Picture of Kore Potash logo

KP2 Kore Potash News Story

0.000.00%
gb flag iconLast trade - 00:00
Basic MaterialsHighly SpeculativeSmall CapNeutral

REG - Kore Potash PLC - Kola Project Optimised DFS update

For best results when printing this announcement, please click on link below:
https://newsfile.refinitiv.com/getnewsfile/v1/story?guid=urn:newsml:reuters.com:20250227:nRSa6894Ya&default-theme=true

RNS Number : 6894Y  Kore Potash PLC  27 February 2025

27 February 2025

Kore Potash Plc

("Kore Potash" or the "Company")

 

Kola Project Optimised DFS update

 

Kore Potash, the potash development company with 97% ownership of the Kola and
DX Potash Projects in the Sintoukola Basin, located within the Republic of
Congo ("RoC"), is pleased to provide an update in relation to the optimised
Kola Definitive Feasibility Study ("Optimised DFS") for the Kola Project
("Kola" or "Kola Project") further to the announcement regarding the signing
of the Engineering, Procurement and Construction contract ("EPC") for the Kola
Project with PowerChina International Group Limited ("PowerChina") on 20
November 2024.

 

Prior to signing an EPC agreement, two studies have been completed by the
Company: the Kola Definitive Feasibility Study ("DFS") in January 2019 and the
Kola Project Optimisation Study ("Optimisation Study") in June 2022, details
of both of which have been released to AIM, JSE and ASX on 29 January 2019 and
28 June 2022 respectively. Following signing of the EPC contract, the Company
undertook an exercise to optimise the DFS to account for the EPC contract,
including updating the Kola production schedule and the forecast financial
information. The Company has now completed its review of the Optimised DFS,
with the results summarised herein by way of update.

 

The results of the Optimised DFS incorporate the most current information
available to the Company, and have been updated from the DFS and Optimisation
Study to ensure compliance with the latest applicable listing rule
requirements and other regulatory policies of the Australian Stock Exchange
Limited, and therefore should be considered as superseding the results of both
the DFS and the earlier Optimisation Study.

 

Unlike the DFS and the Optimisation Study, the Optimised DFS is based on a
production period which utilizes all Proved and Probable Ore Reserves and only
6% of Inferred Minerals Resources, giving a Life of Mine ("LoM") of 23 years.

 

Kore Potash considers there is strong potential for the mine plan on which
this Optimised DFS is based to be extended beyond 23 years by upgrading a
portion of the 340 Mt of Inferred Mineral Resources to Measured or Indicated
Resources through further exploration during the 23 years of operations.

 

 

Highlights of the Optimised DFS

 ·                         Capital cost of US$2.07 billion (nominal basis) on a signed fixed price EPC
                           basis, including owner's costs.
 ·                         Assumed construction start date of 1 January 2026, with construction period of
                           43 months.
 ·                         Kola designed with a nameplate capacity of 2.2 million tonnes per annum
                           ("Mtpa") of Muriate of Potash ("MoP").
 ·                         Average MoP production per year of 2.2 Mtpa of MoP for total MoP production of
                           50Mt over a 23-year life of mine.
 ·                         Average cost of MoP delivered to Brazil is US$128/t. Based on an independent
                           MoP market study commissioned by the Company, management considers Kore Potash
                           is projected to become one of the lowest cost producers in the global
                           agricultural market to Brazil.
 ·                         Average annual EBITDA is approximately US$733 million. Kore Potash is
                           projected to continue to enjoy a very high average EBITDA margin of 74%.
 ·                         Key financial metrics, at MoP CFR Brazil pricing averaging US$449/tonne and on
                           a 90% attributable basis (reflecting Kore's future holding of 90% and the RoC
                           government 10%):
                           o  - Kola NPV(10%) (real) post-tax US$1.7 billion
                           o  - IRR 18% (real) on ungeared post-tax basis
 ·                         Kola is designed as a conventional mechanised underground potash mine with
                           shallow shaft access. Ore from underground is transported to the processing
                           plant via an approximately 25.5 km long overland conveyor. After processing,
                           the finished product is conveyed 8.5 km to the marine export facility. MoP is
                           transferred from the storage area onto barges via a dedicated barge loading
                           jetty before being transhipped into ocean-going vessels for export.

 

Cautionary Statement:

The production target (and the forecast financial information derived from
this production target) includes all of Kore Potash's reported Ore Reserve
estimates, together with a proportion of Inferred Mineral Resources. The
production target includes relative portions of ore by category of Proved and
Probable Ore Reserves (94%) and Inferred Mineral Resources (6%). The Company
is satisfied that the proportion of Inferred Mineral Resources is not the
determining factor in project viability as the project demonstrates positive
economic outcomes with the Inferred Mineral Resources excluded. There is a low
level of geological confidence associated with Inferred Mineral Resources and
there is no certainty that further exploration work will result in the
determination of Indicated Mineral Resources or that the production targets
will be realised.

The forecast financial information derived from the production target uses
Argus Media Marketing's forecast annual MoP CFR Brazil prices to 2047 and then
an incremental increase of US$2/t annually post 2047, which annual prices
imply an average MoP CFR Brazil price of US$449/t over the 23 years of
scheduled production in the Optimised DFS. As discussed in section 12 (Potash
Marketing), Kore Potash has concluded it has a reasonable basis for the use of
those prices, but there is no guarantee that such prices will be realised and
lower product pricing will significantly affect the financial performance of
the Kola Project. Refer to the sensitivity analysis in section 14 (Economic
Evaluation) for further details, together with the Forward Looking Statements
notice below.

 

To achieve the range of outcomes indicated in the Optimised DFS, the Optimised
DFS estimates that funding in the order of US$2.07 billion (nominal basis) in
construction capital will be required. Shareholders and investors should be
aware that there is no certainty that Kore Potash will be able to raise the
required funding when needed and it is possible that such funding may only be
available on terms that may be highly dilutive or otherwise adversely affect
Kore Potash shareholders' exposure to the Kola Project economics. Whilst the
Company has made progress towards financing the development of the Kola
Project as discussed further in section 15 (Project Funding) of Appendix A,
those arrangements are currently non-binding and therefore there is currently
no certainty that the Company will be able to raise the funds required to
develop the Kola Project, or if funding is available, the terms of such
funding.

 

Andre Baya, Chief Executive Officer of Kore Potash, commented:

 

"The Kola Project is of global significance as the security of the world's
food supply is at the mercy of global disruptions to fertilizer supply. Recent
geopolitical events have highlighted this risk as potash production is
concentrated among a small number of companies and countries.

 

Furthermore, to reduce the carbon footprint of our industry, new potash
producers need to be geographically closer to end users with reduced freight
cost and environmental impact. In that sense, Kola's location is ideal to
supply environmentally-friendly potash to meet the growing demand of the
Brazilian market.

 

As our operating cost, inclusive of freight, is of USD 128.19/MT (CFR Brazil),
we can vie for a higher profit margin than any existing potash mine worldwide
when it comes to serving our target market. With an NPV10 of USD 1.7 Billion
for our production target, the Kola project reaches an enticing IRR of 18%.

 

The execution of the Kola EPC contract with PowerChina now moves Kore Potash
one gigantic step closer to production and we eagerly await financial close to
start construction."

 

 

Kola Project Optimised DFS update, EPC

On 6 April 2021, Kore Potash announced the signing of a non-binding Memorandum
of Understanding ("MoU") with the Summit Consortium ("Summit") to arrange the
full financing required for the construction of the Kola Project.

The Optimisation Study, which represented the first part of the financing
process, was undertaken by SEPCO Electric Power Construction Corporation
("SEPCO"). PowerChina is SEPCO's parent company. The key goals of the
Optimisation Study were to improve Kola's value through reductions in capital
costs and by shortening the construction schedule.

During the Optimisation Study, SEPCO employed two key subcontractors: China
ENFI Engineering Corporation to review the mining, processing, and
infrastructure aspects of the Project, and CCCC-FHDI Engineering Co Limited to
optimise the marine facilities.

The optimisations continued in 2023 and 2024 and included in-country work to
better define geotechnical conditions. These works culminated in signing a
US$1.929 billion fixed-cost EPC agreement on 19 November 2024. The EPC
included refined cost estimates with a knowledge of conditions at each
construction location. The Company worked with certain potential suppliers and
vendors to refine the Kola Project requirements and obtained pricing updates
where necessary.

A summary of the key Kola Project parameters and assumptions adopted in the
Optimised DFS update post signing EPC agreement are summarised in Table 1
below.

 

Table 1: Key Project Parameters and Assumptions

 Result                                              Unit         Production Target
 Total MOP production                                Mt           50
 Initial project life                                Years        23
 Average scheduled mining rate                       Mtpa ore     7.0
 KCl recovery in process plant                       % KCl        89.9%
 Average MOP production per year                     Mtpa         2.20 Mtpa
 Capital Cost EPC basis (real)*                      US$ billion  2.01
 Sustaining capital                                  US$/t MOP    13.06
 Construction schedule                               months       43
 Steady state operating cost (Mine gate)             US$/t MOP    74.94
 Operating cost (CFR Brazil)                         US$/t MOP    128.19
 Forecast average MoP granular price (CFR Brazil)**  US$/t MOP    449
 Post tax, real un-geared NPV(10%)                   US$ million  1,675
 Post tax, real un-geared IRR                        %            18%
 Average EBITDA per annum real                       US$ million  733
 Average EBITDA margin                               %            74%

 

Notes:

* The US$2.01 billion capital cost (real) includes US$141 million for Kore's
owner's costs during the EPC phase.

** US$449/t is Argus Media Group's forecast real average future potash CFR
Brazil prices over the project life. Further details in Item 12 Potash
Marketing below.

 

Key assumptions related to the ore reserves, production schedules and
financial evaluation of the project have been updated in Appendix B of this
announcement.

 

Ore Reserves and Mineral Resources

The Kola Potash Ore Reserves (Table 2) are based on the Kola Sylvinite Mineral
Resources  (Table 3) as confirmed on 27 Feb 2025. Further detail on the Ore
Reserve Estimate is provided in Appendix B: Summary of Information required
according to ASX Listing Rule 5.9.1 and Appendix C: JORC 2012 - Table 1,
Section 4 Ore Reserves. All of the Ore Reserves and Mineral Resources reported
here for Kola are Sylvinite.

 

Table 2: Kola Sylvinite Ore Reserves

 Classification      Ore Reserves  KCl grade  Mg       Insolubles

                     (Mt)          (% KCl)    (% Mg)   (% Insol.)
 Proved              61.8          32.1       0.11     0.15
 Probable            90.6          32.8       0.10     0.15
 Total Ore Reserves  152.4         32.5       0.10     0.15

 

Table 3: Kola Sylvinite Mineral Resources (inclusive of Ore Reserves) *

 Classification           Million Tonnes  KCl       Mg       Insoluble

                          (Mt)            (% KCl)   (% Mg)   (% Insol.)
 Total Measured           215.7           35.0      0.08     0.13
 Total Indicated          292.0           35.7      0.06     0.14
 Total Inferred           340.0           34.0      0.08     0.25
 Total Mineral Resources  847.7           34.9      0.08     0.18

* The Kola Mineral Resource Estimate was confirmed on 27 Feb 2025 in an
announcement titled "Confirmation of Mineral Resource for Kola Deposit".

 

Production targets and  forecast financial information derived from
production targets

 

This release contains information that constitutes a production target for the
Kola Project (and forecast financial information derived from that production
target) for the purposes of the ASX Listing Rules.

 

Ore Reserve and Mineral Resource estimates underpinning the production target
for the Kola Project referred to in this release were prepared by, or under
the supervision of, a Competent Person in accordance with the JORC Code, 2012
Edition. Competent Person's statements are set out on page 6. Details of those
Ore Reserves and Mineral Resources are set out in this announcement
(including, in relation to the Ore Reserves, the details in Appendix B and
Appendix C).

 

The production target includes relative portions of ore by category of Proved
and Probable Ore Reserves (94%) and Inferred Mineral Resources (6%).

 

The material assumptions applied in the estimation of the production target
for the Kola Project project and forecast financial information derived from
those production target are set out in the summaries of the study outcomes
accompanying this announcement.

 

The Company is satisfied that in each case, the proportion of Inferred Mineral
Resources is not the determining factor in project viability as the project
demonstrates positive economic outcomes with the Inferred Mineral Resources
excluded. There is a low level of geological confidence associated with
Inferred Mineral Resources and there is no certainty that further exploration
work will result in the determination of Indicated Mineral Resources or that
the production target will be realised.

 

 

 

Market Abuse Regulation

This announcement contains inside information for the purposes of Article 7 of
the Market Abuse Regulation (EU) 596/2014 as it forms part of UK domestic law
by virtue of the European Union (Withdrawal) Act 2018 ("MAR"), and is
disclosed in accordance with the Company's obligations under Article 17 of
MAR.

 

This announcement has been approved for release by the Board.

 

For further information, please visit www.korepotash.com
(http://www.korepotash.com/) or contact:

 

 

 Kore Potash

 Andre Baya, CEO
 Andrey Maruta, CFO                             Tel: +44 (0) 20 3963 1776
 Tavistock Communications

 Emily Moss                                     Tel: +44 (0) 20 7920 3150

 Nick Elwes

 Josephine Clerkin

 SP Angel Corporate Finance - Nomad and Broker  Tel: +44 (0) 20 7470 0470

 Ewan Leggat

 Charlie Bouverat

 Grant Barker
 Shore Capital - Joint Broker                   Tel: +44 (0) 20 7408 4050

 Toby Gibbs

 James Thomas
 Questco Corporate Advisory - JSE Sponsor       Tel: +27 63 482 3802

 Doné Hattingh

 

 

END

 

 

 

Competent Persons Statement

The estimated Ore Reserves and Mineral Resources underpinning the production
target have been prepared by a competent person in accordance with the
requirements of the 2012 Edition of the Australasian Code for Reporting of
Exploration Results, Mineral Resources and Ore Reserves (JORC Code, 2012
Edition).

 

The information relating to Exploration Results and Mineral Resources in this
announcement is based on, or extracted from previous reports referred to
herein, and available to view on the Company's website https://korepotash.com
(https://korepotash.com) . The Kola Mineral Resource Estimate was confirmed on
27 Feb 2025 in an announcement titled "Confirmation of Mineral Resource for
Kola Deposit". The Company confirms that it is not aware of any new
information or data that materially affects the information included in the
original market announcements and that all material assumptions and technical
parameters underpinning the estimates in the relevant market announcement
continue to apply and have not materially changed. The Company confirms that
the form and context in which the Competent Person's findings are presented
have not been materially modified from the original market announcement.

 

The information in this announcement that relates to Mineral Resources is
based on information compiled or reviewed by, Garth Kirkham, P.Geo., who has
read and understood the requirements of the JORC Code, 2012 Edition. Mr.
Kirkham is a Competent Person as defined by the JORC Code, 2012 Edition,
having a minimum of five years of experience that is relevant to the style of
mineralization and type of deposit described in this announcement, and to the
activity for which he is accepting responsibility. Mr. Kirkham is member in
good standing of Engineers and Geoscientists of British Columbia (Registration
Number 30043) which is an ASX-Recognized Professional Organization (RPO). Mr.
Kirkham is a consultant engaged by Kore Potash Plc to review the documentation
for Kola Deposit, on which this announcement is based, for the period ended 29
October 2018. Mr. Kirkham has verified that this announcement is based on and
fairly and accurately reflects in the form and context in which it appears,
the information in the supporting documentation relating to preparation of the
review of the Mineral Resources.

 

The information in this announcement that relates to Ore Reserves is based on
information compiled or reviewed by, Mo Molavi, P. Eng., who has read and
understood the requirements of the JORC Code, 2012 Edition. Mr. Molavi is a
Competent Person as defined by the JORC Code, 2012 Edition, having a minimum
of five years of experience that is relevant to the style of mineralization
and type of deposit described in this announcement, and to the activity for
which he is accepting responsibility. Mr. Molavi is member  good standing of
Engineers and Geoscientists of British Columbia (Registration Number 37594)
which is an ASX-Recognized Professional Organization (RPO). Mr. Molavi is a
consultant engaged by Kore Potash Plc to review the documentation for Kola
Deposit, on which this announcement is based, for the period ended 29 October
2018. Mr. Molavi has verified that this announcement is based on and fairly
and accurately reflects in the form and context in which it appears, the
information in the supporting documentation relating to preparation of the
review of the Ore Reserves.

 

Forward-Looking Statements

This announcement contains certain statements that are "forward-looking" with
respect to the financial condition, results of operations, projects and
business of the Company and certain plans and objectives of the management of
the Company. Forward-looking statements include those containing words such
as: "anticipate", "believe", "expect," "forecast", "potential", "intends,"
"estimate," "will", "plan", "could", "may", "project", "target", "likely" and
similar expressions identify forward-looking statements. By their very nature
forward-looking statements are subject to known and unknown risks and
uncertainties and other factors which are subject to change without notice and
may involve significant elements of subjective judgement and assumptions as to
future events which may or may not be correct, which may cause the Company's
actual results, performance or achievements, to differ materially from those
expressed or implied in any of our forward-looking statements, which are not
guarantees of future performance. There are a number of risks, both specific
to Kore Potash, and of a general nature, which may affect the future operating
and financial performance of Kore Potash, and the value of an investment in
Kore Potash including and not limited to title risk, renewal risk, economic
conditions, stock market fluctuations, commodity demand and price movements,
timing of access to infrastructure, environmental risks, regulatory risks,
operational risks, reliance on key personnel, Ore Reserve estimations, local
communities risks, foreign currency fluctuations, and mining development,
construction and commissioning risks.

 

Neither the Company, nor any other person, gives any representation, warranty,
assurance or guarantee that the occurrence of the events expressed or implied
in any forward-looking statement will occur.  Except as required by law, and
only to the extent so required, none of the Company, its subsidiaries or its
or their directors, officers, employees, advisors or agents or any other
person shall in any way be liable to any person or body for any loss, claim,
demand, damages, costs or expenses of whatever nature arising in any way out
of, or in connection with, the information contained in this document.

 

In particular, statements in this announcement regarding the Company's
business or proposed business, which are not historical facts, are
"forward-looking" statements that involve risks and uncertainties, such as
Mineral Resource estimates market prices of potash, capital and operating
costs, changes in project parameters as plans continue to be evaluated,
continued availability of capital and financing and general economic, market
or business conditions, and statements that describe the Company's future
plans, objectives or goals, including words to the effect that the Company or
management expects a stated condition or result to occur. Since
forward-looking statements address future events and conditions, by their very
nature, they involve inherent risks and uncertainties. Actual results in each
case could differ materially from those currently anticipated in such
statements. Shareholders are cautioned not to place undue reliance on
forward-looking statements, which speak only as of the date they are made. The
forward-looking statements are based on information available to the Company
as at the date of this release. Except as required by law or regulation
(including the ASX Listing Rules), the Company is under no obligation to
provide any additional or updated information whether as a result of new
information, future events, or results or otherwise.

 

Summary information

Kore Potash plc has prepared this announcement. This document contains general
background information about Kore Potash plc current at the date of this
announcement. It does not constitute or form part of any offer or invitation
to purchase, otherwise acquire, issue, subscribe for, sell or otherwise
dispose of any securities, nor any solicitation of any offer to purchase,
otherwise acquire, issue, subscribe for, sell, or otherwise dispose of any
securities. The announcement is in summary form and does not purport to be
all-inclusive or complete. It should be read in conjunction with the Company's
other periodic and continuous disclosure announcements, which are available to
view on the Company's website https://korepotash.com (https://korepotash.com)
.

 

The announcement, publication or distribution of this announcement in certain
jurisdictions may be restricted by law, and therefore, persons in such
jurisdictions into which this announcement is released, published or
distributed should inform themselves about and observe such restrictions.

 

Not financial advice

This document is for information purposes only and is not financial product or
investment advice, nor a recommendation to acquire securities in Kore Potash
plc. It has been prepared without considering the objectives, financial
situation or needs of individuals. Before making any investment decision,
prospective investors should consider the appropriateness of the information
having regard to their own objectives, financial situation and needs and seek
legal and taxation advice appropriate to their jurisdiction.

 

Appendix A: Summary of Kola Project Optimised DFS update - December 2024

 1.                        Project Introduction:
                           Kore Potash is a mineral exploration and development company that is
                           incorporated in the United Kingdom and listed on the AIM (a sub-market of the
                           London Stock Exchange, as KP2), the Australian Securities Exchange (ASX, as
                           KP2),  the Johannesburg Stock Exchange (JSE, as KP2) and A2X Proprietory
                           Limited (an independent stock exchange in South Africa, A2X, as KP2) Markets.

                           The primary asset of Kore is the Kola Project located in the RoC, held by the
                           97%-owned Sintoukola Potash SA ("SPSA"). SPSA has 100% ownership of the Kola
                           Mining Lease, on which the Kola Project is located.

