Table: Asian naphtha crackers' 2017 maintenance

The following lists planned maintenance at some of the naphtha crackers in Asia 
for 2017, based on information from trade and industry sources. 
    The table will be revised when new information becomes available.  
   
NONE = no maintenance in 2017  
NA   = no available information 
 
Company                  Location   Capacity      2017               Previous  
                                  ('000 tonnes)   Maintenance        Maintenance 
INDONESIA 
Chandra Asri             Anyer        860         None               NA          
                
     
JAPAN  
Asahi Kasei              Mizushima    504    ceased in March 2016    2014  
Asahi Kasei Mitsubishi   Mizushima    567    early May to July       NA 
Idemitsu                 Chiba        414    two maintenance         2015  
(Idemitsu's 1st maintenance will be either in April, May or June. It's 2nd 
shutdown will be in either Sept. Oct. or Nov.)                                   
                
Idemitsu                 Tokuyama     687         None               2016  
Keiyo Ethylene           Chiba        768         None               2014  
Maruzen Petchem          Chiba        525         None               2016  
Mitsubishi Chem          Kashima      392    ceased on May 3 2014    NA 
Mitsubishi Chem          Kashima      540         None               2016  
Mitsubishi Chem          Mizushima    570     early May-July         2015  
Mitsui Chem              Ichihara     612     July (about 40 days)   2015  
Mitsui Chem              Osaka        500         None               2016  
JX Nippon Oil            Kawasaki     444         None               2016  
Showa Denko              Oita         695         None               2014  
Sumitomo                 Chiba        415     ceased in May 2015     2011  
Tonen Chem               Kawasaki     540         None               2014  
Tosoh                    Yokkaichi    527         None               2016  
(Tosoh will have maintenance in 2017 but this will not affect cracker's runs)  
     
MALAYSIA      
Titan                  Pasir Gudang   430      Q3 (30 days)           2011  
Titan                  Pasir Gudang   650      Early Feb (45 days)    2010  
 
     
THE PHILIPPINES 
JG Summit              Batangas City  320      None   commissioned in June 2014 
 
         
SOUTH KOREA     
Lotte Chem             Yeosu         1000      None                   2016  
(Lotte Chem to raise Yeosu's cracker capacity to 1.2 million tpy by 2018) 
Lotte Chem             Daesan        1100      None                   2015  
KPIC                   Onsan         470   mid-April to end May       2013 
(KPIC is shutting the cracker for expansion to raise capacity to 800KT) 
LG Chem                Daesan        1040      None                   2015   
(LG Chem to raise Daesan's cracker capacity to 1.27 million tpy by 2019) 
LG Chem                Yeosu         1160      None                   2014  
SK Energy              Ulsan          200      mid March (1 month)    2013  
SK Energy              Ulsan          660      None                   2016  
Hanwha Total           Daesan        1000      None                   2015  
YNCC                   Yeosu          860      None                   2015  
YNCC                   Yeosu          580      None                   2016  
YNCC                   Yeosu          465      None                   2014  
 
     
SINGAPORE 
ExxonMobil        Jurong Island       900      NA                     NA  
ExxonMobil        Jurong Island      1000      NA                     NA 
(ExxonMobil may have a maintenance at one of its crackers in Q2 2017) 
PCS               Jurong Island       465      None                   2013 
PCS               Jurong Island       635      None                   2016  
Shell             Bukom Island    over 960KT   NA                     2014     
(Shell's cracker was shut on outage in Dec 2015 and restarted in Aug 2016. It 
suffered another outage in Sept 2016 and restarted in Nov 2016) 
     
THAILAND    
ROC               Map Ta Phut         800      None                   2016  
IRPC              Map Ta Phut         360      Jan-March              NA 
 
     
TAIWAN       
CPC               Lin Yuan            380      Q4 2017 (60 days)      NA 
CPC               Kaohsiung           500      ceased in 2015         2014  
CPC               Lin Yuan            720      mid Feb to mid April   NA 
(CPC's newer 720,000 tpy cracker was commissioned in 2013) 
Formosa           Mailiao             700      None                   2015       
Formosa           Mailiao            1030      None                   2016  
Formosa           Mailiao            1200      mid-Aug to early Oct   2014  
  
 
 (Reporting by Osamu Tsukimori in TOKYO; Jane Chung in SEOUL and Seng Li Peng in 
SINGAPORE) 
 ((lipeng.seng@thomsonreuters.com; +65 6870 3086; Reuters Messaging: 
lipeng.seng.thomsonreuters.com@reuters.net)) 
 