REG - Xtract Resources plc - Bushranger pit optimisation & financial study

For best results when printing this announcement, please click on link below:
http://newsfile.refinitiv.com/getnewsfile/v1/story?guid=urn:newsml:reuters.com:20231106:nRSF5059Sa&default-theme=true

RNS Number : 5059S  Xtract Resources plc  06 November 2023

 

For immediate release

6 November 2023

 

Xtract Resources Plc

("Xtract" or the "Company")

Bushranger Pit Optimisation & Financial Study

 

The Board of Xtract Resources Plc ("Xtract" or the "Company") is pleased to
announce the successful completion of an updated Pit Optimisation &
Financial Modelling Study ("Bushranger Study") to examine the economics of
open pit extraction of the copper-gold Mineral Resources currently defined on
the Bushranger Porphyry Copper-Gold Project ("Project") in central New South
Wales, Australia.

 

Highlights

 

·    Xtract engaged independent consultants, Optimal Mining Solutions
(Pty) Ltd of Australia ("Optimal Mining"), to investigate the economics of a
5Mtpa, 20Mtpa or 25Mtpa open pit mining operation, focussed on the extraction
of shallow higher-grade mineralisation from the Bushranger Project.

 

·    The Racecourse Prospect Mineral Resource is 512Mt @ 0.22% CuEq*, at a
cut-off of 0.1% CuEq, containing 1.1Mt of copper equivalent metal and
classified as Inferred and Indicated in accordance with JORC (2012) (see RNS
23 November 2022).

 

·    The current Racecourse Prospect Mineral Resource has the potential to
be economically mined at mining rates of 20Mpta, or greater, and at copper
prices of US$10,000/t and above.

 

·    The Bushranger Study concluded that the highest post tax NPV8 of
AU$363m (NPV10 - AU$265m) processes ore above 0.10% CuEq at 20mtpa with a sale
price of US$11,000/t.

 

·    The Bushranger Study recognised that optimisation of the processing
plant capacity, capital costs, operating costs and metallurgical recoveries
could greatly improve the economic outcomes of mining the Racecourse deposit.
Addition of an ore sorter does not add value at this stage.

 

·    The Company is focusing efforts on further improvements in
metallurgical recovery and potential associated cost benefits linked to
capital and operating costs.

 

·    The Bushranger Study concluded that due to the large size and
relatively low grade of the Racecourse deposit, conditions are expected to be
excellent for efficient and productive mining. The current Ascot Mineral
Resource is not of sufficient size, or close enough to surface, to warrant
mining.

 

·    The Company believes that the discovery of the Ascot prospect
porphyry copper deposit (see RNS 9 December 2021) confirms that the Bushranger
Project hosts multiple copper-gold porphyry systems and further new
discoveries could significantly enhance the economics of the overall
Bushranger Project.

 

*CuEq % = (Cu%) + (Au g/t * 0.6577)% + (Ag g/t * 0.008769) %

Cu Price = US$8800/t, Au Price = US$1800/oz, Ag Price = US$24/oz

 

 

Colin Bird, Executive Chairman said: "The final results from the Bushranger
Study show that the currently defined Mineral Resources on the Bushranger
Project have the potential to be the basis of a large scale, economic mining
operation, producing significant free cash flows. The outcomes generated from
the mining study are a solid start to understanding the economics of mining
the Project's mineral resources and show there is considerable upside possible
through optimisation of plant capacity, capital costs, operating costs and
metallurgical recoveries, along with potential incorporation of alternative
ore pre-concentration methods. More work is warranted in all these areas but
particularly metallurgical studies where improved recoveries could have a
knock-on effect on both capital and operating cost. Larger deposits require
significantly more capital expenditure and as such warrant considerable study
and due diligence at an early stage of project development when optimisation
can radically change a Project's fortunes. We are at this stage and with this
in mind, the Company will continue with its studies working towards the
ultimate mine and operating plan that provides the best scenario for
development of the Bushranger resource."

