By Scott DiSavino
NEW YORK, Feb 16 (Reuters) - At least three proposed
U.S. liquefied natural gas (LNG) export plants have likely found
enough customers to receive financial approvals this year,
according to Reuters calculations, developments that would make
the country the world's largest LNG exporter for years to come.
After a dearth of plant approvals last decade, developers
have secured dozens of long-term contracts to finance new
multibillion-dollar LNG plants. The pace of approvals has
accelerated as Europe has shifted away from Russian gas since
Moscow's invasion of Ukraine.
About a dozen developers hope to make final investment
decisions (FID) this year. Many of these projects have been
delayed several times, but analysts said at least three have
secured enough customers to move ahead soon.
The United States was long an importer of LNG, but natural
gas discoveries and production from the shale revolution flipped
the country into an LNG exporter in 2016. U.S. LNG exports hit
10.6 billion cubic feet per day (bcfd) in 2022, making the
country the second biggest LNG exporter behind Australia.
READY TO LAUNCH
Projects best positioned to move ahead include Sempra
Energy's SRE.N Port Arthur plant in Texas, Energy Transfer
LP's ET.N Lake Charles in Louisiana and NextDecade Corp's
NEXT.O Rio Grande in Texas.
They have all or most of the long-term LNG sales agreements
needed to convince bank's that the projects are ready for debt
financing, say analysts.
Sempra said in January it has sold all the capacity needed
to advance the first phase of Port Arthur. Buyers include
Poland's Polski Koncern Naftowy Orlen SA PKN.WA , U.S. oil
producer ConocoPhillips COP.N and Germany's RWE AG RWEG.DE .
NextDecade has signed deals for about 64% of the first phase
of Rio Grande and may soon push it to about 87%, according to
analysts at Morgan Stanley, a bank. Rio Grande's customers
include Exxon Mobil Corp XOM.N , Shell PLC SHEL.L , Portugal's
Galp Energia GALP.LS and Japan's Itochu Corp 8001.T .
NextDecade could secure a financial go-ahead in the second
half of this year, Morgan Stanley said. NextDecade has said that
it was targeting a first-quarter FID for the project's first
phase.
Energy Transfer signaled on Wednesday it might miss its
first-quarter target for a FID due to extreme competition for
LNG buyers. It has deals to sell LNG to several firms, including
Shell, China's ENN Group and Swiss commodity trader Gunvor.
It takes roughly four years to build these giant plants,
so their LNG is not likely to reach markets before 2027. But
their production volumes will allow the United States to remain
ahead of output from Australia and Qatar.
SUPPLY ADDITIONS
The United States already has the capacity to produce the
most LNG in the world and would have been the biggest exporter
if not for the shutdown of Freeport LNG's plant in Texas after a
fire in June 2022.
"The United States still sits atop the ranking of global
LNG supply additions through 2030 ... followed by Qatar,
Mozambique, and Canada," analysts at energy consultancy Tudor
Pickering Holt & Co said in a note.
The United States should export around 11.8 bcfd this year
and 12.6 bcfd next, estimates the U.S. Energy Information
Administration. The seven U.S. export plants already in service,
including Freeport LNG, can turn about 13.8 billion cubic feet
of gas into LNG each day.
The next U.S. LNG plants expected to open are the
QatarEnergy-Exxon joint venture at Golden Pass in Texas in late
2024, the first phase of Venture Global LNG's Plaquemines in
Louisiana in 2024-2026, and Cheniere Energy Inc's LNG.A
expansion at its Corpus Christi plant in Texas in 2025.
(Reporting by Scott DiSavino; Editing by David Gregorio)