                           The Kola Project is situated in the Kouilou Province of the RoC, within 40 km
                           of the Atlantic Coast and approximately 70 km north of the port city of Pointe
                           Noire.

                           The Kola DFS considers the mining of the Kola Sylvinite, and the production of
                           approximately 2.2 Mtpa of MoP and its export to its target markets and
                           considers all associated infrastructure. It delivers an economic model based
                           on life of project of 23 years that is based upon 23 production years
                           exploiting Ore Reserves of 152.4 Mt and 9.7 Mt of Inferred Mineral Resource.

                           In 2017, Kore commissioned a consortium of French companies ("FC") to conduct
                           a DFS for the Kola Project. The FC included: Technip France ("TPF"), Vinci
                           Construction Grands Projets ("VCGP"), Egis International ("EGIS") and Louis
                           Dreyfus Armateurs ("LDA").

                           Met-Chem DRA Global ("MTC") and AMC Consulting ("AMC") were appointed by the
                           FC as their specialist subconsultants.

                           Kore directly contracted with MTC for the Mineral Resource Estimate ("MRE"),
                           and SRK Consulting (UK) Limited ("SRK") for undertaking the Environmental and
                           Social Impact Assessment ("ESIA").

                           The Kola DFS was finalised in January, 2019.

                           On 6 April 2021, Kore Potash announced the signing of a non-binding MoU with
                           Summit to arrange the full financing required for the construction of the Kola
                           Project.

                           The Optimisation Study, which represented the first part of the financing
                           process, has been undertaken by SEPCO. PowerChina is SEPCO's parent company.
                           The key goals of the Optimisation Study were to improve the value of Kola
                           through reductions in the capital cost and by shortening the construction
                           schedule.

                           During the Optimisation Study, SEPCO employed two key sub-contractors, China
                           ENFI Engineering Corporation to review the mining, processing and
                           infrastructure aspects of the Project and CCCC-FHDI Engineering Co Limited to
                           consider the optimisation of the marine facilities.

                           A Deepening Design Study phase was conducted in 2023 and included in-country
                           work to better define geotechnical conditions. The Deepening Design Study also
                           refined cost estimates with a knowledge of conditions at each construction
                           location. These works culminated in signing a US$1.929 billion fixed-cost EPC
                           agreement on 19 November 2024. The Company worked with certain potential
                           suppliers and vendors to refine the Kola Project requirements and obtained
                           pricing updates where necessary.

                           Prior to 2019, Kore directly contracted with MTC for the Mineral Resource
                           Estimate, and SRK for undertaking an ESIA. The ESIA received a 25-year
                           approval from the Congolese Environmental authorities and while still valid,
                           it will require a minor amendment linked to the change of location of the
                           Process plant.  The MRE has remained unchanged and has been incorporated into
                           the Optimisation Study update together with the ESIA recommendations.

                           Figure 1 shows the Location Map for the Optimised Kola Project

 

Figure 1: Location Map showing Optimised Kola Project

 

 

2.    Mineral Resource

The Kola Mineral Resources are summarised in Table 4 below.

The total Measured and Indicated Mineral Resources are 508 Mt with an average
grade of 35.4% KCl and provides the basis for the Ore Reserve statement.
Sections 1 to 3 of the JORC 2012 Table 1 Checklist of Assessment and Reporting
Criteria for that Mineral Resource estimate remain unchanged as confirmed to
shareholders on 27 Feb 2025, and can be found in Appendix D.

The Company confirms there has been no material change to those Mineral
Resources. The Company advises that the Mineral Resources are inclusive of
Mineral Resources to which modifying factors have been applied to be reported
as Ore Reserves.

In accordance with JORC 2012, the Competent Persons ("CP") for the Kola MRE
is:

o  Mr. Kirkham P. Geo of MTC.  Mr Kirkham is a member of good standing of
the Association of Professional Engineers and Geoscientists of British
Columbia.

 

 

 

 

Table 4 July 2017 Kola Mineral Resources for Sylvinite

 July 2017 - Kola Deposit Potash Mineral Resources - SYLVINITE
                                             Million Tonnes  KCl   Mg    Insoluble
                                             Mt              %     %     %
 Hanging wall Seam  Measured                 ‒               ‒     ‒     ‒
                    Indicated                29.6            58.5  0.05  0.16
                    Inferred                 18.2            55.1  0.05  0.16
                    Total Mineral Resources  47.8            57.2  0.02  0.16
 Upper Seam         Measured                 153.7           36.7  0.04  0.14
                    Indicated                169.9           34.6  0.04  0.14
                    Inferred                 220.7           34.3  0.04  0.15
                    Total Mineral Resources  544.3           35.1  0.04  0.14
 Lower Seam         Measured                 62.0            30.7  0.19  0.12
                    Indicated                92.5            30.5  0.13  0.13
                    Inferred                 59.9            30.5  0.08  0.11
                    Total Mineral Resources  214.4           30.6  0.13  0.12
 Footwall Seam      Measured                 ‒               ‒     ‒     ‒
                    Indicated                ‒               ‒     ‒     ‒
                    Inferred                 41.2            28.5  0.33  1.03
                    Total Mineral Resources  41.2            28.5  0.33  1.03
 Total Measured + Indicated                  507.7           35.4  0.07  0.14
 Total Inferred                              340.0           34.0  0.08  0.25
 Total Mineral Resources                     847.7           34.9  0.08    0.18

 

 

3.    Ore Reserves

The Kola Ore Reserves are summarised in Table 5 below.

The Kola Sylvinite Ore Reserves are 152.4 Mt with average grade of 32.5% KCl.
Section 4 of the JORC 2012 Table 1 as reported to shareholders on 29 January
2019 has been updated based on the Optimised DFS and is included in this
announcement in Attachment C.

The original statement of Ore Reserves was prepared by Met-Chem DRA Global and
was reported in accordance with JORC 2012.

In conjunction with the Optimised DFS the Ore Reserves have been reviewed and
restated in accordance with JORC 2012 by the CP for the Kola Ore Reserves:

o  Mr. Molavi P. Eng. of AMC, for the Reserve Review ("RR").  Mr Molavi is a
member of good standing of the Association of Professional Engineers and
Geoscientists of British Columbia.

There is no change to the Kola Sylvinite Ore Reserves from those previously
reported.

 

Table 5: Kola Sylvinite Ore Reserves

 Seam                         Classification      Ore Reserves Tonnage  KCl      Mg      Insolubles

                                                  (Mt)                  (%KCl)   (%Mg)   (%Insol)
 Upper Seam Sylvinite         Proved              47.3                  33.43    0.08    0.15
                              Probable            58.7                  31.83    0.06    0.15
                               Total              106.0                 32.54    0.07    0.15
 Lower Seam Sylvinite         Proved              14.5                  27.88    0.20    0.13
                              Probable            23.4                  28.35    0.08    0.14
                               Total              37.9                  28.17    0.13    0.14
 Hanging Wall Seam Sylvinite  Proved
                              Probable            8.4                   52.09    0.47    0.19
                              Total               8.4                   52.09    0.47    0.19
 TOTAL                        Proved              61.8                  32.13    0.11    0.15
                              Probable            90.6                  32.81    0.10    0.15
                              Total Ore Reserves  152.4                 32.54    0.10    0.15

All Sylvinite in the Measured and Indicated Resource category was considered
for Ore Reserve conversion because of the sharp grade boundaries of the
Sylvinite seams and the fact that the economic Cut- off Grade ("CoG") is below
the Mineral Resources CoG of 10% KCl.

 

 

 

 

 

 

Table 6. Kore's Sylvinite Mineral Resources and Ore Reserves

 

 KOLA SYLVINITE DEPOSIT
                                 Gross                                                      Net Attributable (90%)
 Mineral Resource Category       Million Tonnes  Grade KCl %  Contained KCl million tonnes  Million Tonnes  Grade KCl %  Contained KCl million tonnes
 Measured                        216             34.9         75                            194             34.9         68
 Indicated                       292             35.7         104                           263             35.7         94
 Sub-Total Measured + Indicated  508             35.4         180                           457             35.4         162
 Inferred                        340             34.0         116                           306             34.0         104
 TOTAL                           848             34.8         295                           763             34.8         266

                                 Gross                                                      Net Attributable (90%)
 Ore Reserve Category            Million Tonnes  Grade KCl %  Contained KCl million tonnes  Million Tonnes  Grade KCl %  Contained KCl million tonnes
 Proved                          62              32.1         20                            56              34.9         19
 Probable                        91              32.8         30                            82              35.7         29
 TOTAL                           152             32.5         50                            137             35.4         49
 Table provided as Gross and Net Attributable (reflecting Kore's future holding
 of 90% and the RoC government 10%), prepared and reported according to the
 JORC Code, 2012 edition. Table entries are rounded to the appropriate
 significant figure.

 Ore Reserves are not in addition to Mineral Resources but are derived from
 them by the application of modifying factors.

 

4.    Mining

The Kola mine design utilised in the Optimised DFS remains materially
unchanged from the design used in the DFS and is described below:

The Kola orebody is planned to be mined using conventional underground
mechanised methods, extracting the ore within 'panels', using Continuous Miner
("CM") machines of the drum-cutting type. This is the most widely used method
of potash mining world-wide and is considered a low-risk method. The mine
design adopts a relatively typical layout including panels, comprised of rooms
and pillars. Pillars are the support rock left in place to provide stable
ground support during the operation of the mine.

The mine design is based on a minimum mining height of 2.5 m with mining being
undertaken by a CM which is capable of mining seam heights of between 2.5 m
and 6 m. Each panel is accessed by 4 entries. Each entry is 8m wide and 3m to
6m high depending on the seam height. The rooms are mined in a chevron pattern
at an angle of 65 degrees from the middle entry, each with a length of
approximately 150 m.

Key geotechnical parameters evaluated in the mine design were:

o  support interval between potash seams to be minimum of 3 m thick,

o  8 m wide pillar between consecutive production rooms (of 8 m each)

o  50 m wide pillar between Production Panels and between the side of the
Production Panel and the Main Haulage

o  minimum thickness of 10 m to 15 m of the Salt Member between the mine
openings and the floor of the overlying Anhydrite Member (referred to as the
'salt back')

o  stand-off distance of 20 m from any exploration holes

o  stand-off distance of between 30 m - 60 m from significant geological
anomalies

o  pillar of 300 m in radius around Shafts

Mine access is provided by two vertical Shafts, each 8 m in diameter. The
shafts will be sunk near the center of the orebody. To provide access to the
underground, the Intake Shaft will be equipped with a hoist and cage system
for transportation of persons and material. The Exhaust Shaft will be equipped
with a Pocket Lift conveyor system to continuously convey the mined-out ore to
the surface. Both shafts are approximately 270 m deep.

Mining equipment selected for the Kola Project Mine includes a fleet of 7
electrically powered continuous miners. Ore haulage from the CMs to the feeder
breaker apron feeder will be done using electrically-powered Shuttle Cars,
with a rated payload of 30 t and a 250 m power supply cable.

Underground conveyor belts will be used for ore transportation to the shaft.
The belt conveyors are distributed in the haulages and into the working panels
near the CM working face. The ore will be placed on the belts from feeder
breakers that are fed by the Shuttle Cars. Belt conveyors will carry the ore
loaded by the feeder breakers to the ore bins. The ore is then conveyed from
the ore bins to the vertical conveyor (Pocket Lift) system located in the
Exhaust Shaft.

5.    Life of Project schedule

The LoM production schedule reported in the Optimised DFS is as summarized
below.

The project LoM production schedule, including tonnes of ROM, tonnes of MoP
product, and the average KCl grade of the Run-Of-Mine ("ROM") material, is
summarized in Figure 2.

The Life of Ore Reserves for the Kola Project is estimated at 23 years, and
full-scale production averaging approximately 2.1 million tonnes per annum of
MoP from Ore Reserves occurs for approximately 21 years post commissioning and
ramp up. During the exploitation of Ore Reserves, 9.7 Mt of Inferred Mineral
Resources are scheduled to be mined and processed. This represents
approximately 6.0% of the total amount of ROM material processed in the first
23 years. This portion of the Inferred Mineral Resources is at the periphery
of the Mineral Resources envelope and immediately adjacent to the Ore Reserves
and logically would be extracted in conjunction with the adjacent Ore
Reserves.

 

In preparing the production target and economic evaluation, each of the
modifying factors was considered and applied and the Company considers there
are reasonable grounds for the inclusion of Inferred Mineral Resources in the
production target for the Kola Project.

 

There is a low level of geological confidence associated with Inferred Mineral
Resources and there is no certainty that further exploration work will result
in the determination of Indicated Mineral Resources or that the production
target itself will be realized.

 

The Ore Reserves (Proved and Probable) and Inferred Mineral Resources
underpinning the production target have been prepared by a competent person in
accordance with the requirements of JORC 2012. Details of those Ore Reserves
and Mineral Resources are set out in this announcement (including, in relation
to the Ore Reserves, the details in Appendix B and Appendix C).

 

No Exploration Target material has been included in the economic evaluation
for the Kola Project.

 

 

Figure 2 - Life-of-Mine Production Summary of the Kola Mine

 

Kore Potash believes there is a strong potential for the LoM Production to be
extended beyond 23 years by upgrading a portion of the 340Mt of Inferred
Mineral Resources to Measured or Indicated resource, through further
exploration during operations.

 

 

 

6.    Hydrogeology

The DFS hydrogeological investigations have been used in the Optimised DFS and
there are no changes to the information or assumptions related to
hydrogeology. The hydrogeology test work that was carried out, is summarised
below:

1.   Identify sources of fresh water supply for construction and operations.

These tests concluded that process plant area water supply is available at
required rate of 150 m(3)/hr utilising 5 wells at a depth of 120 m. Similarly,
the required water supply at the mine site of 30 m(3)/hr can be supplied via 2
wells sunk to 120 m depth. Hydrogeological modelling indicates that extraction
of these quantities of water over the project life will not adversely impact
the aquifers and minor drawdown in the aquifers is expected over the life of
the project.

2.   Understand the risk that aquifer system poses to mining operations and
how        to mitigate this risk.

The risk of water ingress to the mining areas is a common risk in almost all
salt and potash mines. These mines are typically overlain by water-bearing
sediments. At operating potash mines in Canada and Europe, the hydrogeological
risk is considered higher in areas of disturbance of the stratigraphy,
referred to as geological or subsidence anomalies. At Kola, a detailed
understanding of the aquifers overlying the evaporite rocks, as well as of the
aquitards (or barriers to water flow), has been developed over a number of
years. The conclusions drawn following hydrogeological testing were:

o  A problematic water ingress is considered a low probability as no linear
faults have been identified and all potential subsidence features can be
accurately delineated using (proposed 50 m spaced line) 3D seismic surveying,
to add to the existing 186 km of seismic survey data over the Deposit.

o  No mining or shaft sinking is planned within areas of subsidence. In
addition, horizontal 'cover drilling' and ground penetrating radar ("GPR")
will be employed as forward-looking actions to improve understanding of ground
conditions in advance of mining and further mitigate the risk of intersecting
a structure or area of disturbance.

o  The mine design incorporates a 10-15 m minimum 'salt-back' barrier between
the mining area and the anhydrite aquitard, effectively reinforcing the
anhydrite member aquitard layer.

 

3.   Understand the impacts of groundwater composition and the aquifers on
the shaft

      sinking operation.

The results of this testing confirmed:

 

o  That ground freezing during shaft sinking will not be impacted by
hydraulic flow or high salinity in the deep aquifer. In fact, low
permeability, and low total dissolve solids ("TDS") and salinity in both
aquifers is to be expected, supporting the planned freeze-hole spacing and
comparatively low energy consumption for the ground freezing operation.

o  The presence of a thick Anhydrite Member (12 m) overlying the salt member
which acts as an aquitard and reduces risk of water inflow into the salt
member.

 

7.    Metallurgy and Process

Ore from underground is transported to the process plant via an overland
conveyor approximately 24 kilometers long.

A conventional potash flotation plant with a maximum designed production of
2.2 million tonnes per annum of MoP has been designed for the Kola Project. As
a result of the low Insolubles content, no separate process circuit is
required to remove Insoluble material.

The final MoP product is then transported 11 km by conveyor belt from process
plant to the marine export facility at the coast.

A schematic of the full process to extract ore and produce MoP product is
shown in Figure 3.

Figure 3: Process flow from mine to ship

The design strategy adopted delivers a Process Plant designed to produce 2.2
Mtpa of MoP at a KCl grade of 95.3 %w and that will accommodate the variety of
ROM feedstock characteristics expected to be encountered during the Life of
the project.

The optimised process design references the DFS metallurgical test work in
2017 and 2018. The description of the test work used in the Optimised DFS is
summarised below.

Characterisation tests were performed on pure seam samples (USS, LSS and HWS)
expected to be mined as part of the mine schedule. Composite samples of
multiple seams, prepared to be as representative as possible of the expected
range of Run of Mine Ore characteristics foreseen in the mine schedule, were
prepared from the seam samples.

The insoluble content of the samples was less than 0.5%w and close to 0.1%w in
the composite from the USS and LSS. The characterisation of both the composite
samples and the pure seam samples established that the KCl content in the
composite was 32.2%w.

A process plant KCl recovery rate of 89.9% has been used in the economic
evaluation.

8.    Marine Facilities

The marine facility used in the Optimised DFS was based on the DFS design. A
summary of the design is given below.

A trans-shipment arrangement has been designed whereby MoP for export is
loaded from a dedicated Jetty into self-propelled shuttle Barges (two units),
which then travel to the Ocean-Going Vessels ("OGVs") anchored 11 nautical
miles (20 km) offshore at a dedicated transshipment zone. The MoP is
transferred from the Barges to the OGVs using a Floating Crane Transhipper
Unit ("FCTU").

Transshipping was selected over direct ship loading from the export jetty. The
ocean depth along the coastline is shallow and it was not considered feasible
to construct the length of jetty required to facilitate direct ship loading.

To ensure sufficient year-round operational availability of the Jetty, a
breakwater structure has been designed to shelter the berthing area for Barge
loading operations.

The Jetty has been widened to accommodate both a Seawater Intake ("SWI") and a
Seawater Outfall ("SWO") system.

 

9.    Residue and Brine Disposal

The Kola Project's process residue is combined into a single waste stream
composed of the NaCl (the brine from product and salt de-brining - bulk of the
effluent) and the residue stream which originates from the insoluble
de-brining circuit within the Process Plant. The residue is collected in
onshore dissolution/dilution tanks and then discharged at sea via the SWO pipe
and diffuser. The discharge stream's dispersion characteristics comply with
the applicable environmental criteria.

Ecotoxicological test work of the expected discharge confirms that the
discharge at sea of the combined salt and insoluble tails stream does not
place undue stress on the marine environment.

No onshore tails storage facility is therefore required for the Kola Project.

10.  General Infrastructure

There have been no material changes to the mining, processing, export and
marine facility locations since the Optimisation Study in 2022.

a.    Mine Site - Infrastructure

The Mine Site is located near the village of Koutou and the current KP2
Exploration Camp. It is 24 km north and inland of the Project Process Plant
Site.

The sites can be accessed from Pointe Noire through the existing National Road
(Route Nationale) RN5 which crossses Madingo Kayes and then by driving into
RN6 as from Kilounga village.

The Mine Site surface facilities and infrastructure provides access and
support facilities for the Underground Mining operations.

No permanent living accommodation is planned at the Mine Site for the
Operational phase of the Project.

b.    Process Plant Site - Infrastructure

The Process Plant Site is located 11 km inland from the marine facilities,
next to the village of Tchizalamou, approximately 60 km northwest of Pointe
Noire. ROM ore is transferred from the Mine Site via the Overland Long
Conveyor ("OLC").

The Process Plant Site facilities and infrastructure produces granular MoP,
which is transferred to the Marine Facilities for export. The main
administration, control and support functions (Maintenance, Storage,
Logistics, Training, etc.) are also located within the Process Plant Site.

c.     Mining Complex & Off-Site - Infrastructure

The operation of the Kola Project's Mine and Process Plant sites are supported
by ancillary sites (Accommodation Camp and Solid Waste Management Centre) and
interconnecting infrastructures (Roads, Power, Water and Gas supply, and
Communications).

The permanent accommodation camp will be located approximately 3 km from the
Process Plant and will accommodate up to 950 people.

d.    Power

Operational electrical power is guaranteed from the RoC national grid. This
would require a 57 km long 220 kV transmission line to be built from the Mongo
Kamba II substation, situated north of Pointe Noire, to the Process Plant. The
power demand is estimated to be 25 MVA at the Mine Site and 50 MVA at the
Process Plant.