 

Final Results from Bushranger Study

Following definition of the updated Mineral Resource for the Racecourse
Prospect and definition of the maiden Mineral Resource for the Ascot Prospect,
Xtract contracted Optimal Mining to complete the Bushranger Study. The
Bushranger Study was aimed at examining the economics of 5Mtpa (the high-grade
option), 20Mtpa or 25Mtpa open pit mining operation.

 

Where appropriate, input from other independent consultants was utilised,
including Measured Resources (mineral resource estimate), Lycopodium (mineral
processing experts) and TOMRA (ore sorting technology). The Bushranger Study
was commissioned to assess the open pit potential based on the currently
defined Inferred and Indicated Resources. The objective of the Bushranger
Study was to assess the potential of the deposit to be initially developed as
an open cut mine and to identity material variables which could affect the
overall economics of a mining operation at Bushranger. The Bushranger Study
included inferred and indicated Mineral Resources some of which are considered
too speculative geologically to have economic considerations applied to them
that would enable them to be categorised as mineral reserves. The Bushranger
Study was based on technical and economic assessments that are insufficient to
support estimation of Ore Reserves or to provide assurance of an economic
development case at this stage, or to provide certainty that the conclusions
of the Bushranger Study will be realised.

 

 

The economic limits of the deposit were initially calculated as part of a pit
optimisation assessment using Deswik's pseudoflow module. The economic limits
of the deposit were calculated applying all foreseeable operating costs and
revenues, with capital costs not included. The pit optimisation assessment was
undertaken utilising the following assumptions:

 

·    Capital Cost Estimate                      -
AU$713M (10Mtpa), AU$1,159M (20Mtpa)

·    Annual Feed Rate (ROM t)           - 5Mpta, 20Mtpa and
25Mtpa

·    Concentrate Output Cu Grade   - 25%

·    Copper Metal
Recovery                                - 88%

·    Gold Metal Recovery                     - 82.3%

·    Silver Metal Recovery                    - 75%

·    Overall Pit Wall Angle                     -
46(0)

·    Block Model Regularisation         - 10m x 10m x 10m Cells

·    Ore Dilution Grade Cu                    - 0%

·    Ore Dilution Grade Au                   - 0 g/t

·    Ore Dilution Grade Ag                    - 0 g/t

·    Cut off
Grades                                  -
0.10% CuEq*, 0.15% CuEq

·    Copper Sales
Price                           - US$8,000/t,
$9,000/t, $10,000/t, $11,000/t

·    Gold Sales
Price
- US$1,900/oz

·    Silver Sales
Price                               - US$22/oz

·    Exchange Rate AUD                        -
US$0.70

·    Treatment
Cost
- US$85/conc t

·    Refining Charge Cu
- US$/0.085/lb payable copper

·    Refining Charge Au                         -
US$/5.00/oz payable gold

·    Refining Charge Ag
- US$/0.50/oz payable silver

·    Mining
Cost
- AU$1.70/t (20Mtpa), AU$1.67/t (25Mtpa)

·    Depth Penalty for Ore                   -
AU$0.0016/t per vertical metre

·    Depth Penalty for Waste              - AU$0.0023/t per
vertical metre

·    Environmental Costs                      -
AU$0.052/t (20Mtpa), AU$0.051/t (25Mtpa)

·    Royalty (% of ex-mine value)      - 4.0%

·    Processing
Cost
- AU$11.63/t milled (20Mtpa), AU$8.41 (20Mpta -
low-cost                         option), AU$10.64/t
milled (25Mpta)

·    G& A
Costs
- AU$1.50/t milled (20Mtpa), AU$1.35/t milled (25Mpta)

·
Freight
- AU$127.30/concentrate t

·    Copper Payable %
- 95%

·    Gold Payable
%                                 - between
90% and 98%, with average of ~93% realised

·    Silver Payable
%                               - 90%

 

 

Using the four different scenarios for the copper price (US$8,000/t, $9,000/t,
$10,000/t, $11,000/t), the two different copper cut-off grades (0.10% CuEq and
0.15% CuEq) and the two scenarios for the mining rate (20Mtpa and 25Mtpa), a
total of 16 cases were assessed in the pit optimisation assessment for the
Racecourse and Ascot Mineral Resources. A separate ore extraction case was
considering for reducing the processing cost from AU$11.63/t milled to
AU$8.41/t milled. Therefore, in total 17 ore extraction cases were assessed in
the pit optimisation assessment and the physical outcomes are given in Table
1.

