April 24 (Reuters) - PLS Group Ltd PLS.AX:
PLS GROUP - FY26 GUIDANCE REAFFIRMED FOR ALL METRICS
PLS GROUP LTD- QTRLY PRODUCTION 232.4 KT
PLS GROUP - MAJOR MAINTENANCE OVERHAULS SCHEDULED FOR JUNE QUARTER FOR NGUNGAJU PLANT
PLS GROUP - CONTINUES TO MONITOR POTENTIAL SUPPLY CHAIN DISRUPTIONS ARISING FROM ONGOING GEOPOLITICAL TENSIONS IN MIDDLE EAST
PLS GROUP LTD - QTRLY REVENUE A$567 MLN
PLS GROUP - WORKING CLOSELY WITH ITS LONG-TERM CONTRACTED SUPPLIERS TO MANAGE ANY EMERGING RISKS FROM MIDEAST
PLS GROUP - COMPOSITION OF CAPITAL EXPENDITURE IN FY27 TO BE MORE HEAVILY WEIGHTED TOWARDS MINE DEVELOPMENT ACTIVITY COMPARED TO FY26
PLS GROUP - DOES NOT EXPECT ANY MATERIAL DISRUPTION TO OPERATIONS OR ANY IMPACT TO FY26 GUIDANCE FROM MIDEAST
PLS GROUP - EVALUATING POTENTIAL MULTI-YEAR INVESTMENT PROGRAM TO ENHANCE PILGANGOORA INFRASTRUCTURE TO SUPPORT EXISTING OPS
PLS GROUP - DOES NOT FORESEE ANY IMMEDIATE SUPPLY CONSTRAINTS FOR OTHER KEY INPUTS, OTHERS
PLS GROUP - UNIT OPERATING COSTS ARE EXPECTED TO INCREASE IN THE JUNE QUARTER
Source text: ID:nASX8xJCYT
Further company coverage: PLS.AX