REG-Pan African Resources Plc: Revised Production Guidance for the year ending 30 June 2023

Pan African Resources PLC (Incorporated and registered in England and Wales under the Companies Act 1985 with registered number 3937466 on 25 February 2000) Share code on AIM: PAF Share code on JSE: PAN ISIN: GB0004300496 ADR ticker code: PAFRY (“Pan African” or the “Company” or the “Group”)              Pan African Resources Funding Company Limited Incorporated in the Republic of South Africa with limited liability Registration number: 2012/021237/06 Alpha code: PARI  

REVISED PRODUCTION GUIDANCE FOR THE YEAR ENDING 30 JUNE 2023, OPERATIONAL
UPDATE AND COMMENCEMENT OF MINTAILS PROJECT CONSTRUCTION

Pan African wishes to provide shareholders and noteholders with revised
production guidance and an operational update for the financial year ending 30
June 2023 (current financial year). It is also pleased to announce the
imminent commencement of the Mintails project’s construction, with site
clearance activities having commenced.  

Group production guidance
* Production guidance for the current financial year reduced to approximately
175,000oz (previously 195,000oz to 205,000oz), primarily as a result of:	*
Challenges related to Eskom generated electricity supply, resulting in a
production loss of approximately 10,000oz of gold
* Slower than anticipated ramp-up of continuous operations at Barberton Mines,
largely addressed as highlighted below
* Lower than expected production from Evander Mines’ underground operations.
	
* Tailings operations at Barberton and Elikhulu are performing in line with
expectations
* Group production guidance for the financial year ending 30 June 2024 of
178,000oz to 190,000oz, with a further production increase in the 2025
financial year, following the Mintails project’s commissioning during the
first half of this financial year.
Safety performance
* The Group regrets to report a fatal accident that occurred as a result of a
fall of ground at Evander Mines in March 2023, following one million fatality
free shifts achieved at the operation prior to the accident
* Despite this tragic setback, the Group expects an improvement in overall
group safety rates for the full year compared to the first half of the current
financial year as a result of the implementation of various initiatives to
further improve its safety performance
Electricity supply
* The Group estimates a production loss of approximately 10,000oz for the
current financial year as a result of issues related to Eskom generated
electricity supply impacting all of the Group’s operations	* In addition to
load curtailment, power outages and surges, difficulties related to
transformers and other Eskom infrastructure contributed to production
disruptions.
	
* As per the announcement released on 15 May 2023, Pan African is aggressively
rolling out its renewable energy plans in order to mitigate the impact of this
challenge.
Barberton Mines
* After a slower than anticipated ramp-up of continuous operations at
Barberton Mines’ Fairview Mine and Sheba operations, the Group is pleased to
report the following improvements in recent months:	* A marked improvement in
Fairview Mine’s production tonnes has been noted. The average tonnes
produced for the preceding three months to April 2023 have increased by more
than 10% to approximately 9,100t per month, compared to an average of 8,100t
per month in the first seven months of the current financial year. Projected
tonnage is expected to further increase in excess of 5% in the remaining two
months of the current financial year
* Optimisation of mining methods at Sheba Mines’ MRC and ZK stopes, to
reduce dilution and the increased availability of trackless mining machinery
(TMM), has improved underground grade and production, with an increase in
monthly production to approximately 8,700t per month during February to April
2023, compared to an average of 6,600t per month for the prior seven months.
Projected tonnage is expected to further increase in excess of 10% in the
remaining two months of the current financial year.
	
* Implementation of the Consort Mine contractor model has progressed slower
than expected, with challenges encountered with the recruitment of skilled
employees adversely affecting production. A full production ramp-up is
expected during June 2023, with the operation returning to profitability
thereafter.
Evander Mines’ underground operations
* Evander Mines’ underground operations have underperformed as a result of
geological challenges due to faulting of the Kimberley Reef at the tail end of
the 8 Shaft Pillar mining area, and a slower than anticipated transition to
full production from 24 Level 	* Infrastructure development for 24 Level
mining is progressing well, with the equipping of the ventilation shaft for
hoisting to relieve the constraints currently being experienced with the
conveyor belt system. This development is expected to be completed by the end
of March 2024.
Mintails project
* The Group has been informed by the South African Department of Mineral
Resources and Energy (DMRE) of the imminent issuing of the Mintails
project’s integrated environmental authorisation 
* Commencement of plant construction is therefore expected in the next month,
and ground clearing activities have commenced, with steady state production
from the commissioned project expected by December 2024.
Financial
* The impact of the lower than expected gold production for the current
financial year has been partially mitigated by the increased year to date rand
gold price received of ZAR1,003,374/kg (2022: ZAR892,431/kg), relative to the
prevailing gold price of approximately ZAR1,220,000/kg
* As a result of the reduced production guidance, the Group’s all-in
sustaining costs (AISC) for the current financial year is now expected to be
between US$1,325/oz and US$1,350/oz, at an average exchange rate of ZAR:US$
17.70
* Net senior debt (comprising secured, interest bearing debt, net of available
cash) is expected to decrease to between US$25 to US$35 million at the end of
the current financial year, relative to US$49.9 million at the end of the six
month period, ended 31 December 2022. This decrease is despite project
expenditure of US$10.4 million already being incurred during the current
financial year on the Mintails project 
* With manageable group debt levels and the Mintails project’s funding
secured, the group is well positioned to continue making cash distributions to
shareholders in the future.
 