 

Case 12, of 25Mtpa mining rate, $11k/t copper sale price and 0.10% CuEq
cut-off grade, provides the highest cashflow of ~AU$1.9b.  However, as shown
by case 17, which is the same as case 12 but with the lower operating costs of
AU$8.41/t milled, improvements to the operating costs can significantly impact
the economic outcomes, with case 17 generating an additional AU$425M in free
cash flow.

 

The physical outcomes as set out in the link below show that the current Ascot
Mineral Resource only generated small quantities, <5Mt of ore, and
consequently, is too small to warrant development in its current form:

 

Table 1 - Bushranger Project Open Pit Mining Analysis - Ore Extraction Cases

 

http://www.rns-pdf.londonstockexchange.com/rns/5059S_1-2023-11-6.pdf
(http://www.rns-pdf.londonstockexchange.com/rns/5059S_1-2023-11-6.pdf)

 

Due to the grade of the copper-gold mineralisation at the Racecourse deposit,
processing costs are nearly 50% of the total operating costs.
Pre-concentration of ore has the potential to lower operating costs due to
reducing processing mass and accordingly, Xtract had completed tests using the
TOMRA ore sorting system as announced on 20 July 2023.

 

The results from TOMRA tests were inconsistent and following further
assessment of the TOMRA results, Optimal Mining have determined that using
TOMRA only improves the margin of ore blocks with extremely low copper grades
(<0.1%). Accordingly, the conclusion from this assessment is that due to
the low potential for providing economic benefits, a sorter for ore
pre-concentration was not included in the final financial modelling.

 

In the next stage of the Bushranger Study, the economic limits of selected pit
optimisation assessment scenarios were further developed by Optimal Mining
into detailed practical open pit shells with accompanying large out-of-pit
dump designs. The practical pit shell designs contained batters and berms and
haulage ramps to the process plant and overburden dumps. The pit shells were
divided into mining benches, strips and blocks and interrogated by the
geological model to provide the quantities and qualities for the seven
selected mining scenario schedules.

 

A detailed dig and dump schedule, including haulage modelling, was completed
for all seven detailed

cases with the results imported into a financial model for economic
assessment.

 

The seven detailed cases which were fully designed, scheduled and haulage
modelled are as follows:

 

·    Option 1
- 5mtpa @ $8k/t copper with 0.25% CuEq cut-off grade

·    Option 2
- 20mtpa @ $8k/t copper with 0.15% CuEq cut-off grade

·    Option 3
- 20mtpa @ $9k/t copper with 0.15% CuEq cut-off grade

·    Option 4
- 20mtpa @ $10k/t copper with 0.10% CuEeq cut-off grade

·    Option 5
- 20mtpa @ $11k/t copper with 0.10% CuEq cut-off grade

·    Option 6
- same as Option 5 with lower processing cost (case 17)

·    Option 7
- same as Option 5 with 5mtpa production rate

 

Details of the ore extraction cases are set out Table 2 in the link below and
summarised as follows:

 

 Item        Units  Option 1  Option 2  Option 3  Option 4  Option 5  Option 6  Option 7
 Quantities  Unit   Total     Total     Total     Total     Total     Total     Total

 

 EBITDA                  AU$ '000  $301,075   $832,934    $1,156,980  $1,546,265  $2,090,895  $2,109,517  $1,730,271
 Free cash flow          AU$ '000  $185,526   $1,288,250  $1,341,073  $1,541,532  $1,825,980  $1,830,203  $1,549,151
 NPV8                    AU$ '000  -$547,800  -$74,120    -$19,431    $185,950    $362,842    $296,797    -$95,473
 Breakeven Copper Price  US$/t     $11,973    $8,313      $9,085      $9,349      $9,900      $10,170     $11,570
 NPV10                   AU$ '000  -$569,354  -$153,145   -$99,466    $104,862    $264,610    $193,973    -$197,086

 

 

Table 2 - Bushranger Project Open Pit Mining Analysis - Detailed Schedule
Scenarios

