Indonesia waste-to-energy project breaks ground in West Java
Indonesia waste-to-energy project breaks ground in West Java By Bernadette Christina
JAKARTA, July 29 (Reuters) - Jabar Environmental Solutions, a joint venture of Sumitomo Corporation, Hitachi Zosen and a subsidiary of United Tractors, broke ground on its waste-to-energy project in Indonesia's West Java province on Wednesday.
Here are the details:
The Legok Nangka waste-to-energy project will have 40.79 megawatts of installed capacity, deputy energy minister Yuliot Tanjung said in a livestreamed ground breaking ceremony.
The project involves a total investment of $400 million and would process 2,100 metric tons of municipal waste per day to generate power.
Construction is expected to take 41 months with a targeted commercial operation date of late 2029, Yuliot said.
A public-private partnership scheme is involved in the financing.
The project is part of the Asia Zero Emission Community.
(Reporting by Bernadette Christina; Editing by David Stanway)
((Bernadette.Christina@Thomsonreuters.com))
Recent news on Kanadevia
See all newsBrief: Nippon Steel Corp - Subsidiary Nippon Steel Engineering And Kanadevia Resolved To Terminate Discussions Toward Business Integration
Brief: Jx Advanced Metals, Kokusai Electric To Be Added To Benchmark Nikkei 225 Index, Nikkei Says
Table: Kanadevia -Q1 group results
Brief: Kanadevia Inova Signs Concession Agreement For Its First Waste-To-Energy Plant In Africa
Indonesia waste-to-energy project breaks ground in West Java