 

Pan African CEO Cobus Loots commented:

 

“The safety of our people and contractors remains our number one priority
and we continue to implement a number of programmes to further improve the
safety performance at our operations. We are deeply saddened by the fatal
accident that occurred at Evander Mines as a result of a fall of ground
incident.

 

Whilst we are disappointed with the production performance of our underground
operations for the current financial year, the turnaround at Barberton Mines
is now evident, especially in the past two months, following a longer than
anticipated ramp-up after the implementation of continuous operations at
Fairview Mine and Sheba Mine and implementation of the contractor mining model
at Consort Mine. Barberton Mines’ underground production tonnes have
demonstrated a notable increase during the past two months, with further
increases expected during the remainder of the current financial year.
Implementation of the contractor mining model at Consort Mine is also bearing
fruit and the operation is expected to return to profitability in the short
term.

 

Pan African is leading the way in terms of rolling out renewable energy
projects and reducing our dependency on Eskom. In the coming years, we believe
this strategy will greatly benefit all of our stakeholders.

 

The development of the 24 Level project at Evander Mines is progressing well,
with crews redeployed to the 24 Level area as the 8 Shaft pillar mining nears
completion. Improved mining flexibility, together with the other initiatives
being implemented to ensure that infrastructure availability is optimised,
will ensure sustainable production from this long life underground operation.

 

Ground clearing at the Mintails project has commenced in anticipation of the
senior debt component of the funding package being closed by June 2023.
Commissioning of the plant is expected in the fourth quarter of the 2024
calendar year, which will result in a significant increase in the Group’s
production profile from the 2025 financial year onwards.

 

Despite lower than expected production, the Group is positioned to deliver a
robust financial performance for the current financial year as a result of the
excellent rand gold prices being received and also disciplined operational
cost control.

 

Pan African is committed in its resolve to continued value creation for its
stakeholders by positioning the Group as a sustainable, safe, high-margin and
long-life gold producer with an attractive pipeline of growth projects. We
look forward to presenting our final results in September 2023, which will
include further details on our operational and financial performance, as well
as information on progress being made with our growth projects.”

 

Safety

 

As previously communicated, the Group has implemented initiatives during the
second half of the 2023 financial year to further improve its safety
performance.

 

Barberton Mines has seen a progressive improvement in safety performance for
both lost-time injury frequency rate (LTIFR) and reportable injury frequency
rate (RIFR), compared to the first half of the current financial year.

 

Despite the regrettable fatal accident, we remain confident that the safety
performance at Evander Mines will improve as it continues to implement safety
initiatives to reinforce a zero-tolerance approach towards safety incidents.
Elikhulu operations have seen a slight regression in safety performance during
the current financial year, resulting from two recorded contractor lost-time
injuries.

 

The Group’s forecasted LTIFR and RIFR for the current financial year are
expected to improve from the rates reported for the first half of the year.

 

Group production

 

Group production for the current financial year is expected to be
approximately 175,000oz, split per operation as follows:

 

 Operation                                          Year ended 30 June 2021  Year ended 30 June 2022  Guidance for current financial year  Guidance for 2024 financial year  
 Barberton Mines – Underground total                84,826                   75,738                   64,000                               71,000 - 74,000                   
 BTRP                                               18,239                   19,560                   19,000                               17,000 - 20,000                   
 Elikhulu                                           51,459                   52,220                   50,000                               49,000 - 51,000                   
 Evander Mines – Underground and surface sources    47,253                   58,170                   42,000 *                             41,000 - 45,000 *                 
 Total ounces produced                              201,777                  205,688                  175,000                              178,000 - 190,000                 

* Includes gold equivalent PGM ounces produced by Evander Gold Mines’
Osmiridium circuit

 

 

Royal Sheba Project

 

Mine layout optimisation and scheduling was finalised and requests for
quotations were issued for the initial development and production activities.
Preliminary optimisation work for the life-of-mine (LOM) planning has been
completed at a cut-off grade of 1.7g/t, which translates into an average
mining grade of approximately 3.0g/t and circa 235,000oz of gold recovered
over the life of the project, with the orebody open at depth.