 

http://www.rns-pdf.londonstockexchange.com/rns/5059S_2-2023-11-6.pdf
(http://www.rns-pdf.londonstockexchange.com/rns/5059S_2-2023-11-6.pdf)

 

 

The following equipment assumptions were applied in the seven detailed
schedule scenarios:

1.    The following dig units were used in the schedules:

·    PC4000                 - 1,300 bcm/hr on waste and
ore

·    PC7000                 - 2,000 bcm/hr on ore and
2,100 bcm/hr on waste

·    PC8000                 - 2,200 bcm/hr on waste and
ore

2.    All dig units operate for up to 6,000 hours per annum.

3.    The following trucks were used in the schedules:

·    Komatsu 830E    - 83 bcm (220t) capacity, loaded by PC4000's and
PC7000's.

·    Komatsu 930E    - 109 bcm (290t) capacity, loaded by PC8000's.

4.    Stockpiling will be pivotal to achieving the required annual ore
tonnes.

5.    4 ore stockpiles have been created adjacent to the mill - high grade
(>0.25%), medium grade (0.20%-0.25%), low grade (0.15%-0.20%), very low
grade (<0.15%)

6.    Stockpile loaders rehandle from the ore stockpiles to the crusher in
grade priority.

7.    Drill and blast is not scheduled but is not expected to be a
constraint.

The following mining assumptions were applied in the seven detailed schedule
scenarios:

1.    Several dependencies were established to ensure the logical sequence
of the dig and dump faces, including:

·    The entire bench above, in the same phase, must be completed before
starting the next bench.

·    Blocks must be dug in the correct sequence away from the ramp mouth.

2.    Annual ore tonnes are constrained to 5mt, 20mt 25mt, however monthly
ore tonnes are slightly higher so any shortfalls can be picked up later in the
year.

3.    In general, the waste dump logic is as follows:

·    Small pit shells (options 1 to 5) only dump to the western dumps.

·    The large 20mtpa pit shell (option 6) dumps to the western and
eastern dumps.

4.    All options dump in the area adjacent to the processing plant first.

5.    Ex-pit high grade and medium grade ore is dumped directly to the ROM
stockpile if capacity exists, otherwise dumped to ore stockpiles. Low grade
ore is always dumped to stockpiles.

Other key mining operation assumptions used in developing the financial models
for the seven detailed schedule options were as follows:

1.    Vegetation Clearing
$5,000/ha

2.    Topsoil
Removal                               $6.00/bcm

3.
Diesel
$1.00/litre (includes fuel rebate)

4.    Bulk
Explosives
$1,375/explosive tonne

5.    Explosive Ancillaries
$300/explosive tonne

6.    Multi-skilled Operator
$186,000/year

7.    Skilled
Operator
$138,000/year

8.    Mechanical Maintainer                  $192,000/year

9.    Electrical Maintainer
$204,000/year

10.  All labour rates are fully costed including wages, superannuation,
bonuses, on-costs, etc.

11.  A labour factor of 1.2 (for coverage, training, leave, etc.) was applied

12.  Each employee works 1,500 hours annually

 

 

Conclusions of Bushranger Study

 

The key conclusions from the Bushranger Study of the Racecourse and Ascot
Mineral Resources on the Bushranger Copper-Gold Porphyry Project are as
follows:

 

1.    The Racecourse deposit contains significant low-grade tonnes of
copper, gold and silver which may be economically recoverable at copper sale
prices above US$10,000/t.

2.    An annual production rate of 20mtpa is required to generate a
positive post tax NPV8.

3.    The highest post tax NPV8 of AU$363m (NPV10 - AU$265m) (Detailed
schedule option 5) processes ore above 0.10% CuEq at 20mtpa with a sale price
of US$11,000/t.

4.    The highest post tax NPV8 option provides a return on investment of
7.1% with a payback period of 6 years.

5.    Due to its large size and grade, conditions are expected to be
excellent for the efficient and productive mining of the deposit.

6.    The economic recovery of all metals (copper, gold, silver) from low
grade ores (<0.2% Cu) is pivotal for the economic viability of the project.