To reduce the Kola Project's environmental footprint, the Company initiated
discussions with a new local oil and gas producer in RoC. This potential new
supplier's project includes both gas and electricity. As a result of
preliminary negotiations, the Company received competitive rates, which were
used in the revised economics.

e.    Natural Gas

Initially, the natural gas needed for product drying was to be supplied by a
73-kilometer pipeline from the M'Boundi gas treatment plant. However, a recent
marketing decision by this potential supplier has reduced availability in the
country, as the supplier now plans to export at higher prices.

In the above context, the new local oil and gas producer (cited in the Power
paragraph above) stepped in to propose gas from the oilfield they are
developing. This potential supplier plans to start production before Kola
does.

f.     Water

Raw water will be supplied from wells located at the Mine Site (2 wells), the
process plant site (5 wells) and at the Accommodation Camp (4 wells).

11.  Environmental and Social Impact Assessment

The ESIA was prepared managed by SRK Consulting (UK) Limited's environmental
and social (E&S) team. SRK partnered with "Cabinet Management & Etudes
Environnementales S.A.R.L." ("CM2E"), which acted as the Congolese-registered
consultancy.

The Kola ESIA, initially approved on 10 October 2013, was amended to reflect
the design changes made to the Kola Project as part of the DFS and has been
amended to include the service corridors for a gas pipeline and overhead power
line. The application and terms of reference for amending the ESIA were
approved on 12 April 2018 by the Minister of Tourism and Environment.

The ESIA for the Kola Mining License was approved on 31 March 2020 granting a
25-year approval.

The change of location of the process plant, accommodation camp and some other
minor OLC track changes which occurred prior to the 2022 Optimization Study
require an ESIA update which shall be effected in the first half of the 2025
calendar year.

There have also been conflicting reports as to whether part of the
transshipment route between the proposed jetty and the offshore transshipment
location being converted into a marine reserve. If confirmed during the ESIA
update, this might require a small diversion of the route to be taken by
barges transporting the finished product to ocean-going vessels.

The Company shall carry out their construction operations In compliance with
the environmental and social management plan as part of the approved ESIA and
will be subject to Regulator's environmental management compliance audits.

12.  Potash Marketing

Kore's potash marketing strategy recognises the supply opportunities arising
from MoP market growth in Brazil, the project's proximity to Brazil and
African markets and the cost competitiveness of the Kola Project. The DFS,
Optimisation Study and Optimised DFS demonstrate that the Kola project can
deliver MoP into Brazilian and ports on the west coast of Africa at lower cost
than all other international suppliers. Figure 4 shows a comparison of
delivered MoP costs to Brazil.

 

Figure 4 - Brazil delivered MoP cost comparison

Source: August 2024 Argus Media Marketing Report. Kore Potash CFR Cost Brazil
calculated per Table 8.

In August 2024, the Company commissioned a MoP market study and specification
marketing report ("Argus Media Marketing Report") from one of the leading
global consultancy firms, Argus Media Group. According to this report, Kore
Potash is ideally located for exports to Brazil from an inland and seaborne
freight perspective. The Argus Media Marketing Report indicates that the
Company has the shortest distance to the Paranagua port in Brazil and that, in
2023, 59% of Brazil MoP imports entered via three key ports: Santos, Paranagua
and Rio Grande. The total estimated approximate 4,600km transportation
distance from the Kola mine is the shortest distance among all key exporting
mines globally to Paranagua, Brazil. While Canpotex is the largest exporter to
Brazil in the year 2023 and K+S fifth largest importer in 2023 via Vancouver,
Canada, to Paranagua, port total transportation distance is approximately
12,000km, which is almost triple the distance from the Kola Project mine.

The design of the processing plant allows Kore to produce red MoP granular for
the Brazil market.

Potash market research specialist Argus Media provided the Company with
historical and forecast pricing trends for the MoP CFR Brazil benchmarks over
the period up to 2047 (see Figure 5 below). The Argus Media Marketing Report's
estimates are provided in MoP CFR Brazil Real US$/t 2023 values for calendar
years 2024 to 2047. The Company considers that it is reasonable to apply Argus
Media's estimates over that period given Argus Media is independent and
reputable international market research group which has deep knowledge of the
current potash market and its trends. After 2047, prices are indexed by the
Company using a US$2/t incremental annual increase to the 2047 price as in the
Argus Media Marketing Report. As a result, the estimated forecast average
granular MoP price is US$449/t (see Appendix A, section 12) for the life of
the mine operations (with the US$449/t being the simple average of the
forecast price in each year of production over the 23 years of scheduled
production, where the forecast price in each year to 2047 is that in the Argus
Media Marketing Report and for each year after 2047, is the forecast 2047
price with a US$2/t incremental annual increase applied in each year, as
discussed above).

It should be noted that current red granular MoP CFR Brazil prices are around
c.US$300/t, which is less than the average of the granular MoP prices used in
the Optimised DFS (being US$449/t). There is no guarantee that the forecast
annual granular MoP prices used in the Optimised DFS will be realised and
lower realised prices will adversely affect the financial performance of the
Kola Project as demonstrated in the sensitivity analysis in section 14(b)
below. The price at which Kola Project NPV(10%) is greater than zero is flat
c.US$271/t MoP CFR  for the life of the mine operations. Please also refer to
the Cautionary Statement on page 3 of this announcement.

 

Figure 5 - Historical and forecast MoP CFR Brazil Real US$/t 2023. Extract
from Argus Media Marketing Report

 

As stated in the Argus Media Marketing Report MoP prices are currently
reaching their lowest levels over the past 5 years. Short-term pricing in the
next 12 months is based on the current market developments, such as weather
events, planned or unplanned plant outages and market participant sentiment.
Argus Media sees limited upside in medium-term (5 - 7 years) as the market
reaches floor around the year 2028 with the ramp-up of BHP's Jansen project in
Canada. The potash market is facing transition to supply surplus with
recovering Russian and Belarusian and new capacity in Canada and Laos. Argus
Media believes that the long-term price of MoP is dictated by the industry's
Long-Run Marginal Cost ("LRMC") for adding new potash supply.

Total LRMC is the sum of:

·    Mine capital costs, adjusted for location and the weighted average
cost of capital, amortised over the mine's life span;

·    Mine operating costs, including fuel, labour, materials, sustaining
capital and royalties; and

·    Value-in-use considerations, crediting or debiting total cost to
consider access to target markets.

The LRMC base year is then inflated by Argus Media over the forecast period to
provide their long-term price forecast. Each LRMC element is inflated using
the appropriate inflator from Argus Media's forecasts of fuel, energy and
macro inflators. The LRMC is a long-term trend forecast, meaning Argus Media
expects short-term oscillations around the calculated LRMC, driven by factors
such as weather and supply disruptions that cannot be predicted this far in
advance. Russian MoP development is no longer included in the LRMC set. As the
war in Ukraine continues, Argus Media assumes the impact on Russia as a
destination for investment will be more prolonged and this is reflected in a
higher-risk premium. Argus Media's view is that incremental tonnage from
Canada and Israel are expected to dictate long-run LRMC.

13.  Capital and Operating Costs

a.    Capital Cost

The pre-production capital cost for the Kola Project is now estimated at
US$2.07 billion (nominal basis), which includes a fixed price EPC contract of
US$1.929 billion and US$141 million owner's costs. The breakdown of the EPC
capital cost is presented in Table 7 below.

The EPC fixed price is of significant benefit to the Company, as it minimises
the risk of cost overruns. Of the total Contract Price, approximately US$708.9
million is allocated for building transportation links and utility pipelines,
which will make the Kola Project self-reliant without depending on state
infrastructure except for the RoC national grid. The Company considers this to
be a significant advantage compared to other potash projects worldwide. To
accelerate progress during the financing process, Kore Potash and PowerChina
have committed to an Early Works Agreement ("EWA"), which forms part of the
EPC and is targeted to be completed by the end of June 2025.

The owner's costs during the 43-month construction period are projected to be
approximately US$141 million. The EPC also includes provisions for penalties
in the event of delayed completion and non-compliance to performance metrics.

Table 7 - Breakdown of Contract Price

 

 Description                                                 Amount (US$ million)
 Underground Works (shafts and mine face preparation)        319.7
 Processing plant and auxiliary facilities                   609.6
 Surface over land belt conveyor transportation (OLC)*       229.3
 Marine Works*                                               223.1
 Roads*                                                      111.3
 Utilities (electricity overhead line & gas pipeline) *      145.2
 Administration facilities                                   58.9
 General items                                               231.9
 Total                                                       1,929.0

 

* Total US$708.9 million for transportation and related utilities.

 

Sustaining Capital Costs of US$924 million have been included in the financial
analysis, which is equivalent to US$13.06/t MoP and disclosed in Table 8
below.

Sustaining capital costs cover expenditures required to ensure the operation
can sustain the production at nameplate capacity. These costs include overhaul
parts and labour, replacement of equipment, maintenance of infrastructures
(road, jetty etc.), shut down costs, additional continuous miner and
additional underground conveyor costs, and the inspection and maintenance of
the trans-shipment vessels

b.    Operating Cost

The Operating Costs are expressed in US dollars on a real basis and are based
on average annual production of 2.2 Mtpa of MoP over the life of mine. All
costs have been prepared on an owner operated basis and are shown in Table 8.

Table 8 - Summary of Operating Costs

 Cost Category                               Real costs
                                             (US$/t MOP)
 Opex
 Mining Cost                                 25.17
 Process Cost                                29.08
 Other Cost                                  20.69
 Mine Gate Operating Costs                   74.94
 Sustaining Capex                            13.06
 Product Realisation Charges and Allowances  4.08
 Royalties                                   11.74
 Ex Works Cost                               103.81
 Logistics to FOB point                      5.81
 Ocean Shipping                              18.58
 CFR Cost (Landed in Brazil)                 128.19

14.  Economic Evaluation

a.     Summary Economics

The economic evaluation delivers a post-tax NPV(10%) (real 2024) of US$1.7
billion and a real ungeared IRR of 18% on a 90% attributable basis. The
evaluation is based on a forecast average MoP granular price of US$449/t MoP
CFR Brazil (real 2024) as outlined in section 12 above.

 

The key assumptions underpinning the economic evaluation are as follows:

·      Construction start date: 1 January 2026.

·      23-year project life from first production based on depletion of
Ore Reserves.

·      2.2 Mtpa average production of MoP.

·      Granulated MoP represents 100 % of total MOP production and
sales.

·      All cashflows are on a real 2024 basis

·      NPVs are ungeared and calculated after-tax applying a real
discount rate of 10%.

·      NPVs are calculated at a base date of 1 January 2026 prior to the
potential dates for commencement of project construction

·      Fiscal regime assumptions are aligned with the recently finalised
Mining Convention:

o   Corporate tax of 15% of taxable profit with concessions for the first 10
years of production (0% for the first 5 years and 7.5% for years 6 - 10).

o   Mining royalty of 3% of the Ex-Mine Market Value (defined as the value
of the Product (determined by the export market price obtained for the Product
when sold) less the cost of all Mining and Processing Operations, all costs of
Transport (including any demurrage), and all insurance costs).

o   Exemption from withholding taxes during the term of the Mining
Convention.

o   Exemption from VAT and import duty during construction; and

o   Congo Government receives 10% of the shares in KPM which owns the Kola
Project.

The forecast project cash flow on a 90% attributable basis for 23 years of
production is illustrated in Figure 6.

 

Figure 6 - Project Cash Flow Forecast (real 2024) on a 90% Attributable Basis

 

 

b.    Sensitivity Analysis

Kola Project returns have been calculated on a real 10% post-tax unleveraged
basis with the key financial results and assumptions provided in Table 1.
Figure 7 below shows the sensitivity to the four variables that have the most
impact on the real post-tax NPV(10%) and 90% attributable basis (reflecting
Kore's future holding of 90% and the RoC government 10%) of the project, in
descending order of most sensitive to least sensitive. No capital cost
sensitivities were included as the EPC is a fixed price contract. The
financial outcomes of the project are most sensitive to changes in revenue
and, therefore, future MoP prices as well as KCl recovery in the process
plant.

 

Figure 7 - NPV real 10% post-tax US$'000 movement sensitivities*.

 

 

* KCl recovery sensitivities are in incremental steps of 5%, 10% and 15%
increases or decreases relative to the base of 89.9%; increases are: +5% =
94.9%, +10% = 99.9%, +15% = 100% maximum. All other sensitives are % changes
on the base number.

 

15.    Project Funding

As announced on 6 April 2021, a non-binding memorandum of understanding was
signed with Summit to arrange the full financing required for the construction
of the Kola Project ("Summit MOU").

In line with this memorandum of understanding, following signing the EPC,
Summit is expected to deliver a non-binding financing term sheet within three
months. This term sheet will be subject to the completion of detailed and
definitive legal documentation.

The Company confirms its confidence in the Summit Consortium as a financier
for the construction of the Kola Project. This confidence is based on the
Company having worked with the Summit Consortium for the past 10 years and
their track record in assisting with financing for Kore Potash including
sourcing the approximately US$40 million equity investment provided by the
Oman Investment Authority ("OIA") and Sociedad Quimica y Minera de Chile S.A.
("SQM") in 2016. OIA and SQM are among top three largest shareholders of the
Company who together hold 27.58% in the issued share capital of the Company.

The material terms of the Summit MOU were set out in the 6 April 2021
announcement and are reaffirmed as follows:

·    The Summit MOU outlines a roadmap to optimise the capital design to
fully finance and construct Kola via a mix of debt and royalty financing.

·    Under the proposed financing arrangements, the RoC Government will
retain their 10% shareholding in Kola.

·    Under the Summit's proposed financing structure, the Company will not
contribute to the capital needed to build the Kola Project and will retain a
90% equity interest in Kola.

The Company retains the right not to accept any finance proposal presented by
Summit and there is no guarantee that any proposal or legally binding
agreement will be forthcoming. The Company provides no assurance to
shareholders that the Summit Consortium will provide the financing required on
terms which are acceptable to the Company. If the Summit Consortium does not
provide an acceptable financing package leading to binding legal documents,
the Company will need to explore other debt, equity and structured finance
alternatives having regard to then prevailing capital market conditions.

The Company expects any financing provided by the Summit Consortium to be
subject to the Summit Consortium being granted full security over the Kola
Project, however (as noted above) the full terms of any financing proposal
from the Summit Consortium (including any security package) will be subject to
further discussions.

As previously announced on 30 January 2025 the Summit Consortium was expected
to deliver this financial proposal by the end of February 2025. Due to delay
in publication of the Kola Project Optimised DFS update the new expected
delivery date of the financial proposal is now before the end of March 2025.

The Company confirms the Summit Consortium is not a related party of the
Company.

Further details about the financing arrangements will be notified to the
market in accordance with the Company's continuous disclosure obligations

 

 

 

Appendix B: Summary of Information required under ASX Listing Rule 5.9.1 (Ore
Reserves), Listing Rule 5.16.1 (production target) and Listing Rule 5.17.1
(forecast financial information derived from a production target).

 

Pursuant to ASX Listing Rules 5.9.1, 5.16.1 and 5.17.1, and in addition to the
information contained in the body of this release, the Company provides the
following summary information.

 

Kola Project Ore Reserves and related production target and forecast financial
information derived from the production target

 

Summary of Material Assumptions

 

Material assumptions relating to the Kola Project are summarised below:

·      Production life - LoM of 23 years at an average annual production
of 2.2 Mtpa MoP production. The production life fully depletes Ore Reserves
and incorporates a portion of Inferred Mineral Resource into the production
target.

·      Product pricing - Potash market research specialist Argus Media
provided the Company with historical and forecast pricing trends for the MoP
CFR Brazil benchmarks over the period up to 2047 (see Figure 5 above). Kola's
proposed mine life covers the period from 2029 through to 2052 (23 years). The
Argus Media Marketing Report's estimates are provided in MoP CFR Brazil Real
US$/t 2023 values for calendar years 2024 to 2047. After 2047, prices are
indexed by the Company using a US$2/t incremental annual increase to the 2047
price as in the Argus Media Marketing Report. As a result, the estimated
forecast average red granular MoP price is US$449/t for the life of the mine
operations. For more details on product pricing refer to Section 12.

·      MoP Product - The process design is based on a single product
type, Red Granular MOP. (The MoP produced will comprise at least 95.3% KCl,
with a maximum of 0.2% Mg and 0.3% Insolubles).

·      Project duration - A project execution duration of 43 months was
specified in the EPC contract.

·      Project Capital - The total nominal Project Capital of US$2.07
billion includes both EPC costs and owner's cost.

·      Working capital assumptions - Working capital based on 30 days
Debtors and Creditors, 60 days Stores.

·      Operating cost - mine gate operating cost of US$74.94/t and CFR
cost of US$128.19/t were reported in the Kola Project Optimised DFS update.

·      Shipping costs - LoM Shipping costs (trans-shipment and sea
freight) of US$24.38 /MoP t were based on updated ocean freight quotations
received in 2024.

·      Fiscal parameters - The mining convention between the Company and
the Republic of Congo specifies the fiscal parameters summarised below:

o  Company tax rate (15%),

o  Initial tax rates (5 years at 0% + 5 years at 7.5%)

o  Royalties (3% of revenue) (Mining Convention)

o  Government free carry (10%) (Mining Convention)

o  Other minor duties and taxes (Mining Convention)

 

Criteria for Mineral Resource and Ore Reserve Classification

 

The criteria for Mineral Resource and Ore Reserve Classification remain
unchanged from the DFS.

 

The Ore Reserve estimate is based on the Kola Sylvinite Indicated and Measured
Mineral Resources reported by Met-Chem DRA in accordance with the JORC Code
(2012 edition) and confirmed by the Company on 27 Feb 2025.

 

Drill-hole and seismic data were relied upon in the geological modelling and
grade estimation. Across the deposit the reliability of the geological and
grade data is high. Grade variation is small within each domain reflecting the
continuity of the depositional environment and 'all or nothing' style of
Sylvinite formation.

 

Drill hole data spacing determines confidence in the interpretation of the
seam continuity and therefore confidence and classification; the further away
from seismic and drill-hole data the lower the confidence in the Mineral
Resource classification. In the assigning confidence category, all relevant
factors were considered, and the final assignment reflects the Competent
Person's view of the deposit.

 

Table B1: Summary of Criteria used for the Classification of the Kola Mineral
Resource

 

            Drill-hole required                          Seismic data required                                                        Classification extent
 Measured   Average of 1 km spacing                      Within area of close spaced 2010/2011 seismic data (100 - 200 m spacing)     Not beyond the seismic requirement
 Indicated  1-1.5 km spacing                             1 to 2.5 km spaced 2010/2011 seismic data and 1 to 2 km spaced oil industry  Maximum of 1.5 km beyond the seismic data requirement if sufficient drill-hole
                                                         seismic data                                                                 support
 Inferred   Few holes, none more than 2 km from another  1-3 km spaced oil industry seismic data                                      Seismic data required and maximum of 3.5 km from drill-holes

 

The Measured and Indicated Mineral Resources for sylvinite are hosted by 3
layers (or 'seams') which are from uppermost; the Hanging Wall Seam (HWS), the
Upper Seam (US) and the Lower Seam (LS), each separated by rock-salt (a
rock-type typically comprised of >95% halite).

 

Magnesium and insoluble content are considered deleterious but are present in
only very small amounts in the ore (average of 0.07% and 0.14%respectively).

 

The Mineral Resource Estimate was delivered to the Ore Reserve consultants in
the form of a standard block model, blocks having dimensions 250 x 250 x 1 m,
each block having a KCl grade, a density, and magnesium and insoluble content.

 

The Mineral Resources are inclusive of the Ore Reserves i.e. the Ore Reserves
are the mineable part of the Mineral Resources after the application of
technical, economic and other modifying factors.

 

Areas of potential structural disturbance, referred to as geological anomalies
were excluded from the Measured and Indicated Mineral Resource. They were
identified from seismic data as is standard in potash mining districts
elsewhere.

 

A 10% CoG was used in the Mineral Resource Estimate.

 

 

Mining Method and assumptions

 

The mining method and assumptions remain unchanged from the DFS.

 

Mining factors and assumptions have been derived from the historical
information available for mature potash mines, and the current best mining
practices. The Kola orebody will be mined using conventional underground
("UG") mining method consisting of room and pillar in a 'chevron' (or
herringbone) pattern, with Continuous Miners ("CM") mining machines of the
drum-cutting type.

 

Most of the mining will be on one level only where only the US will be
extracted. In some areas, both the US and the LS will be mined, in which case
the LS will only be mined after the US. In other areas only the HWS will be
mined.

 

In determining the Ore Reserves, a minimum mining height of 2.5 m was selected
based on capability of the selected CM which is also capable of mining up to
6 m. Areas of the Mineral Resource with a seam height of less than 2.5 m were
excluded from the Ore Reserves.

 

The mine design is typical of potash mines, having 4 entries for accessing
panels. Each drive will typically be 8 m wide and 3 m to 6 m high depending on
the seam height. The typical configuration for the chevron pattern is an angle
of 65 degrees from the middle entry, and length of 150 m approximately.

