Oct 28 (Reuters) - Chevron CVX.N :
* Sanctions stampede project in the deepwater U.S. Gulf of Mexico
* Says . stampede is a deepwater subsea development, which will be tied-back to
a newly constructed tension leg platform
* Says has reached a final investment decision to proceed with the development
of the Hess Corporation operated stampede project
* Says drilling is planned to commence in the fourth quarter 2015 with first
production expected in 2018
* Says the drilling program includes a total of six production and four water
injection wells
* Project design capacity will be 80,000 barrels of crude oil per day
* Says the stampede field has total estimated recoverable resources in excess
of 300 million barrels of oil equivalent
* Says the Chevron subsidiary has a 25 percent working interest in the
development
* Says stampede project cost is expected to be approximately $6 billion
* Other co-owners of the stampede project include Statoil and Nexen
* Source text for Eikon ID:nBw17sPHca
* Further company coverage CVX.N ((Bangalore Newsroom; +1 646 223 8780))