7.    Optimisation of the processing plant capacity, capital cost,
metallurgical recoveries and operating cost has the potential to greatly
improve the economic viability of the project and further work is warranted in
all of these areas.

8.    A higher grade, lower volume, 5mpta mining practical mining option
does not appear to be economic.

9.    Addition of an ore sorter does not add value at this stage.

10.  The current Ascot Mineral Resource is not of sufficient size, or close
enough to the surface, to warrant mining.

 

The Company believes that additional tonnes of shallow higher-grade
copper-gold mineralisation has the potential to significantly positively
impact the economics of the overall Bushranger Copper-Gold Porphyry Project
and porphyry targets remain untested in close proximity to the Racecourse
Mineral Resource.

 

Further information is available from the Company's website which details the
company's project portfolio as well as a copy of this
announcement: www.xtractresources.com

 

The information contained within this announcement is deemed by the Company to
constitute inside information as stipulated under the Market Abuse Regulations
(EU) No. 596/2014 as it forms part of UK Domestic Law by virtue of the
European Union (Withdrawal) Act 2018 ("UK MAR").

 

The person who arranged for the release of this announcement on behalf of the
Company was Colin Bird, Executive Chairman and Director.

 

Enquiries:

 

 Xtract Resources Plc                               Colin Bird,          +44 (0)20 3416 6471

                                                    Executive Chairman   www.xtractresources.com (http://www.xtractresources.com)

 Beaumont Cornish Limited                           Roland Cornish       +44 (0)207628 3369

 Nominated Adviser and Joint Broker                 Michael Cornish      www.beaumontcornish.co.uk (http://www.beaumontcornish.co.uk)

                                                    Felicity Geidt

 Novum Securities Limited                           Jon Belliss          +44 (0)207 399 9427

 Joint Broker                                       Colin Rowbury        www.novumsecurities.com

 

 

 

 

Qualified Person

Information in this announcement relating to the exploration works has been
reviewed by Edward (Ed) Slowey, BSc, PGeo, a consultant to Xtract. Mr Slowey
is a graduate geologist with more than 40 years' relevant experience in
mineral exploration and mining, a founder member of the Institute of
Geologists of Ireland and is a Qualified Person under the AIM rules. Mr
Slowey has reviewed and approved the geological content of this announcement.

 

Qualified Person

In accordance with AIM Note for Mining and Oil & Gas Companies, June 2009
("Guidance Note"), Colin Bird, CC.ENG, FIMMM, South African and UK Certified
Mine Manager and Director of Xtract Resources plc, with more than 40 years'
experience mainly in hard rock mining, is the qualified person as defined in
the Guidance Note of the London Stock Exchange, who has reviewed the technical
information contained in this press release.

 

Optimal Mining Solutions (Pty) Ltd of Australia

Optimal Mining Solutions (Pty) Ltd of Australia has reviewed the information
in this announcement which has been derived from the Pit Optimisation &
Financial Modelling Study and has confirmed that the information so presented
is balanced and complete and not inconsistent with the Pit Optimisation &
Financial Modelling Study.

 

Mineral Reserves and Resources

The Company estimates and discloses mineral reserves and resources using the
definitions adopted by JORC.  Further details are available at
www.jorc.org.  See the "Glossary of Geological and Mining Terms" for complete
definitions of mineral reserves and mineral resources.

About Mineral Resources

Mineral resources are not mineral reserves and do not have demonstrated
economic viability but do have reasonable prospect for economic extraction.
They fall into three categories: measured, indicated, and inferred. The
reported mineral resources are stated inclusive of mineral reserves.
Measured and indicated mineral resources are sufficiently well-defined to
allow geological and grade continuity to be reasonably assumed and permit the
application of technical and economic parameters in assessing the economic
viability of the mineral resource. Inferred mineral resources are estimated on
limited information not sufficient to verify geological and grade continuity
or to allow technical and economic parameters to be applied.  Inferred
mineral resources are too speculative geologically to have economic
considerations applied to them. There is no certainty that mineral resources
of any category will be upgraded to mineral reserves.