 

The Mine design relies on geotechnical modelling, carried out in FLAC 3D
software. The modelling was based on geotechnical test-work carried out on
representative core samples from the sylvinite seams and host rocks (rock-salt
and lesser carnallitite). The geotechnical modelling established that the mine
design is stable over the LoM and includes the following geotechnical
parameters:

 

·      Where both the US and LS seams are to be mined, the support
interval between the US and LS must be at least 3 m thick.

·      An 8 m wide pillar between two consecutive production rooms (of 8
m each).

·      A 50 m wide pillar between two production panels. Similarly, a 50
m wide pillar will be left in place between the side of the production panel
and the main haulage access drift.

·      The interval of rock-salt between the mine openings and the floor
of the overlying anhydrite member is referred to as the 'salt back'. This is
typically over 30 m but is less in some areas. The DFS design allows that it
may be a minimum of 15 m unless the Anhydrite Member is well developed where
it may be 10 m. This is based on the results of the geotechnical model.

·      A stand-off distance of 20 m radius from the exploration holes.

·      A stand-off distance of 30 m radius from class 2 geological
anomalies and 60 m radius from class 3 geological anomalies.

·      A pillar of 300 m in radius around the exhaust and intake shafts.

 

Based on the selected CMs, it is anticipated that a good cutting selectivity
would be achieved, and that a maximum of 0.2 m of dilution material above
and/or below the potash seam is likely. Carnallitite is present in the floor
of the seam in some areas. The roof is always of rock-salt.

 

On average, the dilution material is equivalent to approximately 10% of the
tonnage of the Ore Reserves. Dilution material was assigned a grade of 3% KCl
if rock-salt and 0% KCl if Carnallitite.

 

Based on the configuration of the proposed mining layout, and the anticipated
fleet of mining equipment, it is assumed that the mining recovery in the
different extraction chambers will be 90% on average (i.e. mining losses will
be 10%). This considers the mining action which will lead to some losses such
as material being excavated and left in the production chamber, or mineralized
material left in the floor or roof, etc.

 

The Global extraction ratio is 30% (25% in the LS, 33% in the US and 28% in
the HWS). This is after the removal from Ore Reserves of all pillars (pillars
around the geological anomalies, the barrier pillars, the shaft pillar, the
pillars between chevrons and main access drifts), the stand-off distance
around boreholes, mining losses and the exclusion of sylvinite <2.5 m
thick.

 

Two vertical shafts, each of 8 m internal diameter, will be sunk at a central
location in the Ore Reserves, to provide access to the underground. The intake
shaft will be equipped with a hoist and cage system for transportation of
persons and material, while the exhaust shaft will be equipped with a vertical
conveyor system to convey the mined-out ore to the surface. Both shafts are
approximately 270 m deep.

 

Ore haulage from the CMs to the feeder breaker apron feeder will be done using
electrically-powered Shuttle Cars.

 

Underground conveyor belts will be used for ore transportation in all the
areas of the mine. The belts are distributed in the mains and submains and
ultimately in the working panels near the CM working face. The ore will be
placed on the belts from the feeder breakers that were fed by the shuttle
cars.

 

The belt conveyors will carry the ore loaded by the feeder breakers to the ore
bins. Then the ore is conveyed from the ore bins to the Pocket Lift system
located in the exhaust shaft.

 

Processing Method and Assumptions

 

The changes to the processing method and assumptions arising from the
Optimisation Study are as follows.

 

·      The product will be granular MoP K60, comprising at least 95.3%
KCl. The Optimisation Study design allows for the production of a single
product, red granular MOP.

·      The process flow sheets were optimised to produce a maximum of
2.2 Mtpa of MoP, at 95.3% KCl purity, with a minimum KCl recovery of 89.9% of
the KCl content in the ROM fed to the Process Plant.

 

·      Eight key areas of process design were changed in the
Optimisation Study

 

o  The crushing circuit was changed from 3 stage crushing to 2 stage crushing

o  The mixing tanks post crushing were replaced with a combination of screens
and tanks

o  The scrubbing capacity has been reduced

o  The thickening capacity has been increased

o  Column cells have been replaced with floatation cells

o  Re-grind flows have been re-routed

o  Tailings centrifuges has been replaced with a belt filters

o  Compaction circuit has been simplified

 

A conventional flotation process will be utilised for potash concentration.
This method is well established and is the most widely used method in the
potash industry.

 

The metallurgical test work campaigns were based on representative core
samples of the three seams, collected from the exploration drill hole cores.
They comprised US (114.5 kg), LS (102.0 kg) and HWS (10.3 kg). All test work
was carried out at the Saskatchewan Research Council ("SRC") laboratory in
Saskatoon, Canada.

 

Two metallurgical test work campaigns were conducted during the DFS in 2017
and 2018. The main philosophy of the first DFS test work campaign was to
prepare representative test feedstocks for each seam, confirm KCl liberation,
characterize the feedstock, perform flotation tests, optimize the operating
conditions, optimize reagent consumption for optimum KCl recovery and grade
performance, perform a sensitivity test on flotation.

 

The objective of the second test work campaign was to optimize the flotation
process and improve the plant recovery from the initial flow sheet. The
results of this second test work campaign demonstrated that the new flotation
process performed above the project performance minimum target.

 

Magnesium and insoluble material are considered deleterious. The extremely low
content of these materials in the ore mean that their removal is relatively
straightforward. Insoluble material is removed by attrition scrubbing and
magnesium removed by brine purge.

 

Cut-off Grades

 

The cut off grades remain consistent with the original DFS Ore Reserves.

 

A CoG of 10% KCl has been calculated within the process to state Ore Reserves.
The CoG calculation included all operating costs associated with the
extraction, processing and marketing of ore material. The cut-offs are based
on a MoP price of US$250 per tonne of MoP. Inputs to the calculation of CoG
included:

 

o  Mining costs

o  Metallurgical recoveries

o  Processing costs

o  Shipping costs

o  General and administrative costs

 

All sylvinite of the Measured and Indicated Resource is above 9.9% KCl (the
Ore Reserve calculated CoG), therefore all the Measured and Indicated
Sylvinite Resources have been considered for the Ore Reserve Estimate by
application of the other modifying factors.

 

The uniformly very low content of deleterious elements (magnesium and
insoluble material) meant that these did not require consideration in the CoG
determination.

 

Cost Estimation Methodology

 

Capital Cost:

·      The pre-production nominal capital cost for the Kola Project is
now estimated at US$2.07 billion, which includes a fixed price EPC contract of
US$1.929 billion and US$141 million owner's costs.

Operating Cost:

·      Operating Cost covering the Life of Mine (23 years) was estimated
in US dollars and reported in the Kola DFS in 2019. They include costs for
Electric power, Fuel, Gas, Labour, Maintenance parts, Operating Consumables,
General and Administration costs and Contract for Employee Facilities.

·      These 2019 Operating Costs were all revised to reflect current
conditions, as follows:

o  Exchange rates (vs US$) for Euro, British Pound, Canadian Dollar, South
African Rand, and Congolese Franc (Central African Franc) were updated;

o  Production split was updated to 100% red granular MOP;

o  Plant KCl recovery was reduced from 91.9% to 89.9%;

o  Plant operating hours were updated according to PC's assumption of 7,920
h/y;

o  Electricity costs were updated according to current budgetary pricing;

o  Natural gas costs were updated according to current budgetary pricing;

o  Labour costs were escalated a flat 10%, in consultation with third-party
labour experts;

o  All other operating costs were escalated a flat 25% to simulate US CPI.

·      Transshipment costs were supplied by an experienced marine
broker.

·      Ocean Freight Transportation estimate produced were based on work
done by the marine brokers.

·      Mine Closure cost is estimated in accordance with the Conceptual
Rehabilitation and Closure Plan developed by SRK Consulting during the DFS,
assuming a Mine Closure duration of 24 months (2 years).

·      For the purpose of Operating Cost and Sustaining Capital, the
quantities of equipment, materials and works were directly assessed from the
Material Take-off prepared within the framework of the Kola DFS.

·      State mineral royalties of 3% of Net Revenue were applied

·      Measured Mineral Resources were used for the estimation of the
Proved Ore Reserves. Indicated Mineral Resources were used for the estimation
of Probable Ore Reserves.

·      The conversion of Measured and Indicated Mineral Resource to
Proved and Probable Ore Reserve reflects the Competent Person's view of the
deposit.

·      40.6% of the Ore Reserves are classified in the Proved category
and 59.4% of the Ore Reserves are classified in the Probable category

 

Material Modifying Factors

 

·      Status of Environmental Approvals

The Kola ESIA, initially approved on 10 October 2013, was amended to reflect
the design changes made to the Kola Project as part of the DFS and has been
amended to include the service corridors for a gas pipeline and overhead power
line. The application and terms of reference for amending the ESIA were
approved on 12 April 2018 by the Minister of Tourism and Environment.

 

The ESIA for the Kola Mining License was approved on 31 March 2020 for 25
years.

 

The proposed new position of the process plant resulting from the Optimisation
Study creates a requirement to issue an addendum to the ESIA. It is intended
that work on this addendum will commence in the second half of 2025.

 

 

·      Status of Mining Tenements and Approvals

Kore has a 97%-holding in SPSA, a company registered in the RoC. The remaining
3% in SPSA is held by "Les Establissements Congolais MGM" (RoC). SPSA in turn
has a 100% interest in its two ROC subsidiaries, Kola Potash Mining SA ("KPM")
and Dougou Potash Mining SA ("DPM").  The Mining Convention includes a
requirement for 10% of free-carry shares in KPM and DPM to be assigned to the
Government of the Congo. The Company is currently awaiting Government
instructions as to the share transfer process.

 

The Kola Deposit is within the Kola Mining Lease which is 100% owned by KPM

 

o  In May 2008, a non-exclusive Prospecting Authorisation was granted to
Sintoukola Potash covering an area of 1,436.5 km(2). On 13 August 2009, this
was changed to a "Permis de Recherches" (Exploration Permit) named 'Permis
Sintoukola' under decree No. 2009-237 giving the Company exclusive rights to
explore.

o  On 27 November 2012, the first renewal of the permit was made, by decree
No. 2012-1193 and reduced in size to 1,408 km(2).

o  On the 9 August 2013, a Mining Lease for Kola issued under decree No.
2013-312, totaling 204.52 km(2) falling entirely within the Exploration
Permit.

 

·      Déclaration d'Utilité Publique or "DUP"

Exclusive land acquisition rights have been granted to the Project company for
plant development through ministerial order gazetted on 30 August 2018 (the
"Déclaration d'Utilité Publique" or "DUP") valid for three years and
renewable once for a two-year period.

 

As a result of the optimization of the processing plant and camp location, a
new DUP process needs to be initiated with the approval and support of the
Government after receipt and acceptance of the financing proposal from Summit.
A subcontractor with prior experience on the previous DUP is awaiting the
greenlight of Kore to start the work.

 

·      Other Governmental Factors

The Company entered into a mining convention with RoC government on 8 June
2017 and it was gazetted into law on 7 December 2018. The Mining Convention
provides certainty and enforceability of the key fiscal arrangements for the
development and operation of the Kola Project. This includes clarifying import
duty and VAT exemptions and agreed tax rates during mine operations. The
Mining Convention provides strengthened legal protection of the Company's
investments in the RoC through the settlement of any disputes by international
arbitration.

 

Infrastructure Requirements for Selected Mining, Processing and Product
Transportation to Market

 

The project infrastructure is comprised of the mine-site (shaft and offices),
the process plant 24 km from the mine and a product and marine export facility
at the coast (at Tchiboula), the 34 km infrastructure corridor between these
(including the overland conveyor, service road and power line), the gas line
from M'boundi gas field, overhead line from the MKII substation, the
accommodation and administrative camp and the transshipment facilities.

 

Changes to the infrastructure requirements that arise from the Optimisation
Study and Optimised DFS, and are thus different from the DFS are summarised
below.

 

·      The process plant position has been moved 11 km inland which has
allowed optimisation of the foundation design, the resultant infrastructure at
the coast consists of the product storage building and marine export
facilities. The design of the barge loading jetty has also been optimised.

·      Road access to the Kola Potash Project sites will be via the
existing Route Nationale 5 (RN5). Two external access roads will be built,
which are respectively connected from RN5 to the mining site and from RN5 to
the mineral processing site and living quarter, with a length of 2.0 km and
4.3 km respectively. Two maintenance roads for long-distance belt conveyors
will be built. One of the roads for RoM belt conveyor maintenance is about
24.0 km, connecting Koutou camp and the mineral processing site. The other
road is for MOP belt conveyor maintenance,

·      Raw Water will be supplied from wells located at the Mine Site
and at the Accommodation Camp close to the Process Plant Site.

·      The Accommodation Camp has been sized for a capacity of 950 beds
and will be located about 2 km away from the Process Plant

·      Electrical Power will be sourced from the ROC national grid. A 57
km long 220 kV transmission line will be built from the Mongo Kamba II
substation north of Pointe Noire to the Process Plant Site. A second 34 km
long 220 kV transmission line will be built from the Process Plant Site to the
Mine Site and the marine facility at the coast.

·      The Natural Gas needed for product drying will be supplied by a
local Oil and Gas producer who has plans to build a gas treatment plant some
35 km away from the Kore processing plant. The same company is also planning
to supply electricity to the Kola Project from the same offtake point. This
will be an interesting option to the Mongo Kamba II substation as it has a
lower environmental impact.

 

The infrastructure requirements that have not been modified in the
Optimisation Study or Optimised DFS, and thus remain the same as the DFS are
summarised below.

 

·      Ongoing operational labour will be a combination of permanent
employees, permanent contract services, and part-time contract services for
intermittent needs.  The total requirement for permanent employees is
expected to be 731.  Local labour resources will be used for the majority of
labour requirements, while some selected positions are planned as expat roles.

·      The Kola Potash Project intends to export up to 2.2 Mt MoP to
world markets each year. A transshipment solution has been developed, whereby
MoP for export is loaded at a dedicated jetty onto self-propelled shuttle
barges (two units), which will then travel to OGVs anchored 11 nautical miles
(20 km) offshore in a dedicated transshipment area. The cargo will be
transferred from the Barges to the OGVs using a Floating Crane Transhipper
Unit ("FCTU").

 

 

Appendix C: JORC 2012 - Table 1, Section 4 Ore Reserves

 

The Company has relied upon its previously reported information, in particular
the announcement of 27 Feb 2025, in respect of the matters related to sections
1, 2 and 3.

 

The Company confirms that the information in sections 1, 2 and 3 has not
changed since it was last reported and has been included in Appendix D of this
announcement for compliance with ASX requirements and ease of reference.

 

Section 4 Estimation and Reporting of Ore Reserves

(Criteria listed in section 1, and where relevant in sections 2 and 3, also
apply to this section)

 Criteria                                                  JORC Code explanation                                                            Commentary
 Mineral Resource estimate for conversion to Ore Reserves  Description of the Mineral Resource estimate used as a basis for the             The Ore Reserves are  based on the Indicated and Measured Mineral Resource
                                                           conversion to an Ore Reserve.                                                    estimate for sylvinite carried out by Met-Chem DRA and reported in accordance

                                                                                with the JORC Code (2012 edition), confirmed by the Company on 27 Feb 2025.
                                                           Clear statement as to whether the Mineral Resources are reported additional

                                                           to, or inclusive of, the Ore Reserves.                                           The Measured Mineral Resource is 216 Mt with an average grade of 35.0% KCl.
                                                                                                                                            The Indicated Mineral Resource is 292 Mt with an average grade of 35.7% KCl.

                                                                                                                                            The total combined Measured and Indicated Mineral Resources are 508 Mt with an
                                                                                                                                            average grade of 35.4% KCl.

                                                                                                                                            The Measured and Indicated Mineral Resources for sylvinite are hosted by 3
                                                                                                                                            layers (or 'seams') which are as follows from uppermost; the Hanging Wall
                                                                                                                                            Seam, the Upper Seam and the Lower Seam, each separated by rock-salt (a
                                                                                                                                            rock-type typically comprised of >95% halite).

                                                                                                                                            Magnesium and insoluble content are considered deleterious but are present in
                                                                                                                                            only very small amounts in the ore (average of 0.07% and 0.14% respectively).

                                                                                                                                            The Mineral Resource Estimate was delivered to the Ore Reserve consultants in
                                                                                                                                            the form of a standard block model, blocks having dimensions 250 x 250 x 1 m,
                                                                                                                                            each block having a KCl grade, a density, and magnesium and insoluble content.

                                                                                                                                            The Mineral Resources are inclusive of the Ore Reserves (i.e. the Ore Reserves
                                                                                                                                            are the mineable part of the Mineral Resources after the application of
                                                                                                                                            technical, economic and other modifying factors.)

                                                                                                                                            Areas of potential structural disturbance, referred to as geological anomalies
                                                                                                                                            were excluded from the Measured and Indicated Mineral Resource. They were
                                                                                                                                            identified from seismic data as is standard in potash mining districts
                                                                                                                                            elsewhere.)

                                                                                                                                            A 10% cut-off grade was used in the Mineral Resource Estimate.
 Site visits                                               Comment on any site visits undertaken by the Competent Person and the outcome    A site visit was conducted by the Competent Person for the Ore Reserve
                                                           of those visits.                                                                 Estimate between June 26 to June 28, 2017. The visit included exploration camp

                                                                                inspection, core viewing, site of shafts and process plant, access route from
                                                           If no site visits have been undertaken indicate why this is the case.            Pointe Noire. The site visit supported the findings of the Competent Person.

 Study status                                              The type and level of study undertaken to enable Mineral Resources to be         Prior to signing an EPC agreement, two studies have been completed by the
                                                           converted to Ore Reserves.                                                       Company: the Kola Definitive Feasibility Study ("DFS") in January 2019 and the

                                                                                Kola Project Optimisation Study ("Optimisation Study") in June 2022. Following
                                                           The Code requires that a study to at least Pre-Feasibility Study level has       signing of the EPC contract, the Company undertook an exercise to optimise the
                                                           been undertaken to convert Mineral Resources to Ore Reserves. Such studies       DFS to account for the EPC contract, including updating the Kola production
                                                           will have been carried out and will have determined a mine plan that is          schedule and the forecast financial information. The Company has now completed
                                                           technically achievable and economically viable, and that material modifying      its review of the Optimised DFS, with the results summarised herein by way of
                                                           factors have been considered.                                                    update.

                                                                                                                                            The results of the Optimised DFS incorporate the most current information
                                                                                                                                            available to the Company, and have been updated from the DFS and Optimisation
                                                                                                                                            Study to ensure compliance with the latest applicable listing rule
                                                                                                                                            requirements and other regulatory policies of the Australian Stock Exchange
                                                                                                                                            Limited, and therefore should be considered as superseding the results of both
                                                                                                                                            the DFS and the earlier Optimisation Study.

 Cut-off parameters                                        The basis of the cut-off grade(s) or quality parameters applied.                 A CoG of 9.9% KCl has been calculated for the Ore Reserve Estimation based on
                                                                                                                                            forecast revenue and estimated operating costs. The cut-off calculation
                                                                                                                                            included all operating costs associated with the extraction, processing and
                                                                                                                                            marketing of ore material. The cut-offs are based on a conservative MoP price
                                                                                                                                            of US$250 per tonne of MoP. Inputs to the calculation of cut-off grades
                                                                                                                                            included:

                                                                                                                                            o Mining costs

                                                                                                                                            o Metallurgical recoveries

                                                                                                                                            o Processing costs

                                                                                                                                            o Shipping costs

                                                                                                                                            o General and administrative costs

                                                                                                                                            All sylvinite of the Measured and Indicated Resource is present at a grade
                                                                                                                                            significantly above 9.9% KCl (the Ore Reserve calculated CoG), therefore all
                                                                                                                                            the Measured and Indicated Sylvinite Resources have been considered for the
                                                                                                                                            Ore Reserve Estimate by application of the other modifying factors.

                                                                                                                                            The uniformly very low content of deleterious elements (magnesium and
                                                                                                                                            insoluble material) meant that these did not require consideration in the CoG
                                                                                                                                            determination.
 Mining factors or assumptions                             The method and assumptions used as reported in the Pre-Feasibility or            Mining factors and assumptions have been derived from the historical
                                                           Feasibility Study to convert the Mineral Resource to an Ore Reserve (i.e.        information available for mature potash mines,  the current best mining
                                                           either by application of appropriate factors by optimisation or by preliminary   practices and the outcomes of the various technical studies completed in the
                                                           or detailed design).                                                             DFS and Optimisation Study

                                                           The choice, nature and appropriateness of the selected mining method(s) and      The Kola orebody will be mined using conventional UG mining method consisting
                                                           other mining parameters including associated design issues such as pre-strip,    of room and pillar in a 'chevron' (or herringbone) pattern, with CMs mining
                                                           access, etc.                                                                     machines of the drum-cutting type.

