Brief: Liontown Says Early Works And Procurement Underway For KV Expansion
April 29 (Reuters) - Liontown Ltd LTR.AX: EARLY WORKS AND PROCUREMENT UNDERWAY FOR KV EXPANSION COMMITTED CAPITAL FOR BALL MILL PURCHASE IS A$12 MILLION EXPECTED CASH EXPENDITURE ACROSS ENTIRE EARLY WORKS PROGRAMME IN FY2026 IS IN RANGE A$15 - 18 MILLION FORMAL FINAL INVESTMENT DECISION FOR KATHLEEN VALLEY LITHIUM OPERATION EXPECTED AT END OF Q1 Further company coverage: LTR.AX ((Reuters.Briefs@thomsonreuters.com;))