 

DRA Global has finalised the feasibility study for placing a crushing and
milling circuit at the Royal Sheba Mine site, together with the design to
enable slurry pumping from the milling plant at Royal Sheba to the BTRP. The
processing plant’s feasibility study and the project’s financial model is
being updated and reviewed. A phased approach to capital spending, based on
the availability of material to feed the BTRP plant, is also being considered.
This will entail the phased development of the decline, production levels, as
well as the ventilation infrastructure required for initial stoping
operations.

 

First stoped ore is planned in 2025 at 5,000t per month, ramping up to
10,000t, 30,000t and 45,000t per month, every twelve months thereafter in line
with a set lateral and vertical development schedule. A trucking cost
trade-off analysis indicates that the onsite crushing and milling circuit and
pipeline will only be required to be completed once production rates reach
45,000t per month. The internal feasibility study for the complete project is
expected to be completed in the next months.

 

Evander Mines’ 8 Shaft pillar and 24, 25 and 26 Level and Egoli projects

 

The opening up of mining areas on 24 Level continues, which will enable the
phased transfer of crews from the pillar area as mining of the pillar resource
is completed. Two crews are currently mining the 24 Level F-line, with an
additional two crews mining the 24 Level D-line. Construction of phase 2 of
the refrigeration plant for cooling 24 Level is ongoing. The development of
the 24_N1B drive towards 25 Level progressed slower than expected due to
challenging ground conditions. As ground conditions progressively improved,
development rates have now increased and multi-blasting is being considered to
further accelerate development.

 

The equipping of the ventilation shaft to enable hoisting of waste and ore
produced on 24 Level will reduce reliance on the ageing conveyor belt system
and simplify the ore handling process. Installation of pipes for equipping the
ventilation shaft at 17 Level has commenced, with the development of the
winder chamber and shaft station ongoing. Completion of the ventilation
shaft’s equipping is expected by the end of the first quarter of the 2024
calendar year and will provide a hoisting capacity of up to 40,000t per month.
Additional crews have been deployed to the conveyor belts in order to improve
maintenance and breakdown reaction times, which is expected to increase
conveyor belt availability until such time that ore hoisting will commence
through the ventilation shaft.

 

Construction of an additional grout plant (for pseudo-pack support) is
expected to be completed in June 2023. This plant will supply 24 Level and
future mining on 25 and 26 Levels with the required output for mining support.
The use of pseudo-packs in the 8 Shaft pillar area has proven to be effective
in controlling mining subsidence and enabling clean mining practices, and
these benefits will also be replicated through the utilisation of pseudo-packs
as mining support on the 24, 25 and 26 Level projects.  

 

Dewatering of the 3 Decline infrastructure to 19 Level at the 7 Shaft Egoli
project is progressing well. The completion of the dewatering is projected to
take place in the next months, which will enable a more accurate assessment of
potential mining of remnant areas within the Egoli complex.

 

Mintails project progress and funding

 

Progress on the Mintails project and expected milestones include:
* Mineral Resource estimation on the Soweto Cluster 2L16 and 2L24 TSFs was
completed at the end of March 2023, resulting in these TSFs being upgraded to
the indicated Mineral Resource category. The remainder of the Soweto Cluster
TSFs remain classified in the Inferred Mineral Resource category 
* Concept engineering work on the Soweto Cluster TSFs is underway, following
completion of the mineral resource estimation
* Completion of optimisation and value engineering activities in preparation
for construction
* Integrated environmental authorisation from the DMRE expected in the next
weeks, with commencement of construction imminent
* Steady state production forecast by December 2024.
 

A derivative funding structure was implemented during March 2023, to complete
the funding package for the Mintails project. The structure provided a US$22.6
million (ZAR400 million) upfront premium which, together with the proceeds of
US$47.3 million from the sustainability bond raised during December 2022 and
the debt funding package of US$73.4 million in the form of a credit approved
term loan facility underwritten by FirstRand Bank Limited, acting through its
Rand Merchant Bank division, ensure that the project is fully funded at
commencement of construction. Independent technical reviews of the project
together with legal drafting are currently underway in anticipation of the
debt funding package being closed by June 2023.    

 

Blyvoor conditional acquisition - update

The due diligence and fulfilment of other conditions precedent for the
acquisition of the Blyvoor Gold Operations Proprietary Limited historical TSFs
was not completed within the required timeframe, and this transaction has
therefore lapsed. Although the Group is currently focused on the construction
of the Mintails Project, it continues to engage with the current owners of
Blyvoor Gold Operations to evaluate options to further develop this project.

