* Aramco selects contractors for Fadhili gas plant - sources
* Tecnicas get 2 contracts worth up to $3 bln combined
* Petrofac to receive $1.7 bln contract
(Adds detail, context)
By Reem Shamseddine
DUBAI, Sept 15 (Reuters) - Spain's Tecnicas Reunidas
TRE.MC and Britain's Petrofac PFC.L have been selected for
contracts worth as much as $4.7 billion to build the Fadhili gas
plant in Saudi Arabia for state oil company Saudi Aramco,
industry sources said on Tuesday.
"They received notification last week; a letter of intent,"
said one of the sources, who declined to be identified as the
information isn't public.
Petrofac and Tecnicas declined to comment. Saudi Aramco said
it does not comment on its business plans.
Aramco's decision to move ahead with the project at Fadhili
is a sign that Saudi Arabia continues to make big investments
that it views as key to its economic future, despite slowing or
shelving some projects regarded as low priority as the plunge in
oil prices since last year impacts state finances.
The new plant is to have a processing capacity of 2.5
billion standard cubic feet per day (scfd) of sour gas from the
onshore Khursaniyah and offshore Hasbah fields. ID:nL6N0T92X7
The project is split into three construction packages for
the gas processing unit, utilities and offsite facilities such
as nitrogen, steam, power and water systems, and sulphur
recovery.
Italy's Saipem SPMI.MI and South Korea's Daelim Industrial
000210.KS had previously been said to be among the bidders,
sources told Reuters in July. ID:nL5N10A2AV
Tecnicas bid for two of the packages on its own, and for the
third in conjunction with South Korea's GS Engineering and
Construction, according to a second industry source.
Ultimately, the Spanish firm won the two packages in which
it bid solo: for the gas processing unit for as much as $2
billion and for utilities and offsites, worth as much as $1
billion, according to the first industry source and a separate
source.
Three sources confirmed that Petrofac won the package for
sulphur recovery worth as much as $1.7 billion.
Aramco said in its 2014 annual review published in May that
the Fadhili gas plant was on track to come onstream by 2019.
Fadhili, together with Aramco's other gas projects in Wasit
and Midyan, are slated to add more than 5 billion scfd of
non-associated gas processing capacity, which will help the
company meet soaring domestic demand for industrial use and
electricity generation in the world's largest oil exporter.
Gas production remains a top priority for Saudi Arabia as it
wants to limit direct crude oil burning for electricity, thereby
preserving its ability to increase oil exports.
(Additional reporting by Jose Elias Rodriguez in Madrid and
Karolin Schaps in London; Editing by David Goodman and David
Holmes)
((davidj.french@thomsonreuters.com; +971 4 362 5864; Reuters
Messaging: davidj.french.thomsonreuters.com@reuters.net))
Keywords: SAUDI ARAMCO GAS/FADHILI