grids of Greece and Cyprus, and later Israel, through an undersea cable, but progress has been slowed by a dispute between Greece and Turkey over maritime zones in the eastern Mediterranean.
($1 = 0.8930 euros)
(Reporting by Antonis Pothitos; Editing by Louise Heavens)
((antonis.pothitos@thomsonreuters.com; +48 58 769 65 78;))
Recent news on Nexans SA
See all newsGreece advances Cyprus power link, grants permits for surveys and cable works
Brief: Nexans Signs Subcontract For 420 KM Cable System For Greek Interconnection
Rexel raises outlook again as US data-centre demand, European electrification drive growth
Cable capacity emerges as bottleneck for AI data centres, Nexans says
Nexans sales rise on grid, data-centre demand; confirms outlook (updated)