Dec 7 (Reuters) - Triton Minerals Ltd TON.AX :
* SIGNIFICANT POTENTIAL PRODUCTION CAPACITY INCREASE AT
PROPOSED
COMMERCIAL PILOT PLANT AT ANCUABE GRAPHITE PROJECT
* INCREASED PRODUCTION CAPACITY WILL GREATLY ASSIST PROPOSED
PROCUREMENT OF DEBT, WITH DISCUSSIONS TO COMMENCE IN Q1 CY2022
* CPP REVISED DESKTOP STUDY NOW ENVISAGES A 250,000 TPA
PLANT
CAPABLE OF PRODUCING 15,000 TO 17,000 TPA OF GRAPHITE
CONCENTRATE
* PRODUCTION AT NO INCREASE TO ESTIMATED CAPITAL
EXPENDITURE.
* TRITON IS CURRENTLY IN DISCUSSIONS WITH POTENTIAL OFFTAKE
PARTNERS FOR INCREASED 5,000 - 8,000TPA OF GRAPHITE CONCENTRATE