BANJA LUKA, Bosnia, Oct 3 (Reuters) - The restart of
Bosnia's 300-megawatt (MW) Ugljevik coal-fired power plant
RTEU.BJ after a three-month regular overhaul will be delayed
for a week due to technical issues, its operator said on
Tuesday.
The plant has been offline since July and was expected to
return to the grid on Oct. 1 but additional work on the
generator is expected to be completed within a week time, the
operator said in a statement to Reuters. L8N1IV27Q
Ugljevik and another 300 MW coal-fired plant at Gacko are
operated by Bosnia's second-largest power utility,
Elektroprivreda Republike Srpske (ERS) ERST.BJ .
Last week ERS sought bids to buy 37,440 megawatt-hours (MWh)
of baseload power to meet demand in the first week October.
L8N1M83QC
(Reporting by Gordana Katana; writing by Maja Zuvela; editing
by Jason Neely)
((maja.zuvela@thomsonreuters.com; +387 33 295 485; Reuters
Messaging: maja.zuvela.thomsonreuters.com@reuters.net))
Keywords: BOSNIA ENERGY/