REG-Pan African Resources Plc: Operational Update for the 6 months ended 31 Dec 2020

Pan African Resources PLC

(Incorporated and registered in England and Wales under Companies Act 1985
with registered number 3937466 on 25 February 2000)

Share code on AIM: PAF

Share code on JSE: PAN

ISIN: GB0004300496

ADR ticker code: PAFRY

(Pan African or the Company or the Group)

OPERATIONAL UPDATE FOR THE SIX MONTHS ENDED 31 DECEMBER 2020

Pan African is pleased to provide shareholders with an operational update for
the six months ended 31 December 2020 (Current Reporting Period).

Key Operational Results for the Current Reporting Period
* Industry leading safety performance maintained with improvements in
reportable rates across all Group operations
* Group gold production increased by 5.9% to 98,386oz (2019: 92,941oz)
* Gold production from Barberton Mines for the period was 52,354oz, while
Elikhulu and Evander Mines produced 26,863oz and 19,169oz respectively
* Operations have continued to implement and maintain stringent policies and
protocols to mitigate the effects of the ongoing COVID-19 pandemic on
employees and production
* ESG projects, including the 10MW renewable energy solar photovoltaic plant
at Evander Mines and large-scale agriculture projects in Barberton Mines, are
on track for commissioning in Q3 2021
* Group net debt decreased by 47.3% to US$65.2 million (2019: US$123.7million)
* Pan African is on track to deliver its full year production guidance of
approximately 190,000oz
Pan African CEO Cobus Loots commented:

 “Pan African’s financial results and increase in gold production for the
first six months of the year demonstrates a commendable operational and safety
performance, amidst the challenges of the ongoing COVID-19 pandemic.

Barberton Mine’s gold production of 52,354oz for the Current Reporting
Period deserves recognition and demonstrates the excellent progress that this
flagship asset and its operating team have made in reserve development and
infrastructure optimisation.

Group net debt decreased by 47.3% to US$65.2 million relative to the six
months ended 31 December 2019 (Corresponding Reporting Period),
notwithstanding a record final Rand dividend distribution for the June 2020
financial year, paid in December 2020.

We expect operations at the Evander Mines’ 8 Shaft pillar to deliver a
much-improved performance during the remainder of the 2021 financial year, as
the pillar mining activities gather momentum.

We have now commenced with early preparation work and limited capital
expenditure for the execution phase of the Egoli project. We expect to
finalise the debt funding package within the first quarter of the 2021
calendar year. This organic growth project will contribute considerably to our
future gold production.

The construction of the solar photovoltaic plant at Evander Mines will
commence during the first quarter of the 2021 calendar year, with first power
expected to be generated during the third quarter of the 2021 calendar year.
This plant will be one of the first of its kind in the South African mining
sector and demonstrates our commitment to ESG initiatives. In conjunction with
several other projects, it also underpins the Group’s profitability and
sustainability.

The Group remains on track to produce 190,000 oz of gold for the financial
year ending 30 June 2021, and we are committed to continue creating value for
our stakeholders by positioning Pan African as a sustainable, safe,
high-margin and long-life gold producer. We look forward to presenting our
interim results on 16 February 2021.”

Safety

The Group continued to maintain an industry-leading safety performance with a
focus on new safety initiatives and interventions in its pursuit of a
zero-harm working environment.
* The lost-time injury frequency rate (‘LTIFR’) improved to 1.64 (2019:
1.69) per million man hours
* The reportable injury frequency rate (‘RIFR’) improved to 0.65 (2019:
0.85) per million man hours
* Regrettably, the Group experienced one fatality at Barberton Mines (2019:
Zero) during July 2020. The details of the fatal accident were discussed in
the year end results announcement released on 16 September 2020
* Evander Gold Mine achieved an excellent RIFR of 1.01 (2019:3.71) per million
man hours
* Elikhulu experienced no lost-time and reportable injuries during the past 6
months, contributing to the Group's commendable safety performance
Barberton Mines

Barberton Mines’ production increased by 10.6% to 52,354oz (2019: 47,356oz)
for the Current Reporting Period. Underground production increased by 15.3% to
42,350oz (2019: 36,737oz) and Barberton Tailings Retreatment Plant (BTRP)
production remained stable at 10,004oz (2019: 10,619oz) for the Current
Reporting Period.