 

Sudan exploration project

Following the outbreak of violence in the Republic of Sudan, all expatriate
employees working on the exploration project were safely repatriated.  All of
the Group’s assets situated in the Republic of Sudan, including the fire
assay multi-element analytical laboratory, are currently guarded and have been
placed under care and maintenance until such time as the situation stabilises
and the Group can resume its exploration programme. The carrying value of the
Group’s investment in the Sudan exploration project to date, including the
acquisition of the exploration concessions and other assets, amounts to
approximately US$5.0 million. Limited expenditure is currently being incurred
on securing the Group’s assets and their care and maintenance, until such
time as exploration activities can recommence.

 

The Group successfully commissioned the first commercial fire assay
multi-element analytical laboratory within the Republic of Sudan during 2022.
This laboratory is used to analyse all exploration samples extracted from the
Block 12 exploration concessions granted to Pan African by the Sudan Ministry
of Mines and any regional exploration work by other explorers.

 

Prior to the conflict, the exploration team active within Block 12A South and
Block 12A North conducted soil geochemistry and hard rock chip sampling
programmes to further define the identified exploration anomalies. Initial
assaying received from the exploration targets identified in the south-eastern
corner of Block 12A South averaged 1.7g/t from 12 samples taken from quartz
veins, rock debris and soil. However, some of the structures sampled indicated
significantly higher gold mineralisation, with values ranging from 2.9g/t up
to 9.4g/t. These structures will be further defined as part of a confirmatory
sampling programme. No Mineral Resources or Mineral Reserves are currently
reported for any of the targets.

Remote sensing imagery in Block 12A North detected a notable additional NE-SW
anomaly approximately 11km long. Initial field investigations identified a
siliceous unit hosting significant iron oxide alteration, with reported grades
of 7.3, 0.19, and 0.58 g/t. Further sampling along the strike and down-dip of
the unit, as well as subsequent mapping, revealed a potential extension of
several kilometres towards the southwest.

Pan African remains positive that the in-country situation will stabilise to
the extent that it can resume exploration activities in the near future.

 

Final results for the twelve months ended 30 June 2023

 

Pan African anticipates announcing its final results for the current financial
year on or about 13 September 2023.

The information contained in this update is the responsibility of the Pan
African board of directors and has not been reviewed or reported on by the
Group’s external auditors.

Certain information communicated in this announcement was, prior to its
publication, inside information for the purposes of Article 7 of Regulation
596/2014.

Rosebank

26 May 2023

For further information on Pan African, please visit the Company's website at

www.panafricanresources.com

 Corporate information                                                                                                                                                                                                                                                                                                                                                                       
 Corporate office The Firs Office Building 2nd Floor, Office 204 Cnr. Cradock and Biermann Avenues Rosebank, Johannesburg South Africa Office: + 27 (0)11 243 2900 info@paf.co.za                                                                                     Registered office 2 nd Floor 107 Cheapside London EC2V 6DN United Kingdom Office: + 44 (0)20 7796 8644 info@paf.co.za  
 Chief executive officer  Cobus Loots  Office: + 27 (0)11 243 2900                                                                                                                                                                                                    Financial director  Deon Louw  Office: + 27 (0)11 243 2900                                                             
 Head: Investor relations Hethen Hira                                                                                                                                                                                                                                 Website: www.panafricanresources.com                                                                                   
  Tel: + 27 (0)11 243 2900                                                                                                                                                                                                                                                                                                                                                                   
  E-mail: hhira@paf.co.za                                                                                                                                                                                                                                                                                                                                                                    
 Company secretary Jane Kirton St James's Corporate Services Limited Office: + 44 (0)20 7796 8644                                                                                                                                                                     Nominated adviser and joint broker Ross Allister/David McKeown Peel Hunt LLP Office: +44 (0)20 7418 8900               
 JSE Sponsor and JSE debt sponsor Ciska Kloppers Questco Corporate Advisory Proprietary Limited Office: + 27 (0) 11 011 9200 (https://www.google.co.za/search?q=questco&rlz=1C1EJFC_enZA816ZA818&oq=questco&aqs=chrome..69i57j0l5.1159j0j4&sourceid=chrome&ie=UTF-8)  Joint broker Thomas Rider/Nick Macann BMO Capital Markets Limited Office: +44 (0)20 7236 1010                          
                                                                                                                                                                                                                                                                      Joint broker Matthew Armitt/Jennifer Lee Joh. Berenberg, Gossler & Co KG Office: +44 (0)20 3207 7800                   

 