Important Information about Mineral Reserve and Resource Estimates

Whilst the Company takes all reasonable care in the preparation and
verification of the mineral reserve and resource figures. the figures are
estimates based in part on forward-looking information. Estimates are based on
management's knowledge, mining experience, analysis of drilling results, the
quality of available data and management's best judgment. They are, however,
imprecise by nature, may change over time, and include many variables and
assumptions including geological interpretation, commodity prices and currency
exchange rates, recovery rates, and operating and capital costs. There is no
assurance that the indicated levels of metal will be produced, and the Company
may have to re-estimate the mineral reserves based on actual production
experience. Changes in the metal price, production costs or recovery rates
could make it unprofitable to operate or develop a particular deposit for a
period of time.

Forward Looking Statements

Certain statements in this announcement, are, or may be deemed to be, forward
looking statements. Forward looking statements are identified by their use of
terms and phrases such as ''believe'', ''could'', "should" ''envisage'',
''estimate'', ''intend'', ''may'', ''plan'', ''will'' or the negative of
those, variations or comparable expressions, including references to
assumptions. These forward-looking statements are not based on historical
facts but rather on the Directors' current expectations and assumptions
regarding the Company's future growth, results of operations, performance,
future capital and other expenditures (including the amount, nature and
sources of funding thereof), competitive advantages, business prospects and
opportunities. Such forward looking statements reflect the Directors' current
beliefs and assumptions and are based on information currently available to
the Directors. A number of factors could cause actual results to differ
materially from the results discussed in the forward-looking statements
including risks associated with vulnerability to general economic and business
conditions, competition, environmental and other regulatory changes, actions
by governmental authorities, the availability of capital markets, reliance on
key personnel, uninsured and underinsured losses and other factors, many of
which are beyond the control of the Company. Although any forward-looking
statements contained in this announcement are based upon what the Directors
believe to be reasonable assumptions, the Company cannot assure investors that
actual results will be consistent with such forward looking statements.

 

TECHNICAL GLOSSARY

The following is a summary of technical terms:

 

 "Ag"                          Silver
 "Au"                          Gold
 "Cu"                          Copper
 "CuEq"                        Copper equivalent grade, calculated using assumed metal prices for copper,
                               gold and other metals

 "Indicated Mineral Resource"  That part of a Mineral Resource for which quantity, grade (or quality),
                               densities, shape and physical characteristics are estimated with sufficient
                               confidence to allow the application of Modifying Factors in sufficient detail
                               to support mine planning and evaluation of the economic viability of the
                               deposit. Geological evidence is derived from adequately detailed and reliable
                               exploration, sampling and testing gathered through appropriate techniques from
                               locations such as outcrops, trenches, pits, workings and drill holes, and is
                               sufficient to assume geological and grade (or quality) continuity between
                               points of observation where data and samples are gathered. (JORC 2012)

 "Inferred Mineral Resource"   That part of a Mineral Resource for which quantity and grade (or quality) are
                               estimated on the basis of limited geological evidence and sampling. Geological
                               evidence is sufficient to imply but not verify geological and grade (or
                               quality) continuity. It is based on exploration, sampling and testing
                               information gathered through appropriate techniques from locations such as
                               outcrops, trenches, pits, workings and drill holes. (JORC 2012)

 "mineralisation"              Process of formation and concentration of elements and their chemical
                               compounds within a mass or body of rock
 "NPV"                         Post-tax net present value
 "porphyry"                    A deposit of disseminated copper minerals in or around a large body of
                               intrusive rock

 "Pseudoflow"                  The Pseudoflow algorithm is used to outline the ultimate pit limit by finding
                               the maximum net value of the blocks extracted.
 "Mtpa"                        Million tonnes per annum

ENDS

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact
rns@lseg.com (mailto:rns@lseg.com)
 or visit
www.rns.com (http://www.rns.com/)
.

RNS may use your IP address to confirm compliance with the terms and conditions, to analyse how you engage with the information contained in this communication, and to share such analysis on an anonymised basis with others as part of our commercial services. For further information about how RNS and the London Stock Exchange use the personal data you provide us, please see our
Privacy Policy (https://www.lseg.com/privacy-and-cookie-policy)
.   END  MSCFQLFBXFLLFBF

Recent news on Xtract Resources

See all news