                                                           The assumptions made regarding geotechnical parameters (e.g. pit slopes, stope   The mining equipment selected for the Kola Potash Project Mine are CMs.
                                                           sizes, etc.), grade control and pre-production drilling.

                                                                                Most of the mining will be one level only where only the US will be extracted.
                                                           The major assumptions made and Mineral Resource model used for pit and stope     In some areas, both the US and the LS will be mined, in which case the LS will
                                                           optimisation (if appropriate).                                                   only be mined after the US. In other areas only the HWS will be mined.

                                                           The mining dilution factors used.                                                In determining the Ore Reserves, a minimum mining height of 2.5 m was selected

                                                                                based on capability of the selected CM which is also capable of mining up to
                                                           The mining recovery factors used.                                                6 m. Areas of the Mineral Resource with a seam height of less than 2.5 m were

                                                                                excluded from the Ore Reserves.
                                                           Any minimum mining widths used.

                                                                                The mine design is typical of potash mines, having 4 entries for access
                                                           The manner in which Inferred Mineral Resources are utilised in mining studies    drives. Each drive will typically be 8 m wide and 3 m to 6 m high depending on
                                                           and the sensitivity of the outcome to their inclusion.                           the seam height. The typical configuration for the chevron pattern is an angle

                                                                                of 65 degrees from the middle entry, and length of 150 m approximately.
                                                           The infrastructure requirements of the selected mining methods.

                                                                                                                                            The Mine design relies on geotechnical modelling, carried out in FLAC 3D
                                                                                                                                            software. The modelling was based on geotechnical test-work carried out on
                                                                                                                                            representative core samples from the sylvinite seams and host rocks (rock-salt
                                                                                                                                            and lesser carnallitite). The geotechnical modelling established that the mine
                                                                                                                                            is stable over the LoM for the DFS mine design which includes the following
                                                                                                                                            geotechnical parameters:

                                                                                                                                            o  Where both the US and LS seams are to be mined, the support interval
                                                                                                                                            between the US and LS must be at least 3 m thick.

                                                                                                                                            o  An 8 m wide pillar between two consecutive production rooms (of 8 m each).

                                                                                                                                            o  A 50 m wide pillar between two production panels. Similarly, a 50 m wide
                                                                                                                                            pillar will be left in place between the side of the production panel and the
                                                                                                                                            main haulage access drift.

                                                                                                                                            o  The interval of rock-salt between the mine openings and the floor of the
                                                                                                                                            overlying anhydrite member is referred to as the 'salt back'. This is
                                                                                                                                            typically over 30 m but is less in some areas. The DFS design allows that it
                                                                                                                                            may be a minimum of 15 m unless the Anhydrite Member is well developed where
                                                                                                                                            it may be 10 m. This is based on the results of the geotechnical model.

                                                                                                                                            o  A stand-off distance of 20 m radius from the exploration holes.

                                                                                                                                            o  A stand-off distance of 30 m radius from class 2 geological anomalies and
                                                                                                                                            60 m radius from class 3 geological anomalies.

                                                                                                                                            o  A pillar of 300 m in radius around the exhaust and intake shafts.

                                                                                                                                            Based on the selected mining equipment (CMs), it is anticipated that a good
                                                                                                                                            cutting selectivity would be achieved, and that a maximum of 0.2 m of dilution
                                                                                                                                            material above and/or below the potash seam is likely. Carnallitite is present
                                                                                                                                            in the floor of the seam in some areas. The roof is always of rock-salt. On
                                                                                                                                            average, the dilution material is equivalent to approximately 10% of the
                                                                                                                                            tonnage of the Ore Reserves. Dilution material was assigned a grade of 3% KCl
                                                                                                                                            if rock-salt and 0% KCl if Carnallitite.

                                                                                                                                            Based on the configuration of the proposed mining layout, and based on the
                                                                                                                                            anticipated fleet of mining equipment, it is assumed that the mining recovery
                                                                                                                                            in the different extraction chambers willbe 90% on average (i.e. mining losses
                                                                                                                                            will be 10%). This considers the mining action which will lead to some losses
                                                                                                                                            such as material being excavated and left in the production chamber, or
                                                                                                                                            mineralized material left in the floor or roof, etc.

                                                                                                                                            The Global extraction ratio is 30% (25% in the LS, 33% in the US and 28% in
                                                                                                                                            the HWS). This is after excluding the tonnage associated with removal of all
                                                                                                                                            pillars (pillars around the geological anomalies, the barrier pillars, the
                                                                                                                                            shaft pillar, the pillars between chevrons and main access drifts), the
                                                                                                                                            stand-off distance around boreholes, mining losses and the exclusion of
                                                                                                                                            sylvinite <2.5 m thick.

                                                                                                                                            Two vertical shafts, each with 8 m internal diameter, will be sunk at a
                                                                                                                                            central location in the Ore Reserves, to provide access to the underground.
                                                                                                                                            The intake shaft will be equipped with a hoist and cage system for
                                                                                                                                            transportation of persons and material, while the exhaust shaft will be
                                                                                                                                            equipped with a vertical conveyor system (pocket lift configuration) to convey
                                                                                                                                            the mined-out ore to the surface. Both shafts are approximately 270 m deep.

                                                                                                                                            One haulage from the CMs to the feeder breaker apron feeder will be done using
                                                                                                                                            electrically- powered Shuttle Cars.

                                                                                                                                            Underground conveyor belts will be used for materials handling (ore haulage)
                                                                                                                                            ore transportation in all the areas of the mine. Conveyor belts are
                                                                                                                                            distributed in the mains and submains and ultimately in the working panels
                                                                                                                                            near the CM working face. The ore will be placed on the belts from the feeder
                                                                                                                                            breakers that were fed by the shuttle cars. The conveyor belts will carry the
                                                                                                                                            ore loaded by the feeder breakers to the ore bins. Then the ore is conveyed
                                                                                                                                            from the ore bins to the Pocket Lift system located in the exhaust shaft.

                                                                                                                                            The Life of Ore Reserves for the Kola Project is estimated at 23 years, and
                                                                                                                                            full-scale production averaging approximately 2.1 million tonnes per annum of
                                                                                                                                            MoP from Ore Reserves occurs for approximately 23 years. During the
                                                                                                                                            exploitation of the 152.4 Mt of Ore Reserves, 9.7 Mt of Inferred Mineral
                                                                                                                                            Resources are scheduled to be mined and processed. This represents
                                                                                                                                            approximately 6.0% of the total amount of ROM material processed in the first
                                                                                                                                            23 years. This portion of the Inferred Mineral Resources is at the periphery
                                                                                                                                            of the Mineral Resources envelope and immediately adjacent to the Ore Reserves
                                                                                                                                            and logically would be extracted in conjunction with the adjacent Ore
                                                                                                                                            Reserves.  The bulk of the Inferred Mineral Resources are planned for
                                                                                                                                            extraction from year 10 onwards.
 Metallurgical factors or assumptions                      The metallurgical process proposed and the appropriateness of that process to    The metallurgical factors and assumptions applying to the Kola Project were
                                                           the style of mineralization.                                                     set out in the Company's announcement "Kola Definitive Feasibility Study"

                                                                                dated 29 January 2019.
                                                           Whether the metallurgical process is well-tested technology or novel in

                                                           nature.                                                                          As noted in that announcement, the final product will be MoP K60, comprising

                                                                                at least 95% KCl. The DFS design allows for the production of this MoP in two
                                                           The nature, amount and representativeness of metallurgical test work             forms, standard and  granular. The optimised design simplified production to
                                                           undertaken, the nature of the metallurgical domaining applied and the            a single product - red granular K60 MOP.
                                                           corresponding metallurgical recovery factors applied.

                                                                                A conventional flotation process will be utilized for potash concentration.
                                                           Any assumptions or allowances made for deleterious elements.                     This method is well established, and the most widely used method in the potash

                                                                                industry.
                                                           The existence of any bulk sample or pilot scale test work and the degree to

                                                           which such samples are considered representative of the orebody as a whole.      The DFS metallurgical test work campaigns were based on representative core

                                                                                samples of the three seams, collected from the exploration drill hole cores.
                                                           For minerals that are defined by a specification, has the Ore Reserve            They comprised US (114.5 kg), LS (102.0 kg) and HWS (10.3 kg). All test work
                                                           estimation been based on the appropriate mineralogy to meet the                  was carried out at the Saskatchewan Research Council laboratory in Saskatoon,
                                                           specifications?                                                                  Canada.  No further testing was completed during optimisation.

                                                                                                                                            The process flow sheets were optimised to meet the Kola Potash Project targets
                                                                                                                                            of producing 2.2 Mtpa of MoP, at 95.3% KCl purity, with a minimum KCl recovery
                                                                                                                                            of 89.9%.

                                                                                                                                            Two metallurgical test work campaigns were conducted during the DFS in 2017
                                                                                                                                            and 2018. The main philosophy of the first DFS test work campaign was to
                                                                                                                                            prepare representative test feedstocks for each seam, confirm KCl liberation,
                                                                                                                                            characterize the feedstock, perform flotation tests, optimize the operating
                                                                                                                                            conditions, optimize reagent consumption for optimum KCl recovery and grade
                                                                                                                                            performance, perform a sensitivity test on flotation.

                                                                                                                                            The objective of the second test work campaign was to optimize the flotation
                                                                                                                                            process and improve the plant recovery from the initial flow sheet.  The
                                                                                                                                            results of this second test works processed in SYSCAD™ model demonstrated
                                                                                                                                            that the new flotation process performed above the project performance minimum
                                                                                                                                            target.

                                                                                                                                             With a raw ore feed grade of 31.3% KCl, the material balance confirmed that
                                                                                                                                            the project objectives can be met with a production of 2.2 Mtpa with an
                                                                                                                                            expected product recovery of 89.9%, and a final product grade of 95.3% KCl.

                                                                                                                                            Magnesium and insoluble material are considered deleterious. The extremely low
                                                                                                                                            content of these materials in the ore mean that their removal is relatively
                                                                                                                                            straightforward. Insoluble material is removed by attrition scrubbing and
                                                                                                                                            magnesium removed by brine purge.

                                                                                                                                            The metallurgical test work campaigns provided a sound foundation for the
                                                                                                                                            development of the process design engineering and subsequent project
                                                                                                                                            performance, overall engineering studies and the cost estimate.

 Environmental                                             The status of studies of potential environmental impacts of the mining and       The ESIA for the construction and operation phases of the mining project was
                                                           processing operation. Details of waste rock characterisation and the             initially prepared by the consulting company SRK in Cardiff and approved by
                                                           consideration of potential sites, status of design options considered and,       the RoC regulator in 2013.
                                                           where applicable, the status of approvals for process residue storage and

                                                           waste dumps should be reported.                                                  An amendment was prepared by SRK in parallel with the DFS to capture changes
                                                                                                                                            to the project description and was submitted to the ROC regulator in Q4 2018;
                                                                                                                                            It was approved on 31 March 2020 for 25 years.

                                                                                                                                            The 2022 Optimization Study having proposed new locations for the
                                                                                                                                            accommodation camp, process plant and small concomitant changes in the route
                                                                                                                                            of the OLC, this has created a requirement to further amend some parts of the
                                                                                                                                            2018 ESIA.

                                                                                                                                            Discussions with the RoC authorities have led to the conclusion that Kore
                                                                                                                                            Potash needs to make an addendum to the existing document to cover all recent
                                                                                                                                            changes. It is planned to commence the base data collection for the route and
                                                                                                                                            location changes once Term Sheets for financing the Kola project are finalized
                                                                                                                                            during the first quarter of 2025.

                                                                                                                                            While the approved ESIA already includes a detailed an Environment and Social
                                                                                                                                            Management Plan ("ESMP") that is central to the construction construction, it
                                                                                                                                            is expected that an augmented ESMP will result from the supplementary ESIA
                                                                                                                                            work to be accomplished in 2025.

                                                                                                                                            It should be noted that the mine-site and a portion of the infrastructure
                                                                                                                                            corridor are located within the economic development and buffer zones of the
                                                                                                                                            Conkouati-Douli National Park ("CDNP") while the processing plant is located
                                                                                                                                            outside. Project activity in this area has been minimized and influx is led
                                                                                                                                            away from the park through the siting of employee facilities outside the CDNP.

                                                                                                                                            Tailings are insignificant, being only the <0.2% of insoluble material or
                                                                                                                                            just under 1Mt over the LoM. The bulk of the waste is dissolved halite in the
                                                                                                                                            form on an NaCl brine. All waste streams will be diluted with seawater to a
                                                                                                                                            concentration of 200mg/l and discharged via a diffuser into the ocean. This
                                                                                                                                            material has been characterised and ecotoxicological testing has been
                                                                                                                                            undertaken to confirm that no adverse impacts are caused at the edge of the
                                                                                                                                            mixing zone.

                                                                                                                                            The overall conclusion of the ESIA is that negative environmental impacts
                                                                                                                                            identified can be reduced to acceptable levels.

                                                                                                                                            A rehabilitation and closure plan has been prepared and included in owner's
                                                                                                                                            costs of the project.

                                                                                                                                            Biodiversity, air quality, social, archeological, water and noise baseline
                                                                                                                                            studies have been prepared and incorporated into the ESIA process.
 Infrastructure                                            The existence of appropriate infrastructure: availability of land for plant      The project infrastructure is comprised of the mine-site (shaft and offices),
                                                           development, power, water, transportation (particularly for bulk commodities),   the process plant is 24km from the mine site and the marine and product
                                                           labour, accommodation; or the ease with which the infrastructure can be          storage facility a further 11km from the plant site, on the coast (at
                                                           provided or accessed.                                                            Tchiboula), the 34 km infrastructure corridor between these (including the
                                                                                                                                            overland conveyor, service road and power line), the gas line from M'boundi
                                                                                                                                            gas field, overhead line from the MKII substation, the accommodation and
                                                                                                                                            administrative camp and the transshipment facilities.

                                                                                                                                            Exclusive land acquisition rights through the DUP process will be applied for
                                                                                                                                            based on the new plant position.

                                                                                                                                            Road access to the Kola Potash Project sites will be via the existing Route
                                                                                                                                            Nationale 5 (RN5). Two external access roads will be built, which are
                                                                                                                                            connected from RN5 to the mining site and from RN5 to the mineral processing
                                                                                                                                            site and living quarter, with a length of 2.0km and 4.3km respectively. Two
                                                                                                                                            maintenance roads for long-distance belt conveyors will be built. One of the
                                                                                                                                            roads for RoM belt conveyor maintenance is about 25 km, connecting Koutou camp
                                                                                                                                            and the mineral processing site. The other 9 km road is for MOP belt conveyor
                                                                                                                                            maintenance,

                                                                                                                                            Electrical Power will be sourced from the RoC national grid. A 57 km long 220
                                                                                                                                            kV transmission line will be built from the Mango Kamba II substation north of
                                                                                                                                            Pointe Noire to the Process Plant Site. A second 34 km long 220 kV
                                                                                                                                            transmission line will be built from the Process Plant Site to the Mine Site
                                                                                                                                            from process plant to marine facility.

                                                                                                                                            ·      The Natural Gas needed for product drying will be supplied by a
                                                                                                                                            local Oil and Gas producer who has plans to build a gas treatment plant some
                                                                                                                                            35 km away from the Kore processing plant. The same company is also planning
                                                                                                                                            to supply electricity to the Kola Project from the same offtake point. This
                                                                                                                                            will be an interesting option to the Mongo Kamba II substation as it has a
                                                                                                                                            lower environmental impact.

                                                                                                                                            Ongoing operational labour will be a combination of permanent employees,
                                                                                                                                            permanent contract services, and part-time contract services for intermittent
                                                                                                                                            needs.  The total requirement for permanent employees is expected to be
                                                                                                                                            731.  Local labour resources will be used for most labour requirements, while
                                                                                                                                            some selected positions are planned as expat roles.

                                                                                                                                            The Accommodation Camp has been sized for a capacity of 950 beds and will be
                                                                                                                                            located 2km away from the process plant.

                                                                                                                                            The Kola Potash Project intends to export up to 2.2 Mt MoP to world markets
                                                                                                                                            each year. A transshipment solution has therefore been developed, whereby the
                                                                                                                                            material for export is loaded at a dedicated Jetty onto self-propelled shuttle
                                                                                                                                            Barges (two units), which will then travel to OGVs anchored 11 nautical miles
                                                                                                                                            (20 km) offshore in a dedicated transshipment area. The cargo will be
                                                                                                                                            transferred from the Barges to the OGVs using a FCTU.
 Costs                                                     The derivation of, or assumptions made, regarding projected capital costs in     Capital Cost:
                                                           the study.

                                                                                The pre-production capital cost for the Kola Project is now estimated at
                                                           The methodology used to estimate operating costs.                                US$2.07 billion (nominal), which includes the fixed price EPC contract of

                                                                                US$1.929 billion and US$141 million owner's costs.
                                                           Allowances made for the content of deleterious elements.

                                                           The derivation of assumptions made of metal or commodity price(s), for the

                                                           principal minerals and co- products.                                             Operating Cost:

                                                           The source of exchange rates used in the study.                                  Operating costs were estimated using the detailed model in the Kola DFS,

                                                                                revised to reflect current cost conditions. The Kola DFS Operating costs were
                                                           Derivation of transportation charges.                                            based on first principles using quoted rates, estimated consumption, forecast

                                                                                labour complements and remuneration estimates.
                                                           The basis for forecasting or source of treatment and refining charges,

                                                           penalties for failure to meet specification, etc.                                Operating Cost covering the Life of Mine (23 years) was estimated in 2019 and

                                                                                revised to reflect current cost conditions. They include costs for Electric
                                                           The allowances made for royalties payable, both Government and private.          power, Fuel, Gas, Labour, Maintenance parts, Operating Consumables, General
                                                                                                                                            and Administration costs and Contract for Employee Facilities.

                                                                                                                                            Mine Closure cost estimated in accordance with the Conceptual Rehabilitation
                                                                                                                                            and Closure Plan developed by SRK Consulting.

                                                                                                                                            Mine Closure duration of 24 months (2 years), for the effective dismantling,
                                                                                                                                            demolition and rehabilitation works..

                                                                                                                                            Quantities of equipment, materials and works directly assessed from the
                                                                                                                                            Material Take-off prepared within the framework of the DFS for the Kola Potash
                                                                                                                                            Project.

                                                                                                                                            State mineral royalties of 3% of Net Revenue applies.

                                                                                                                                            Other criteria

                                                                                                                                            The marketed MoP will comprise at least 95% KCl, with a maximum of 0.2% Mg and
                                                                                                                                            0.3% Insolubles.
 Revenue factors                                           The derivation of, or assumptions made regarding revenue factors including       Head grade, recovery and product grade forecasts were based on the DFS
                                                           head grade, metal or commodity price(s) exchange rates, transportation and       results.
                                                           treatment charges, penalties, net smelter returns, etc.

                                                                                Product pricing - Potash market research specialist Argus Media provided the
                                                           The derivation of assumptions made of metal or commodity price(s), for the       Company with historical and forecast pricing trends for the MoP CFR Brazil
                                                           principal metals, minerals and co-products.                                      benchmarks over the period up to 2047 (see Figure 5 above). Kola's proposed
                                                                                                                                            mine life covers the period from 2029 through to 2052 (23 years). The Argus
                                                                                                                                            Media Marketing Report's estimates are provided in MoP CFR Brazil Real US$/t
                                                                                                                                            2023 values for calendar years 2024 to 2047. After 2047, prices are indexed by
                                                                                                                                            the Company using a US$2/t incremental annual increase to the 2047 price as in
                                                                                                                                            the Argus Media Marketing Report. As a result, the estimated forecast average
                                                                                                                                            granular MoP price is US$449/t for the life of the mine operations. For more
                                                                                                                                            details on product pricing refer to Section 12.
 Market assessment                                         The demand, supply and stock situation for the particular commodity,             As stated in the Argus Media Marketing Report MoP prices are currently
                                                           consumption trends and factors likely to affect supply and demand into the       reaching their lowest levels over the past 5 years. Short-term pricing in the
                                                           future.                                                                          next 12 months is based on the current market developments, such as weather

                                                                                events, planned or unplanned plant outages and market participant sentiment.
                                                           A customer and competitor analysis along with the identification of likely       Argus Media sees limited upside in medium-term (5 - 7 years) as the market
                                                           market windows for the product.                                                  reaches floor around the year 2028 with the ramp-up of BHP's Jansen project in

                                                                                Canada. Potash market is facing transition to supply surplus with recovering
                                                           Price and volume forecasts and the basis for these forecasts.                    Russian and Belorussian and new capacity in Canada and Laos. Argus Media

                                                                                believes that the long-term price of MoP is dictated by the industry's LRMC
                                                           For industrial minerals the customer specification, testing and acceptance       for adding new potash supply.
                                                           requirements prior to a supply contract.

