Brief: Viva Energy Says Power Outage At Geelong Refinery Occurred On 12 Jan
Jan 13 (Reuters) - Viva Energy Group Ltd VEA.AX :
* POWER OUTAGE AT GEELONG REFINERY OCCURRED ON 12 JANUARY
2025
* OUTAGE DUE TO AN EXTERNAL INTERRUPTION IN POWER SUPPLY
* OUTAGE CAUSED AN UNSCHEDULED SHUTDOWN ACROSS ALL UNITS AT
GEELONG REFINERY
* TIMEFRAME TO RESUME NORMAL PRODUCTION EXPECTED TO BE
BETWEEN ONE
AND TWO WEEKS
Further company coverage: VEA.AX
((Reuters.Briefs@thomsonreuters.com;))
Recent news on Viva Energy
See all newsAustralia's Viva Energy eyes worst week in a month as alkylation unit kept offline
Australia's Viva Energy extends losses as Geelong refinery's alkylation unit kept offline
Australian energy stocks hit lowest level since late February on weaker oil
Australia's Viva Energy drops on extended Geelong refinery unit outage
Brief: Viva Energy Group Says Alkylation Unit Remains Offline At Geelong Refinery