Oct 22 (Reuters) - SAUDI ARABIAN MINING CO 1211.SE :
* ANNOUNCES PROJECT SIGN OFF TO DAELIM INDUSTRIAL LIMITED
AND
SAUDI DAELIM LIMITED
* DEAL VALUE SAR 3.35 BILLION
* ANNOUNCES THAT IT IS DEVELOPING ITS THIRD AMMONIA PLANT
WITH
DAELIM INDUSTRIAL LIMITED AND SAUDI DAELIM LIMITED
* FINANCIAL IMPACT WILL BEGIN BY THE SECOND OR THIRD QUARTER
AFTER
THE EXPECTED COMPLETION DATE (38 MONTHS) IN 2022
* PLANT WILL BE CONSTRUCTED IN RAS ALKHAIR INDUSTRIAL CITY
* DAELIM INDUSTRIAL AND SAUDI DAELIM LIMITED WILL JOINTLY
CARRY
OUT ENGINEERING, PROCUREMENT AND CONSTRUCTION FOR PROJECT
* PROJECT WILL BE IMPLEMENTED OVER 38 MONTHS
* DESIGN CAPACITY IS APPROXIMATELY 1.1MT OF AMMONIA PER
ANNUM
* AMMONIA PLANT IS FOUNDATION OF MULTIPLE PLANTS THAT
MA’ADEN
PLANS TO BUILD TO FORM A THIRD PHOSPHATE COMPLEX WITH AN
ESTIMATED TOTAL COST 24 BILLION RIYALS