                                                                                                                                            Total LRMC is the sum of:

                                                                                                                                            ·      Mine capital costs, adjusted for location and the weighted
                                                                                                                                            average cost of capital, amortised over the mine's life span

                                                                                                                                            ·      Mine operating costs, including fuel, labour, materials,
                                                                                                                                            sustaining capital and royalties

                                                                                                                                            ·      Value-in-use considerations, crediting or debiting total cost to
                                                                                                                                            consider access to target markets

                                                                                                                                            The LRMC base year is then inflated by Argus Media over the forecast period to
                                                                                                                                            provide their long-term price forecast. Each LRMC element is inflated using
                                                                                                                                            the appropriate inflator from Argus Media's forecasts of fuel, energy and
                                                                                                                                            macro inflators. The LRMC is a long-term trend forecast, meaning Argus Media
                                                                                                                                            expects short-term oscillations around the calculated LRMC, driven by factors
                                                                                                                                            such as weather and supply disruptions that cannot be predicted this far in
                                                                                                                                            advance. Russian MoP development is no longer included in the LRMC set. As the
                                                                                                                                            war in Ukraine continues, Argus Media assumes the impact on Russia as a
                                                                                                                                            destination for investment will be more prolonged and this is reflected in a
                                                                                                                                            higher-risk premium. Argus Media's view is that incremental tonnage from
                                                                                                                                            Canada and Israel are expected to dictate long-run LRMC.

                                                                                                                                            For more details on product pricing refer to Section 12.
 Economic                                                  The inputs to the economic analysis to produce the net present value (NPV) in
                                                           the study, the source and confidence of these economic inputs including

                                                           estimated inflation, discount rate, etc.                                         Key valuation assumptions and (sources)

                                                           NPV ranges and sensitivity to variations in the significant assumptions and      Production - LoM of 23 years at nominal 2.2 Mtpa MoP production.
                                                           inputs.

                                                                                                                                            Single MoP product type - red MOPG (Muriate of Potash - Granular)

                                                                                                                                            Average LoM CFR price of US$ 449/tMoP

                                                                                                                                            On-mine LoM average operating cost US$ 103.81/tMoP, Real

                                                                                                                                            LoM Shipping (transshipment and sea freight) of US$ 24.38/tMoP

                                                                                                                                            Project capital period 43 months

                                                                                                                                            Total Nominal Project Capital US$ 2.07 billion (including Owners Capital)

                                                                                                                                            Owners Capital US$ 141 million

                                                                                                                                            Sustaining Capital US$ 13.06/tMoP, Real

                                                                                                                                            Fiscal parameters: Company tax rate (15%), tax holidays (5 years at 0% + 5
                                                                                                                                            years at 7.5%) (Mining Convention)

                                                                                                                                            Royalties 3% (Mining Convention)

                                                                                                                                            Government free carry (10%) (Mining Convention)

                                                                                                                                            Other minor duties and taxes (Mining Convention)

                                                                                                                                            Working capital: 30 days Debtors and Creditors, 60 days Stores (Kore)

                                                                                                                                            Payback period: 8.5 years from start of construction

 Social                                                    The status of agreements with key stakeholders and matters leading to social     Approval of an ESIA is a prerequisite for beginning construction of any mining
                                                           license to operate.                                                              project in the Republic of Congo. The amended 2018 ESIA for the Kola Mining
                                                                                                                                            License was approved on 31 March 2020 for 25 years. It was written to the
                                                                                                                                            applicable international standards while respecting all Congolese legislation.
                                                                                                                                            It is directly related to the Relocation Action Plan ("RAP") which was
                                                                                                                                            prepared by RSK Consultants back in June 2018. Notwithstanding, socio-economic
                                                                                                                                            and livelihood baseline reports which were prepared and approved as part of
                                                                                                                                            the ESIA baseline process need to be updated with the passing of time. A RAP
                                                                                                                                            update is thus planned for the first half of 2025.

                                                                                                                                            At the time of the RAP, a DUP process was initiated with the support and input
                                                                                                                                            of various Government ministries and legal authorities to allow land
                                                                                                                                            acquisition and possible expropriation with compensation from the various
                                                                                                                                            owners and users whose property or livelihood would be affected by the project
                                                                                                                                            zone. The gazetted DUP was valid for 3 years but has since expired, requiring
                                                                                                                                            a new process to be started afresh.The company is awaiting the new RAP/ESIA
                                                                                                                                            updates to refresh the DUP.

                                                                                                                                            Sintoukola Potash has implemented a Stakeholder Engagement Process and is
                                                                                                                                            actively engaging with a wide range of project stakeholders, including, NOE,
                                                                                                                                             the conservation NGO managing the adjacent National Park, the regulator and
                                                                                                                                            communities.

                                                                                                                                            In the RAP, three separate land take corridors were identified by RSK : the
                                                                                                                                            Service Corridor including the Mine Site, the Conveyor Belt and Process Plant,
                                                                                                                                            an HV line and the Gas Pipeline. Physical displacement is minimal with most
                                                                                                                                            actions requiring livelihood restoration. Resettlement Costs have been
                                                                                                                                            included in owner's costs and timed in the implementation schedule.

                                                                                                                                            There are believed to be no social related issues that do not have a
                                                                                                                                            reasonable likelihood of being resolved.

 Other                                                     To the extent relevant, the impact of the following on the project and / or      Kola is currently compliant with all legal and regulatory requirements subject
                                                           on the estimation and classification of the Ore Reserves:                        to final approval of the Kola Environmental and Social Impact Assessment

                                                                                Amendments (which was required following the project design changes
                                                           Any identified material naturally occurring risks.                               implemented during the optimisation study).

                                                           The status of material legal agreements and marketing arrangements.              A mining convention entered into between the RoC government and the Companies

                                                                                on 8 June 2017 and gazetted into law on 29 November 2018 concludes the
                                                           The status of governmental agreements and approvals critical to the viability    framework envisaged in the 25-year renewable Kola Mining License granted in
                                                           of the project, such as mineral tenement status, and government and statutory    August 2013. The Mining Convention provides certainty and enforceability of
                                                           approvals. There must be reasonable grounds to expect that all necessary         the key fiscal arrangements for the development and operation of Kola Mining
                                                           Government approvals will be received within the timeframes anticipated in the   Licenses, which amongst other items include import duty and VAT exemptions and
                                                           Pre-Feasibility or Feasibility study. Highlight and discuss the materiality of   agreed tax rates during mine operations. The Mining Convention provides
                                                           any unresolved matter that is dependent on a third party on which extraction     strengthened legal protection of the Company's investments in the Republic of
                                                           of the reserve is contingent.                                                    Congo through the settlement of disputes by international arbitration.

                                                                                                                                            To the best of the Competent Person's knowledge, there is no reason to assume
                                                                                                                                            any government permits and licenses or statutory approvals will not be
                                                                                                                                            granted. There are no unresolved matters upon which extraction is contingent.
 Classification                                            The basis for the classification of the Ore Reserves into varying confidence     Measured Mineral Resources were used for the estimation of the Proved Ore
                                                           categories.                                                                      Reserves. Indicated Mineral Resources were used for the estimation of Probable

                                                                                Ore Reserves.
                                                           Whether the result appropriately reflects the Competent Person's view of the

                                                           deposit.                                                                         The conversion of Measured and Indicated Mineral Resource to Proved and

                                                                                Probable Ore Reserve reflects the Competent Person's view of the deposit.
                                                           The proportion of Probable Ore Reserves that have been derived from Measured

                                                           Mineral Resources (if any).                                                      40.6% of the Ore Reserves are classified in the Proved category and 59.4% of
                                                                                                                                            the Ore Reserves are classified in the Probable category

 Audits or reviews                                         The results of any audits or reviews of Ore Reserve estimates.                   DFS deliverables were continually reviewed by an Owner's Team consisting of an
                                                                                                                                            inter-discipline engineering team, specialists in ESIA and economic modelling
                                                                                                                                            and construction experts.

 Discussion of relative accuracy/ confidence               Where appropriate a statement of the relative accuracy and confidence level in   In the Competent Person's view, the Kola DFS achieves the required level of
                                                           the Ore Reserve estimate using an approach or procedure deemed appropriate by    confidence in the modifying factors to justify the estimation of an Ore
                                                           the Competent Person. For example, the application of statistical or             Reserve. All relevant modifying factors were considered in the Ore Reserve
                                                           geostatistical procedures to quantify the relative accuracy of the reserve       Estimation and deemed to be modelled at a level of accuracy appropriate to the
                                                           within stated confidence limits, or, if such an approach is not deemed           classification, that a global change of greater than 10% considered unlikely
                                                           appropriate, a qualitative discussion of the factors which could affect the

                                                           relative accuracy and confidence of the estimate.                                The DFS determined a mine plan and production schedule that is technically

                                                                                achievable and economically viable.
                                                           The statement should specify whether it relates to global or local estimates,

                                                           and, if local, state the relevant tonnages, which should be relevant to          The capital and operating costs are based on the fixed-price EPC contract
                                                           technical and economic evaluation. Documentation should include assumptions      signed in November 2024.
                                                           made and the procedures used.

                                                                                Factors that could affect the Ore Reserves locally include; localised changes
                                                           Accuracy and confidence discussions should extend to specific discussions of     in salt-back thickness, greater dip of the seam in some areas, local changes
                                                           any applied modifying factors that may have a material impact on Ore Reserve     in the thickness of the rock-salt support layer between the seams, areas of
                                                           viability, or for which there are remaining areas of uncertainty at the          unexpected carnallite in floor. The Mineral Resource model attempted to model
                                                           current study stage.                                                             these features to a high level of detail and are 'passed-on' into the Ore

                                                                                Reserve and mine plan. The Ore Reserve is also partially reliant on the model
                                                           It is recognized that this may not be possible or appropriate in all             for the thickness of the overlying Anhydrite Member which was not part of the
                                                           circumstances. These statements of relative accuracy and confidence of the       Mineral Resource.
                                                           estimate should be compared with production data, where available.

                                                                                                                                            While local variation from the mine plan in the above are expected, is
                                                                                                                                            considered unlikely that these would lead to significant negative change in
                                                                                                                                            the Ore Reserves, and that positive changes are equally likely.

                                                                                                                                            For the optimisation study, data from a potash mining operation was used to
                                                                                                                                            guide and check the design, productivity assumptions, cost estimates and
                                                                                                                                            budgets. The input data and design are likely to be realistic and achievable
                                                                                                                                            in the Competent Persons view.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Section 1 Sampling Techniques and Data

(Criteria in this section apply to all succeeding sections.)

 Criteria                                                      JORC Code explanation                                                            Commentary
 1.1 Sampling techniques                                       ·     Nature and quality of sampling (e.g. cut channels, random chips, or        Sampling was carried out according to a strict quality control protocol
                                                               specific specialised industry standard measurement tools appropriate to the      beginning at the drill rig. Holes were drilled to PQ size (85 mm core
                                                               minerals under investigation, such as down hole gamma sondes, or handheld XRF    diameter) core, with a small number of holes drilled HQ size (63.5 mm core
                                                               instruments, etc). These examples should not be taken as limiting the broad      diameter). Sample intervals were between 0.1 and 2.0 metres and sampled to
                                                               meaning of sampling.                                                             lithological boundaries. All were sampled as half-core except very recent

                                                                                holes (EK_49 to EK_51) which were sampled as quarter core. Core was cut using
                                                               ·     Include reference to measures taken to ensure sample representivity        an Almonte© core cutter without water and blade and core holder cleaned down
                                                               and the appropriate calibration of any measurement tools or systems used.        between samples. Sampling and preparation were carried out by trained

                                                                                geological and technical employees. Samples were individually bagged and
                                                               ·     Aspects of the determination of mineralisation that are Material to        sealed.
                                                               the Public Report.

                                                               ·     In cases where 'industry standard' work has been done this would be

                                                               relatively simple (eg 'reverse circulation drilling was used to obtain 1 m       A small number of historic holes were used in the Mineral Resource model; K6,
                                                               samples from which 3 kg was pulverised to produce a 30 g charge for fire         K18, K19, K20, K21. K6 and K18 were the original holes twinned by the Company
                                                               assay'). In other cases more explanation may be required, such as where there    in 2010. The grade data for these holes was not used for the Mineral Resource
                                                               is coarse gold that has inherent sampling problems. Unusual commodities or       estimate but they were used to guide the seam model. The 2010 twin hole
                                                               mineralisation types (eg submarine nodules) may warrant disclosure of detailed   drilling exercise validated the reliability of the geological data for these
                                                               information.                                                                     holes (section 1.7).

                                                                                                                                                KCl data for EK_49 to EK_51 was based on the conversion on calibrated API data
                                                                                                                                                from downhole geophysical logging, as is discussed in Section 6. Subsequent
                                                                                                                                                laboratory assay results for EK_49 and EK_51 support the API derived grades.
 1.2 Drilling techniques                                       ·     Drill type (eg core, reverse circulation, open-hole hammer, rotary         Holes were drilled by 12 and 8 inch diameter rotary Percussion through the
                                                               air blast, auger, Bangka, sonic, etc) and details (eg core diameter, triple or   'cover sequence', stopping in the Anhydrite Member and cased and grouted to
                                                               standard tube, depth of diamond tails, face-sampling bit or other type,          this depth. Holes were then advanced using diamond coring with the use of
                                                               whether core is oriented and if so, by what method, etc).                        tri-salt (K, Na, Mg) mud to ensure excellent recovery. Coring was PQ (85 mm
                                                                                                                                                core diameter) as standard and HQ (64.5 mm core diameter) in a small number of
                                                                                                                                                the holes.

 1.3 Drill sample recovery                                     ·     Method of recording and assessing core and chip sample recoveries          Core recovery was recorded for all cored sections of the holes by recording
                                                               and results assessed.                                                            the drilling advance against the length of core recovered. Recovery is between

                                                                                95 and 100% for the evaporite and all potash intervals, except in EK_50 for
                                                               ·     Measures taken to maximise sample recovery and ensure                      the Carnallitite interval in that hole (as grade was determined using API data
                                                               representative nature of the samples.                                            for that hole this is of no consequence).  The use of tri-salt (Mg, Na, and

                                                                                K) chloride brine to maximize recovery was standard.  A fulltime mud engineer
                                                               ·     Whether a relationship exists between sample recovery and grade and        was recruited to maintain drilling mud chemistry and physical properties. Core
                                                               whether sample bias may have occurred due to preferential loss/gain of           is wrapped in cellophane sheet soon after it is removed from the core barrel,
                                                               fine/coarse material.                                                            to avoid dissolution in the atmosphere, and is then transported at the end of
                                                                                                                                                each shift to a de-humidified core storage room where it is stored
                                                                                                                                                permanently.

 1.4 Logging                                                   ·     Whether core and chip samples have been geologically and                   The entire length of each hole was logged from rotary chips in the 'cover
                                                               geotechnically logged to a level of detail to support appropriate Mineral        sequence' and core in the evaporite. Logging is qualitative and supported by
                                                               Resource estimation, mining studies and metallurgical studies.                   quantitative downhole geophysical data including gamma, acoustic televiewer

                                                                                images, density and calliper data which correlates well with the geological
                                                               ·     Whether logging is qualitative or quantitative in nature. Core (or         logging. Due to the conformable nature of the evaporite stratigraphy and the
                                                               costean, channel, etc) photography.                                              observed good continuity and abrupt contacts, recognition of the potash seams

                                                                                is straightforward and made with a high degree of confidence. Core was
                                                               ·     The total length and percentage of the relevant intersections              photographed to provide an additional reference for checking contacts at a
                                                               logged.                                                                          later date.

 1.5 Sub-sampling techniques and sample preparation            ·     If core, whether cut or sawn and whether quarter, half or all core         Excluding QA-QC samples 2368 samples were analysed at two labs in 44 batches,
                                                               taken.                                                                           each batch comprising between 20 and 250 samples. Samples were submitted in 46

                                                                                batches and are from 41 of the 47 holes drilled at Kola. The other 6
                                                               ·     If non-core, whether riffled, tube sampled, rotary split, etc and          drill-holes (EK03, EK_21, EK_25, EK_30, EK_34, EK_37) were either stopped
                                                               whether sampled wet or dry.                                                      short of the evaporite rocks or did not intersect potash layers. Sample

                                                                                numbers were in sequence, starting with KO-DH-0001 to KO-DH-2650 (EK_01 to
                                                               ·     For all sample types, the nature, quality and appropriateness of           EK_44) then KO-DH-2741 to KO-DH-2845 (EK_46 and EK_47).
                                                               the sample preparation technique.

                                                               ·     Quality control procedures adopted for all sub-sampling stages to

                                                               maximise representivity of samples.                                              The initial 298 samples (EK_01 to EK_05) were analysed at K-UTEC in

                                                                                Sondershausen, Germany and thereon samples were sent to Intertek-Genalysis in
                                                               ·     Measures taken to ensure that the sampling is representative of the        Perth. Samples were crushed to nominal 2 mm then riffle split to derive a 100
                                                               in-situ material collected, including for instance results for field             g sample for analysis. K, Na, Ca, Mg, Li and S were determined by ICP-OES. Cl
                                                               duplicate/second-half sampling.                                                  is determined volumetrically. Insolubles (INSOL) were determined by filtration

                                                                                of the residual solution and slurry on 0.45 micron membrane filter, washing to
                                                               ·     Whether sample sizes are appropriate to the grain size of the              remove residual salts, drying and weighing. Loss on drying by Gravimetric
                                                               material being sampled.                                                          Determination (LOD/GR) was also competed as a check on the mass balance.
                                                                                                                                                Density was measured (along with other methods described in section 3.11)
                                                                                                                                                using a gas displacement Pycnometer.

 1.6 Quality of assay data and laboratory tests                ·     The nature, quality and appropriateness of the assaying and                For drill-holes EK_01 to EK_47, a total of 412 QAQC samples were inserted into
                                                               laboratory procedures used and whether the technique is considered partial or    the batches comprising 115 field duplicate samples, 84 blank samples and 213
                                                               total.                                                                           certified reference material (CRM) samples. Duplicate samples are the other

                                                                                half of the core for the exact same interval as the original sample, after it
                                                               ·     For geophysical tools, spectrometers, handheld XRF instruments,            is cut into two. CRMs were obtained from the Bureau of Reference (BCR), the
                                                               etc, the parameters used in determining the analysis including instrument make   reference material programme of the European Commission. Either river sand or
                                                               and model, reading times, calibrations factors applied and their derivation,     later barren Rock-salt was used for blank samples. These QA-QC samples make up
                                                               etc.                                                                             17% of the total number of samples submitted which is in line with industry

                                                                                norms.  Sample chain of custody was secure from point of sampling to point of
                                                               ·     Nature of quality control procedures adopted (eg standards, blanks,        reporting.
                                                               duplicates, external laboratory checks) and whether acceptable levels of

                                                               accuracy (i.e. lack of bias) and precision have been established.

                                                                                                                                                In addition two batches of 'umpire' analyses were submitted to a second lab.
                                                                                                                                                The first batch comprised 17 samples initially analysed at K-UTEC sent to
                                                                                                                                                Intertek-Genalysis for umpire. The second umpire batch comprised 23 samples
                                                                                                                                                from Intertek-Genalysis sent to SRC laboratory in Saskatoon for umpire. They
                                                                                                                                                demonstrate excellent validation of the primary laboratory analyses.

                                                                                                                                                Potash intersections for EK_49 to EK_51 were partially sampled for
                                                                                                                                                geotechnical test work and so were not available in full for chemical
                                                                                                                                                analysis. Gamma ray CPS data was converted to API units which were then
                                                                                                                                                converted to KCl % by the application of a conversion factor known, or
                                                                                                                                                K-factor. The geophysical logging was carried out by independent downhole
                                                                                                                                                geophysical logging company Wireline Workshop ("WW") of South Africa, and data
                                                                                                                                                was processed by WW. Data collection, data processing and quality control and
                                                                                                                                                assurance followed a stringent operating procedure. API calibration of the
                                                                                                                                                tool was carried out at a test-well at WW's base in South Africa to convert
                                                                                                                                                raw gamma ray CPS to API using a coefficient for sonde NGRS6569 of 2.799 given
                                                                                                                                                a standard condition of a diameter 150mm bore in fresh water (1.00gm/cc mud
                                                                                                                                                weight).

