** Shares of Metarock Group Ltd MYE.AX fall as much as
14.9% to A$0.200, their lowest since Oct. 7, 2016
** The diversified miner updates on the Thalanga mining
contract, where its unit had entered a deal with Red River's
RVR.AX unit to provide contracting services urn:newsml:reuters.com:*:nASXfgD39
** Co says administrators appointed by Red River have placed
the mine on care and maintenance, prompting Metarock to take
steps to scale down workforce and remove equipment from site
** Adds, Metarock also seeks advice on termination of the
contract
** Says revised FY23 guidance announced previously had
materially downgraded the performance of contract for the
remainder of FY23 due to operation issues at the
mine urn:newsml:reuters.com:*:nL4N31K05K
** Co says, under the Thalanga contract, Metarock has to
recover about A$5.7 million ($3.66 million) in debtors and work
in progress
** Stock posts its biggest intraday pct fall since Oct 20
** Stock has fallen 72.02% this year, as of last close
($1 = 1.5569 Australian dollars)
(Reporting By Udbhav Krishna P in Bengaluru)