The increased production from Barberton Mines is principally due to:
* Improved mining flexibility and available face length with the establishment
of three high grade platforms at the Fairview mine, as well as the extension
of the strike length on the 256 and 257 platforms through active delineation
drilling and systematic development. Fairview mine has now established
concurrent multiple platform availability.
* Improved recoveries at BTRP following the implementation of an oxygen
Carbon-in-leach (CIL) addition project, resulting in the feed sources
achieving a higher recovery than previously estimated.
* The high-grade section at New Consort’s Prince Consort (PC) Shaft 42 Level
being successfully extracted, this orebody remains continuous along the
planned strike length and up-dip to 41 Level.
Elikhulu tailings retreatment plant (Elikhulu)

Gold production from Elikhulu decreased by 8.3% to 26,863oz (2019: 29,301oz)
during the Current Reporting Period, as a result of:
* Lower gold recoveries from the re-mining activities on Kinross Dam 1 and 2
during the Current Reporting Period. As per the mine plan, re-mining
activities have subsequently moved to Kinross Dam 3, and Kinross Dam 3’s
material indicates an improvement in recoveries of approximately 5-10%, albeit
at a lower head grade, relative to Dam 1 and 2 recoveries.
* Plant throughput was constrained by preventative maintenance and improvement
work to sections of the lower Elikhulu tailings storage facility compartment
and the installation of elevated drains. This work will be complete in
February 2021, where after tonnage throughput will again be increased.
Gold production from Elikhulu is expected to increase in the second half of
the 2021 financial year.

Evander Mines’ 8 Shaft Pillar project (8 Shaft Pillar) and surface sources

Production from the Evander Mines operations increased by 17.7% to 19,169oz
(2019: 16,284oz).

Underground production increased by 9.1% to 12,607oz (2019: 11,553oz). The
ramp-up in production of the 8 Shaft Pillar was slower than expected during
the Current Reporting Period, as a result of:
* Difficulties encountered with the initial installation of underground
support pseudo-packs, which have now been resolved following the introduction
of dry tailings and additional grout ranges for filler use.
* Production delays due to fracturing of the shaft lining following the
establishment of the pillar mining in the vicinity of the shaft.
Production from the 8 Shaft Pillar is expected to further improve during the
second half of the 2021 financial year.

The increased production from surface sources of 6,562oz (2019: 4,731oz) also
contributed positively to the Group’s production for the Current Reporting
Period.

Evander Mines Egoli Project (Egoli)

Early works and preparation for the execution phase of the Egoli project has
commenced. Finalisation of the legal agreements for the implementation of
Egoli’s debt funding package is also currently underway. Inception of the
project’s construction is expected in the next month, with phase -1
construction and development expected to be completed in 18 months, followed
by phase-2 development and equipping in the next 18 months thereafter.  First
gold is expected to be produced within 20 months from the project’s
inception.

Group net debt

The Group’s net debt decreased by 47.3% to US$65.2 million (2019: US$123.7
million). Relative to the 30 June 2020 financial year-end, Group net debt
decreased by 14.7% from US$76.4 million to US$65.2 million. The Group’s debt
is denominated in South African Rand and, in US Dollar terms, the decline in
net debt compared to the 30 June 2020 financial year-end, was impacted by the
strengthening of the Rand relative to the US Dollar at a closing rate of
US$/ZAR14.70 compared to US$/ZAR17.33 as at 30 June 2020.

The reduction in the net debt was achieved notwithstanding the cash outflow
associated with the record net Rand dividend payment to shareholders in
December 2020 of US$18.4 million (2019: US$2.9 million).

Interim results for the six months ended 31 December 2020

Pan African will announce its interim results on 16 February 2021.

The information contained in this update is the responsibility of the Pan
African board of directors and has not been reviewed or reported on by the
Group’s external auditors.

Rosebank

22 January 2021

This announcement contains inside information.

For further information on Pan African and its ESG initiatives, please visit
the Company's website at www.panafricanresources.com

 Contact information                                                                                                                                                                                                                                                                                  
 Corporate Office The Firs Office Building 2nd Floor, Office 204 Cnr. Cradock and Biermann Avenues Rosebank, Johannesburg South Africa Office: + 27 (0)11 243 2900 info@paf.co.za  Registered Office Suite 31 Second Floor 107 Cheapside London EC2V 6DN United Kingdom Office: + 44 (0)20 7796 8644  
 Cobus Loots Pan African Resources PLC Chief Executive Officer Office: + 27 (0)11 243 2900                                                                                         Deon Louw Pan African Resources PLC Financial Director Office: + 27 (0)11 243 2900                                 
 Phil Dexter/Jane Kirton St James's Corporate Services Limited Company Secretary Office: + 44 (0)20 7796 8644                                                                      Ross Allister/David McKeown Peel Hunt LLP Nominated Adviser and Joint Broker Office: +44 (0)20 7418 8900           
 Ciska Kloppers Questco Corporate Advisory Proprietary Limited JSE Sponsor Office: + 27 (0)11 011 9200                                                                             Thomas Rider BMO Capital Markets Limited Joint Broker Office: +44 (0)20 7236 1010                                  
 Hethen Hira Pan African Resources PLC Head: Investor Relations Tel: + 27 (0)11 243 2900 E-mail: hhira@paf.co.za                                                                   Website: www.panafricanresources.com                                                                               



Copyright (c) 2021 PR Newswire Association,LLC. All Rights Reserved

Recent news on Pan African Resources

See all news