                                                                                                                                                To provide a Kola-specific field based K-factor, log data were converted via a
                                                                                                                                                K-factor derived from a comparison with laboratory data for drill-holes EK_13,
                                                                                                                                                EK_14 and EK_24. In converting from API to KCl (%), a linear relationship is
                                                                                                                                                assumed (no dead time effects are present at the count rates being
                                                                                                                                                considered). To remove all depth and log resolution variables, an
                                                                                                                                                'area‐under‐the‐curve' method was used to derive the K factor. This
                                                                                                                                                overcomes the effect of narrow beds not being fully resolved as well as the
                                                                                                                                                shoulder effect at bed boundaries. For this, laboratory data was converted to
                                                                                                                                                a wireline log and all values between ore zones were assigned zero. A block
                                                                                                                                                was created that covered all data and both Wireline Gamma Ray Log ("GAMC") and
                                                                                                                                                laboratory data log were summed in terms of area under the curves. From this
                                                                                                                                                like-for -like comparison a K factor of 0.074 was calculated. In support if
                                                                                                                                                this factor, it compares well with the theoretical K-factor derived using
                                                                                                                                                Schlumberger API to KCl conversion charts which would be 0.0767 for this tool
                                                                                                                                                in hole of PQ diameter (125 mm from calliper data. As a check on instrument
                                                                                                                                                stability over time, EK_24 is logged frequently. No drift in the gamma-ray
                                                                                                                                                data is observed.

                                                                                                                                                As confirmation of the accuracy of the API-derived KCl grades for EK_49 to
                                                                                                                                                EK_51, samples for the intervals that were not taken for geotechnical
                                                                                                                                                sampling, were sent to Intertek-Genalysis for analysis. The results are within
                                                                                                                                                5% of the API-derived KCl and thickness, and so the latter was used
                                                                                                                                                unreservedly for the Mineral Resource estimation.

 1.7 Verification of sampling and assaying                     ·     The verification of significant intersections by either independent        40 samples of a variety of grades and drill-holes were sent for umpire
                                                               or alternative company personnel.                                                analysis and as described these support the validity of the original analysis.

                                                                                Other validation comes from the routine geophysical logging of the holes.
                                                               ·     The use of twinned holes.                                                  Gamma data provides a very useful check on the geology and grade of the potash

                                                                                and for all holes a visual comparison is made in log form. API data for a
                                                               ·     Documentation of primary data, data entry procedures, data                 selection of holes (EK_05, EK_13, EK_14, EK_24) were formally converted to KCl
                                                               verification, data storage (physical and electronic) protocols.                  grades. In all cases the API derived KCl supports the reported intersections.

                                                               ·     Discuss any adjustment to assay data.                                      As mentioned above; K6, K18, K19, K20, K21 were used in the geological
                                                                                                                                                modelling but not for the grade estimate. K6 and K18 were twinned in 2010 and
                                                                                                                                                the comparison of the geological data is excellent, providing validation that
                                                                                                                                                the geological information for the aforementioned holes could be used with a
                                                                                                                                                high degree of confidence.

 1.8 Location of data points                                   ·     Accuracy and quality of surveys used to locate drill holes (collar         A total of 50 Resource related drill-holes have been drilled by the Company:
                                                               and down-hole surveys), trenches, mine workings and other locations used in      EK_01 to EK_52. EK_37 and EK_48 were geotechnical holes. Of the 50 Resource
                                                               Mineral Resource estimation.                                                     holes, 4 stopped short above the Salt Member due to drilling difficulties. Of

                                                                                the 46 Resource holes drilled into the Salt Member, all except 4 contained a
                                                               ·     Specification of the grid system used.                                     significant Sylvinite intersection.

                                                               ·     Quality and adequacy of topographic control.

                                                                                                                                                The collars of all drill-holes up to EK_47 including historic holes were
                                                                                                                                                surveyed by a professional land surveyor using a DGPS. EK_48 to EK_52 were
                                                                                                                                                positioned with a handheld GPS initially (with elevation from the LIDAR data)
                                                                                                                                                and later with a DGPS. All data is in UTM zone 32 S using WGS 84 datum.

                                                                                                                                                Topography for the bulk of the Mineral Resource area is provided by high
                                                                                                                                                resolution airborne LIDAR (Light Detection and Ranging) data collected in
                                                                                                                                                2010, giving accuracy of the topography to <200 mm. Beyond this SRTM 90
                                                                                                                                                satellite topographic data was used. Though of relatively low resolution, it
                                                                                                                                                is sufficient as the deposit is an underground mining project.

 1.9 Data spacing and distribution                             ·     Data spacing for reporting of Exploration Results.                         In most cases drill-holes are 1-2 km apart. A small number of holes are much

                                                                                closer such as EK_01 and K18, EK_04 and K6, EK_14 and EK_24 which are between
                                                               ·     Whether the data spacing and distribution is sufficient to                 50 and 200 m apart.
                                                               establish the degree of geological and grade continuity appropriate for the

                                                               Mineral Resource and Ore Reserve estimation procedure(s) and classifications
                                                               applied.

                                                                                The drill-hole data is well supported by 186 km of high frequency closely
                                                               ·     Whether sample compositing has been applied.                               spaced seismic data acquired by the Company in 2010 and 2011 that was
                                                                                                                                                processed to a higher standard in 2016. This data provides much guidance of
                                                                                                                                                the geometry and indirectly the mineralogy of the potash seams between and
                                                                                                                                                away from the holes, as well as allowing the delineation of discontinuities
                                                                                                                                                affecting the potash seams. The combination of drill-hole data and the seismic
                                                                                                                                                data supports geological modelling with a level of confidence appropriate for
                                                                                                                                                the classification assigned to the Measured, Indicated and Inferred sections
                                                                                                                                                of the deposit. The seismic data is described in greater detail below.

                                                                                                                                                Two sources of seismic data were used to support the Mineral Resource model:

                                                                                                                                                1)    Historical oil industry seismic data of various vintage and acquired
                                                                                                                                                by several companies, between 1989 and 2006. The data is of low frequency and
                                                                                                                                                as final SEG-Y files as PreStack Time Migrated ("PreSTM") form. Data was
                                                                                                                                                converted to depth by applying a velocity to best tie the top-of-salt
                                                                                                                                                reflector with drill-hole data. The data allows the modelling of the top of
                                                                                                                                                the Salt Member (base of the Anhydrite Member) and some guidance of the
                                                                                                                                                geometry of the layers within the Salt Member.

                                                                                                                                                2)    The Company acquired 55 lines totalling 185.5 km of data (excluding
                                                                                                                                                gaps on two lines) in 2010 and 2011. These surveys provide high frequency data
                                                                                                                                                specifically to provide quality images for the relatively shallow depths
                                                                                                                                                required (surface to approximately 800 m). Data was acquired on strike (tie
                                                                                                                                                lines) and dip lines. Within the Measured Mineral Resource area lines are
                                                                                                                                                between 100 and 200 m apart. Data was re-processed in 2016, for the 2017
                                                                                                                                                Mineral Resource update, by DMT Petrologic GmbH ("DMT") of Germany. DMT worked
                                                                                                                                                up the raw field data to Post Stack Migration ("PoSTM") and PreSTM format. By
                                                                                                                                                an iterative process of time interpretation of known reflectors (with
                                                                                                                                                reference to synthetic seismograms) the data was converted to PreStack Depth
                                                                                                                                                Migrated ("PSDM") form.  Finally, minor adjustments were made to tie the data
                                                                                                                                                exactly with the drill-hole data.

                                                                                                                                                The Competent Person reviewed the seismic data and processing and visited DMT
                                                                                                                                                in Germany for meetings around the final delivery of the data to the Company.

 1.10 Orientation of data in relation to geological structure  ·     Whether the orientation of sampling achieves unbiased sampling of          All exploration drill-holes were drilled vertically and holes were surveyed to
                                                               possible structures and the extent to which this is known, considering the       check for deviation. In almost all cases tilt was less than 1 degree (from
                                                               deposit type.                                                                    vertical). Dip of the potash seam intersections ranges from 0 to 45 degrees

                                                                                with most dipping 20 degrees or less. All intersections with a dip of greater
                                                               ·     If the relationship between the drilling orientation and the               than 15 degrees were corrected to obtain the true thickness, which was used
                                                               orientation of key mineralised structures is considered to have introduced a     for the creation of the Mineral Resource model.
                                                               sampling bias, this should be assessed and reported if material.

 1.11 Sample security                                          ·     The measures taken to ensure sample security.                              At the rig, the core is under full time care of a Company geologist and end of
                                                                                                                                                each drilling shift, the core is transported by Kore Potash staff to a secure
                                                                                                                                                site where it is stored within a locked room. Sampling is carried out under
                                                                                                                                                the fulltime watch of Company staff; packed samples are transported directly
                                                                                                                                                from the site by Company staff to DHL couriers in Pointe Noire 3 hours away.
                                                                                                                                                From here DHL airfreight all samples to the laboratory. All core remaining at
                                                                                                                                                site is stored is wrapped in plastic film and sealed tube bags, and within an
                                                                                                                                                air-conditioned room (17-18 degrees C) to minimize deterioration.
 1.12 Audits or reviews                                        ·     The results of any audits or reviews of sampling techniques and            The Competent Person has visited site to review core and to observe sampling
                                                               data.                                                                            procedures. As part of the Mineral Resource estimation, the drill-hole data
                                                                                                                                                was thoroughly checked for errors including comparison of data with the
                                                                                                                                                original laboratory certificates; no errors were found.

 
Section 2 Reporting of Exploration Results

(Criteria listed in the preceding section also apply to this section.)

 Criteria                                                              JORC Code explanation                                                            Commentary
 2.1 Mineral tenement and land tenure status                           ·     Type, reference name/number, location and ownership including              The Kola deposit is within the Kola Mining Lease which is held 100% under the
                                                                       agreements or material issues with third parties such as joint ventures,         local company Kola Mining SARL which is in turn held 100% by Sintoukola Potash
                                                                       partnerships, overriding royalties, native title interests, historical sites,    SA RoC, of which Kore Potash holds a 97% share. The lease was issued August
                                                                       wilderness or national park and environmental settings.                          2013 and is valid for 25 years. There are no impediments on the security of

                                                                                tenure.
                                                                       ·     The security of the tenure held at the time of reporting along with

                                                                       any known impediments to obtaining a licence to operate in the area.
 2.2 Exploration done by other parties                                 ·     Acknowledgment and appraisal of exploration by other parties.              Potash exploration was carried out in the area in the1960's by Mines de
                                                                                                                                                        Potasse d' Alsace S.A in the 1960's. Holes K6, K18, K19, K20, K21 are in the
                                                                                                                                                        general area. K6 and K18 are within the deposit itself and both intersected
                                                                                                                                                        Sylvinite of the Upper and Lower Seam; it was the following up of these two
                                                                                                                                                        holes by Kore Potash (then named Elemental Minerals) that led to the discovery
                                                                                                                                                        of the deposit in 2012.

                                                                                                                                                        Oil exploration in the area has taken place intermittently from the 1950's
                                                                                                                                                        onwards by different workers including British Petroleum, Chevron, Morel et
                                                                                                                                                        Prom and others. Seismic data collected by some of these companies was used to
                                                                                                                                                        guide the evaporite depth and geometry within the Inferred Mineral Resource
                                                                                                                                                        area. Some oil wells have been drilled in the wider area such as Kola-1 and
                                                                                                                                                        Nkoko-1.
 2.3 Geology                                                           ·     Deposit type, geological setting and style of mineralisation.              The potash seams are hosted by the 300-900 m thick Lower Cretaceous-aged
                                                                                                                                                        (Aptian age) Loeme Evaporite formation These sedimentary evaporite rocks
                                                                                                                                                        belong to the Congo (Coastal) Basin which extends from the Cabinda enclave of
                                                                                                                                                        Angola to the south well into Gabon to the north, and from approximately 50 km
                                                                                                                                                        inland to some 200-300 km offshore. The evaporites were deposited between 125
                                                                                                                                                        and 112 million years ago, within a post-rift 'proto Atlantic' sub-sea level
                                                                                                                                                        basin following the break-up of Gondwana forming the Africa and South America
                                                                                                                                                        continents.

                                                                                                                                                        The evaporite is covered by a thick sequence of carbonate rocks and clastic
                                                                                                                                                        sediments of Cretaceous age to recent (Albian to Miocene), referred to as the
                                                                                                                                                        'Cover Sequence', which is between 170 and 270 m thick over the Kola deposit.
                                                                                                                                                        The lower portion of this Cover Sequence is comprised of dolomitic rocks of
                                                                                                                                                        the Sendji Formation. At the top of the Loeme Formation, separating the Cover
                                                                                                                                                        Sequence and the underlying Salt Member is a layer of anhydrite and clay
                                                                                                                                                        typically between 5 and 15 m thick and referred to as the Anhydrite Member. At
                                                                                                                                                        Kola, this layer rests un-conformably over the Salt-Member, as described in
                                                                                                                                                        more detail below.

                                                                                                                                                        Within the Salt Member, ten sedimentary-evaporative cycles (I to X) are
                                                                                                                                                        recognized with a vertical arrangement of mineralogy consistent with classical
                                                                                                                                                        brine-evolution models; potash being close to the top of cycles.  The Salt
                                                                                                                                                        Member and potash layers formed by the seepage of brines into an extensive sub
                                                                                                                                                        sea-level basin. Evaporation resulted in precipitation of evaporite minerals
                                                                                                                                                        over a long period of time, principally halite (NaCl), carnallite
                                                                                                                                                        (KMgCl(3)·6H(2)O) and bischofite (MgCl(2)·6H(2)O), which account for over
                                                                                                                                                        90% of the evaporite rocks. Sylvinite formed by the replacement of
                                                                                                                                                        Carnallitite within certain areas. Small amounts of gypsum, anhydrite,
                                                                                                                                                        dolomite and insoluble material (such as clay, quartz, organic material) is
                                                                                                                                                        present, typically concentrated in relatively narrow layers at the base of the
                                                                                                                                                        cycles (interlayered with Rock-salt), providing useful 'marker' layers. The
                                                                                                                                                        layers making up the Salt Member are conformable and parallel or sub-parallel
                                                                                                                                                        and of relatively uniform thickness across the basin, unless affected by some
                                                                                                                                                        form of discontinuity.

                                                                                                                                                        There are upwards of 100 potash layers within the Salt Member ranging from 0.1
                                                                                                                                                        m to over 10 m in thickness. The Kola deposit is hosted by 4 seams within
                                                                                                                                                        cycles 7, 8 and 9, from uppermost these are; (HWS,  US, LS, Footwall Seam
                                                                                                                                                        ("FWS"). Seams are separated by Rock-salt.

                                                                                                                                                        Individual potash seams are stratiform layers that can be followed across the
                                                                                                                                                        basin are of Carnallitite except where replaced by Sylvinite, as is described
                                                                                                                                                        below. The potash mineralogy is simple; no other potash rock types have been
                                                                                                                                                        recognized and Carnallitite and Sylvinite are not inter-mixed. The seams are
                                                                                                                                                        consistent in their purity; all intersections of Sylvinite are comprised of
                                                                                                                                                        over 97.5% euhedral or subhedral halite and sylvite of medium to very coarse
                                                                                                                                                        grainsize (0.5 mm to ≥ 5 mm). Between 1.0 and 2.5% is comprised of anhydrite
                                                                                                                                                        (CaSO(4)) and a lesser amount of insoluble material. At Kola the potash layers
                                                                                                                                                        are flat or gently dipping and at depths of between 190 and 340 m below
                                                                                                                                                        surface.

                                                                                                                                                        The contact between the Anhydrite Member and the underlying salt is an
                                                                                                                                                        unconformity and due to the undulation of the layers within the Salt Member at
                                                                                                                                                        Kola, the thickness of the salt member beneath this contact varies. This is
                                                                                                                                                        the principal control on the extent and distribution of the seams at Kola and
                                                                                                                                                        the reason why the uppermost seams such as the Hangingwall Seam are sometimes
                                                                                                                                                        absent, and the lower seams such as the Upper and Lower Seam are preserved
                                                                                                                                                        over most of the deposit.

                                                                                                                                                        The most widely distributed Sylvinite seams at Kola are the US and LS, hosted
                                                                                                                                                        within cycle 8 of the Salt Member. These seams have an average grade of 35.5
                                                                                                                                                        and 30.5 % KCl respectively and average 3.7 and 4.0 m thick. The Sylvinite is
                                                                                                                                                        thinned in proximity to leached zones or where they 'pinch out' against
                                                                                                                                                        Carnallitite. They are separated by 2.5-4.5 m thick Rock-salt layer referred
                                                                                                                                                        to as the interburden halite ("IBH"). Sylvinite Hangingwall Seam is extremely
                                                                                                                                                        high grade (55-60% KCl) but is not as widely preserved as the Upper and Lower
                                                                                                                                                        Seam being truncated by the Anhydrite Member over most of the deposit. Where
                                                                                                                                                        it does occur, it is approximately 60 m above the Upper Seam and is typically
                                                                                                                                                        2.5 to 4.0 m thick. The Top Seams are a collection of narrow high grade seams
                                                                                                                                                        10-15 m above the Hangingwall Seam but are not considered for extraction at
                                                                                                                                                        Kola as they are absent (truncated by the Anhydrite Member) over almost all
                                                                                                                                                        the deposit.

                                                                                                                                                        The Footwall Seam occurs 45 to 50 m below the Lower Seam. The mode of
                                                                                                                                                        occurrence is different to the other seams in that it is not a laterally
                                                                                                                                                        extensive seam, but rather elongate lenses with a preferred orientation,
                                                                                                                                                        formed not by the replacement of a seam, but by the 'accumulation' of
                                                                                                                                                        potassium at a particular stratigraphic position. It forms as lenses of
                                                                                                                                                        Sylvinite up to 15 m thick and always beneath areas where the Upper and Lower
                                                                                                                                                        seam have been leached. It is considered a product of re-precipitation of the
                                                                                                                                                        leached potassium, into pre-existing Carnallitite-Bischofitite unit at the top
                                                                                                                                                        of cycle 7.

                                                                                                                                                        The insoluble content of the seams and the Rock-salt immediately above and
                                                                                                                                                        below them is uniformly low (<0.2%) except for the FWS which has an average
                                                                                                                                                        insoluble content of 1%. Minor anhydrite is present throughout the Salt
                                                                                                                                                        Member, as 0.5-3 mm thick laminations but comprise less than 2.5% of the rock
                                                                                                                                                        mass of the potash layers.

                                                                                                                                                        Reflecting the quiescence of the original depositional environment, the
                                                                                                                                                        Sylvinite seams exhibit low variation in terms of grade, insoluble content,
                                                                                                                                                        magnesium content; individual sub-layers and mm thick laminations within the
                                                                                                                                                        seams can be followed across the deposit. The grade profile of the seams is
                                                                                                                                                        consistent across the deposit except for the FWS; the US is slightly higher
                                                                                                                                                        grade at its base, the LS slightly higher grade at its top. The HWS is 50 to
                                                                                                                                                        60% sylvite (KCl) throughout. The FWS, forming by introduction of potassium
                                                                                                                                                        and more variable mode of formation has a higher degree of grade variation and
                                                                                                                                                        thickness.

                                                                                                                                                        The original sedimentary layer and 'precursor' potash rock type is
                                                                                                                                                        Carnallitite and is preserved in an unaltered state in many holes drill-holes,
                                                                                                                                                        especially of LS and in holes that are lateral to the deposit. It is comprised
                                                                                                                                                        of the minerals carnallite (KMgCl(3)·6H(2)O), halite (NaCl) (these two
                                                                                                                                                        minerals comprise 97.5% of the rock) and minor anhydrite and insolubles
                                                                                                                                                        (<2.5%).  The Carnallitite is replaced by Sylvinite by a process of
                                                                                                                                                        'outsalting' whereby brine (rich in dissolved NaCl) resulted in the
                                                                                                                                                        dissolution of carnallite, and the formation of new halite (in addition to
                                                                                                                                                        that which may already be present) and leaving residual KCl precipitating as
                                                                                                                                                        sylvite. This 'outsalting' process produced a chloride brine rich in Mg and
                                                                                                                                                        Na, which presumably continued filtering down and laterally through the Salt
                                                                                                                                                        Member.

                                                                                                                                                        The grade of the Sylvinite is proportional to the grade of the precursor
                                                                                                                                                        Carnallitite. For example, in the case of the HWS when Carnallitite is 90
                                                                                                                                                        percent carnallite (and grades between 24 and 25 percent KCl), if all
                                                                                                                                                        carnallite was replaced by sylvite the resulting Sylvinite would theoretically
                                                                                                                                                        be 70.7 percent (by weight) sylvite. However, as described above the inflowing
                                                                                                                                                        brine introduced new halite into the potash layer, reducing the grade so that
                                                                                                                                                        the final grade of the Sylvinite of layer 3/IX is between 50 and 60 percent
                                                                                                                                                        KCl (sylvite).

                                                                                                                                                        Importantly, the replacement of Carnallitite by Sylvinite advanced laterally
                                                                                                                                                        and always in a top-down sense within the seam. This Sylvinite-Carnallitite
                                                                                                                                                        transition (contact) is observed in core and is very abrupt.  Above the
                                                                                                                                                        contact the rock is completely replaced (Sylvinite with no carnallite) and
                                                                                                                                                        below the contact the rock is un-replaced (Carnallitite with no sylvite). In
                                                                                                                                                        many instances the full thickness of the seam is replaced by Sylvinite, in
                                                                                                                                                        others the Sylvinite replacement advanced only part-way down through the seam.
                                                                                                                                                        Carnallitite is reliably distinguished from Sylvinite based on any one of the
                                                                                                                                                        following:

                                                                                                                                                        ·      Visually: Carnallitite is orange, Sylvinite is orange-red or
                                                                                                                                                        pinkish red in colour and less vibrant.

                                                                                                                                                        ·      Gamma data: Carnallitite < 350 API, Sylvinite >350 API

                                                                                                                                                        ·      Magnesium data: Sylvinite at Kola does not contain more than 0.1%
                                                                                                                                                        Mg. Instances of up to 0.3% Mg within Sylvinite explained by 1-2 cm of
                                                                                                                                                        Carnallitite included in the lowermost sample where underlain by Carnallitite.
                                                                                                                                                        Carnallitite contains upwards to 5% Mg.

                                                                                                                                                        ·      Acoustic televeiwer and calliper data clearly identify
                                                                                                                                                        Carnallitite from Sylvinite.

                                                                                                                                                        Based on the 'stage' of replacement, 5 seam types are recognized. The
                                                                                                                                                        replacement process was extremely effective, no mixture of Carnallitite and
                                                                                                                                                        Sylvinite is observed, and within a seam, Carnallitite is not found above
                                                                                                                                                        Sylvinite.

                                                                                                                                                        It is thought that over geological time groundwater and/or water released by
                                                                                                                                                        the dehydration of gypsum (during conversion to anhydrite in the Anhydrite
                                                                                                                                                        Member) infiltrated the Salt Member under gravity, centred on areas of
                                                                                                                                                        'relatively disturbed stratigraphy' referred to as RDS zones (not to be
                                                                                                                                                        confused with subsidence anomalies, see section 3.5). In these areas the salt
                                                                                                                                                        appears to be gently undulating over broad zones, or forms more discrete
                                                                                                                                                        strike extensive gentle antiformal features. There appears to be a correlation
                                                                                                                                                        of these areas with small amounts undulation of the overlying strata and the
                                                                                                                                                        Salt Member and thickening of the Bischofitite at the top of Cycle 7 (some
                                                                                                                                                        45-50 m below the LS). The cause of the undulation appears to be related to
                                                                                                                                                        immature salt-pillowing.

                                                                                                                                                        The process of sylvinite formation appears to have been very gradual and
                                                                                                                                                        non-destructive; where leached, the salt remains in-tact and layering is
                                                                                                                                                        preserved. Brine or voids are not observed. Fractures within the Salt Member
                                                                                                                                                        appear to be restricted to areas of localized subsidence, as observed in
                                                                                                                                                        potash deposits mined elsewhere, and described in more detail in section 3.5.

                                                                                                                                                        Within and lateral to the RDS zones, brine moved downward then laterally,
                                                                                                                                                        preferentially along the thicker higher porosity Carnallitite layers,
                                                                                                                                                        replacing the carnallite with sylvite (as described in preceding text) 10s to
                                                                                                                                                        100's metres laterally and to a depth of 80-90 m below the Anhydrite Member.
                                                                                                                                                        Beyond the zone affected by sylvite replacement, the potash is of unaltered
                                                                                                                                                        primary Carnallitite. In the intermediate zone, the lower part of the layer
                                                                                                                                                        may not be replaced supporting a lateral then 'top-down' replacement of the
                                                                                                                                                        seams. For the most part the US is 'full' (fully replaced by Sylvinite), and
                                                                                                                                                        the LS often is Carnallitite especially within synformal areas giving rise to
                                                                                                                                                        pockets or troughs of Carnallitite. The HWS, being close to the anhydrite is
                                                                                                                                                        only preserved in synformal areas where it is always Sylvinite (being close to
                                                                                                                                                        the top of the Salt Member), or lateral to the main deposit where it is likely
                                                                                                                                                        to be Carnallitite, relating to the broader control on the zone of Sylvinite
                                                                                                                                                        formation discussed below.

                                                                                                                                                        Some of the longer seismic lines show that the relative disturbance of the
                                                                                                                                                        salt over much of Kola relates to the 'elevation' of the stratigraphy due to
                                                                                                                                                        the formation of a northwest-southeast orientated horst block, bound either
                                                                                                                                                        side by half-graben. The horst block referred to as the 'Kola High' and is
                                                                                                                                                        approximately 8 km wide and at least 20 km in length. Lateral to this 'high'
                                                                                                                                                        Sylvinite is rarely found except immediately beneath (within 5-10 m of) the
                                                                                                                                                        Anhydrite Member.

 2.4 Drill hole Information                                            ·     A summary of all information material to the understanding of the          All drill-hole collar information for holes relevant to the Mineral Resource
                                                                       exploration results including a tabulation of the following information for      estimate was provided in Table 5 of the announcement (dated 27 Feb 2025),
                                                                       all Material drill holes:                                                        including historic holes. Hydrological drill-holes are excluded as they were

                                                                                drilled to a shallow depth. All holes except one were drilled vertically and
                                                                       o easting and northing of the drill hole collar                                  deflection from this angle was less than 3 degrees for almost all holes. Holes

                                                                                were surveyed with a gyroscope or magnetic deviation tool to obtain downhole
                                                                       o elevation or RL (Reduced Level - elevation above sea level in metres) of the   survey data.
                                                                       drill hole collar

                                                                       o dip and azimuth of the hole

                                                                       o down hole length and interception depth

                                                                       o hole length.

                                                                       ·     If the exclusion of this information is justified on the basis that
                                                                       the information is not Material and this exclusion does not detract from the
                                                                       understanding of the report, the Competent Person should clearly explain why
                                                                       this is the case.
 2.5 Data aggregation methods                                          ·     In reporting Exploration Results, weighting averaging techniques,          For the calculation of the grade over the full thickness of the seams, the
                                                                       maximum and/or minimum grade truncations (eg cutting of high grades) and         standard 'length-weighted' compositing method was used to combine individual
                                                                       cut-off grades are usually Material and should be stated.                        results within each seam intersection.

                                                                       ·     Where aggregate intercepts incorporate short lengths of high grade
                                                                       results and longer lengths of low grade results, the procedure used for such

                                                                       aggregation should be stated and some typical examples of such aggregations      No selective cutting of high or low grade material was carried out as it is
                                                                       should be shown in detail.                                                       not justified given the massive nature of the potash mineralization and

                                                                                absence of the localised high/low grade areas.
                                                                       ·     The assumptions used for any reporting of metal equivalent values

                                                                       should be clearly stated.

                                                                                                                                                        Results for short lengths of high grade material included in the Mineral
                                                                                                                                                        Resource Estimate are justifiable based on their lateral continuity. They were
                                                                                                                                                        included in the full seam grade by standard 'length-weighted' compositing.

                                                                                                                                                        No metal equivalents were calculated.

 2.6 Relationship between mineralisation widths and intercept lengths  ·     These relationships are particularly important in the reporting of         All mineralised intersections where the dip of the seam is 15 degrees or
                                                                       Exploration Results.                                                             greater were corrected to obtain true thickness which was used in the Mineral

                                                                                Resource Estimate.
                                                                       ·     If the geometry of the mineralisation with respect to the drill
                                                                       hole angle is known, its nature should be reported.

                                                                       ·     If it is not known and only the down hole lengths are reported,
                                                                       there should be a clear statement to this effect (eg 'down hole length, true
                                                                       width not known').
 2.7 Diagrams                                                          ·     Appropriate maps and sections (with scales) and tabulations of             The announcement (dated 27 Feb 2025) included appropriate maps and sections.
                                                                       intercepts should be included for any significant discovery being reported
                                                                       These should include, but not be limited to a plan view of drill hole collar
                                                                       locations and appropriate sectional views.
 2.8 Balanced reporting                                                ·     Where comprehensive reporting of all Exploration Results is not            Not relevant to the reporting of the Mineral Resource Estimate.
                                                                       practicable, representative reporting of both low and high grades and/or
                                                                       widths should be practiced to avoid misleading reporting of Exploration
                                                                       Results.
 2.9 Other substantive exploration data                                ·     Other exploration data, if meaningful and material, should be              All substantive data has been reported herein.
                                                                       reported including (but not limited to): geological observations; geophysical
                                                                       survey results; geochemical survey results; bulk samples - size and method of
                                                                       treatment; metallurgical test results; bulk density, groundwater, geotechnical
                                                                       and rock characteristics; potential deleterious or contaminating substances.
 2.10 Further work                                                     ·     The nature and scale of planned further work (eg tests for lateral         The exploration database should be updated with the most recent drilling data.
                                                                       extensions or depth extensions or large-scale step-out drilling).                No other further work is necessary currently. If conversion of Indicated

                                                                                resources to Measured and Inferred to Indicated Mineral Resource is deemed
                                                                       ·     Diagrams clearly highlighting the areas of possible extensions,            important, additional seismic data would need to be acquired. Furthermore, the
                                                                       including the main geological interpretations and future drilling areas,         deposit is open laterally, in places to the west and east (though in the case
                                                                       provided this information is not commercially sensitive.                         of the latter is limited by the Mining Lease boundary) and probably to the
                                                                                                                                                        greatest extent to the southeast, along the strike of the Kola High.
                                                                                                                                                        Additional drilling and seismic data may allow the delineation of additional
                                                                                                                                                        resources in these areas if results of the work are positive.

 
Section 3 Estimation and Reporting of Mineral Resources

(Criteria listed in section 1, and where relevant in section 2, also apply to
this section.)

 Criteria                                          JORC Code explanation                                                            Commentary
 3.1 Database integrity                            ·     Measures taken to ensure that data has not been corrupted by, for          Geological data is collected in hardcopy then captured digitally by data
                                                   example, transcription or keying errors, between its initial collection and      entry. All entries are thoroughly checked. During import into Micromine©
                                                   its use for Mineral Resource estimation purposes.                                software, an error file is generated identifying any overlapping intervals,

                                                                                gaps and other forms of error. The data is then compared visually in the form
                                                   ·     Data validation procedures used.                                           of strip logs against geophysical data. Laboratory data was imported into an
                                                                                                                                    Access database using an SQL driven software, to sort QA-QC samples and a
                                                                                                                                    check for errors is part of the import. Original laboratory result files are
                                                                                                                                    kept as a secure record. For the Mineral Resource model a 'stratigraphic file'
                                                                                                                                    was generated, as synthesis of key geological units, based on geological,
                                                                                                                                    geophysical and assay data. The stratigraphic file was then used as a key
                                                                                                                                    input into the Mineral Resource model; every intersection and important
                                                                                                                                    contact was checked and re-checked, by visual comparison with the other data
                                                                                                                                    types in log format. Kore Potash is in the process of creating an updated
                                                                                                                                    database, to include the most recent geology and assay data.

                                                                                                                                    For the process of setting up a Mineral Resource database, Met-Chem division
                                                                                                                                    of DRA Americas Inc., a subsidiary of the DRA Group underwent a rigorous
                                                                                                                                    exercise of checking the database, including a comparison with the original
                                                                                                                                    laboratory certificates. Once an explanation of the files had had been
                                                                                                                                    provided, no errors were found with the assay or stratigraphic data, or with
                                                                                                                                    the other data types imported (collar, survey, geophysics). The database is
                                                                                                                                    considered as having a high degree of integrity.

 3.2 Site visits                                   ·     Comment on any site visits undertaken by the Competent Person and          The Competent Person visited the project from the 5-7 November 2016 to view
                                                   the outcome of those visits.                                                     drill-hole sites, the core shed and sample preparation area. Explanation of

                                                                                all procedures were provided by the Company, and a procedural document for
                                                   ·     If no site visits have been undertaken indicate why this is the            core logging, marking and sampling reviewed.  Time was spent reviewing core
                                                   case.                                                                            and hard copy geological logs. All was found to meet or exceed the industry
                                                                                                                                    standards.

 3.3 Geological interpretation                     ·     Confidence in (or conversely, the uncertainty of) the geological           Recognition and correlation of potash and other important layers or contacts
                                                   interpretation of the mineral deposit.                                           between holes is straightforward and did not require assumptions to be made,

                                                                                due the continuity and unique characteristics of each of the evaporite layers;
                                                   ·     Nature of the data used and of any assumptions made.                       each being distinct when thickness, grade and grade distribution, and

                                                                                stratigraphic position relative to other layers is considered. Further support
                                                   ·     The effect, if any, of alternative interpretations on Mineral              is provided by the reliable identification of 'marker' units within and at the
                                                   Resource estimation.                                                             base of the evaporite cycles. Correlation is further aided by the downhole

                                                                                geophysical data clearly shows changes in mineralogy of the evaporite layers
                                                   ·     The use of geology in guiding and controlling Mineral Resource             and is used to validate or adjust the core logged depths of the important
                                                   estimation.                                                                      contacts. The abrupt nature of the contacts, particularly between the

                                                                                Rock-salt, Sylvinite and Carnallitite contributes to above.
                                                   ·     The factors affecting continuity both of grade and geology.

                                                                                                                                    Between holes the seismic interpretation is the key control in the form and
                                                                                                                                    extent of the Sylvinite, in conjunction with the application of the geological
                                                                                                                                    model. The controls on the formation of the Sylvinite is well understood and
                                                                                                                                    the 'binary' nature of the potash mineralization allows an interpretation with
                                                                                                                                    a degree of confidence that relates to the support data spacing, which in turn
                                                                                                                                    is reflected in the classification. In this regard geology was relied upon to
                                                                                                                                    guide and control the model, as described in detail section 3.5. Alternative
                                                                                                                                    interpretations were tested as part of the modelling process but generated
                                                                                                                                    results that do not honour the drill-hole data as well as the adopted model.

                                                                                                                                    The following features affect the continuity of the Sylvinite or Carnallitite
                                                                                                                                    seams, all of which are described further in Section 3.5. By using the seismic
                                                                                                                                    data and the drill-hole data, the Mineral Resource model captures the
                                                                                                                                    discontinuities with a level of confidence reflected in the classification.

                                                                                                                                    •     where the seams are truncated by the anhydrite

                                                                                                                                    •     where the Sylvinite pinches out becoming Carnallitite or vice
                                                                                                                                    versa

                                                                                                                                    •     areas where the seams are leached within zones of subsidence

                                                                                                                                    Outside of these features, grade continuity is high reflecting the small range
                                                                                                                                    in variation of grade of each seam, within each domain. Further description of
                                                                                                                                    grade variation is provided in later in text.

 3.4 Dimensions                                    ·     The extent and variability of the Mineral Resource expressed as            In its entirety, the deposit is 14 km in length (deposit scale strike) and 9
                                                   length (along strike or otherwise), plan width, and depth below surface to the   km in width. The shallowest point of the upper most Sylvinite (of the HWS) is
                                                   upper and lower limits of the Mineral Resource.                                  approximately 190 metres below surface. The depth to the deepest Sylvinite (of
                                                                                                                                    the FWS) is approximately 340 metres below surface. The thickness of the seams
                                                                                                                                    was summarized in Table 3 of the announcement (dated 27 Feb 2025).
 3.5 Estimation and modelling techniques           ·     The nature and appropriateness of the estimation technique(s)              Table 8 and Table 9 of the announcement (dated 27 Feb 2025) provide the
                                                   applied and key assumptions, including treatment of extreme grade values,        Mineral Resource for Sylvinite and Carnallitite at Kola. This Mineral Resource
                                                   domaining, interpolation parameters and maximum distance of extrapolation from   replaces that dated 21 August 2012, prepared by CSA Global Pty Ltd. This
                                                   data points. If a computer assisted estimation method was chosen include a       update incorporates reprocessed seismic data and additional drilling data.
                                                   description of computer software and parameters used.                            Table 10 and Table 11 of the announcement (dated 27 Feb 2025) provide the

                                                                                Sylvinite and Carnallitite Mineral Resource from 2012. The updated Measured
                                                   ·     The availability of check estimates, previous estimates and/or mine        and Indicated Mineral Resource categories are not materially different from
                                                   production records and whether the Mineral Resource estimate takes appropriate   the 2012 estimate and is of slightly higher grade. The Inferred category has
                                                   account of such data.                                                            reduced due to the reduction in the FWSS tonnage, following the updated

                                                                                interpretation of it being present within relatively narrow lenses that are
                                                   ·     The assumptions made regarding recovery of by-products.                    more constrained than in the previous interpretation. There is no current plan

                                                                                to consider the FWSS as a mining target and so the reduction in FWSS tonnage
                                                   ·     Estimation of deleterious elements or other non-grade variables of         is of no consequence to the project's viability.
                                                   economic significance (eg sulphur for acid mine drainage characterisation).

                                                   ·     In the case of block model interpolation, the block size in

                                                   relation to the average sample spacing and the search employed.                  As described in section 3.3, the spatial application of the geological model

                                                                                was central to the creation of the Mineral Resource model. Geological controls
                                                   ·     Any assumptions behind modelling of selective mining units.                were used in conjunction with the seismic data interpretation. The process

                                                                                commenced with the interpretation of the depth migrated drill-hole-tied
                                                   ·     Any assumptions about correlation between variables.                       seismic data in Micromine 2013 © involving the following. Table 7 of the

                                                                                announcement (dated 25 Feb 2025) provides an explanation of abbreviations used
                                                   ·     Description of how the geological interpretation was used to               in text.
                                                   control the resource estimates.

                                                   ·     Discussion of basis for using or not using grade cutting or

                                                   capping.                                                                         1.     Interpretation of the base of anhydrite surface or Salt Roof

                                                                                ("SALT_R") which is typically a distinct seismic event.
                                                   ·     The process of validation, the checking process used, the

                                                   comparison of model data to drill hole data, and use of reconciliation data if   2.     Interpretation of base of salt, the 'intra-salt marker' and 'base
                                                   available.                                                                       cycle 8' ("BoC8") markers. Based on synthetic seismograms the latter is a
                                                                                                                                    negative event picking out the contrast between the top of the Cy78 and
                                                                                                                                    overlying Rock-salt.

                                                                                                                                    Using Leapfrog Geo 4.0 (Leapfrog) surfaces were created for the SALT_R and
                                                                                                                                    BoC8 . In doing so, an assessment of directional control on the surfaces was
                                                                                                                                    made; following the observation based on the sectional interpretation a
                                                                                                                                    WNW-ESE 'strike' is evident. Experimental semi-variograms were calculated for
                                                                                                                                    the surface elevation values at 10° azimuth increments. All experimental
                                                                                                                                    semi-variograms were plotted; 100° and 10° produce good semi-variograms for
                                                                                                                                    the directions of most and least continuity respectively. This directional
                                                                                                                                    control was adopted for the modelling of surfaces, created in Leapfrog on a 20
                                                                                                                                    by 20 m 'mesh' using a 2:1 ellipsoid ratio (as indicated by the semi-variogram
                                                                                                                                    ranges).

                                                                                                                                    The following steps were then carried out:

                                                                                                                                    1.     The BoC8 surface was projected up to the position of the Upper Seam
                                                                                                                                    roof (US_R) by 'gridding' the interval between these units from drill-hole
                                                                                                                                    data. On seismic lines, The US_R interpretation was then adjusted to fit
                                                                                                                                    reflectors at that position, considering interference features common in the
                                                                                                                                    data in the Salt Member close to the SALT_R

                                                                                                                                    2.     In all cases drill-hole intersections were honoured. In addition to
                                                                                                                                    USS and USC intersections, the small number of leached US intersections, all
                                                                                                                                    within subsidence zones) were used to guide the seam model.

                                                                                                                                    3.     The new US_R interpretation along seismic lines, was then 'gridded'
                                                                                                                                    in Leapfrog, also into a mesh of 20 m by 20 m resolution making use of the
                                                                                                                                    100° directional control and 2:1 anisotropy, to create a new US_R surface.

                                                                                                                                    The Mineral Resource model has two potash domains in order to represent the
                                                                                                                                    geology i.e. Sylvinite or Carnallitite. A third non-potash domain areas of
                                                                                                                                    leaching and/or subsidence as described in the following text. Using the
                                                                                                                                    reference horizons, the Sylvinite and Carnallitite seam model was developed as
                                                                                                                                    follows:

                                                                                                                                    1.     The US_R surface was fixed as the reference horizon for the
                                                                                                                                    modelling of the US, LS and HWS. The US_R surface was imported into Datamine
                                                                                                                                    Studio 3 (Datamine), using the same 20 by 20 m cells as described above.

                                                                                                                                    2.     The US Sylvinite (USS) model was developed by analysing the
                                                                                                                                    position of the cell in relation to the SALT_R and to the RDS zones. The
                                                                                                                                    latter were interpreted from seismic data. As described in section 2.3 these
                                                                                                                                    attributes are the main geological controls.

                                                                                                                                    3.     To a lesser extent the dip of the seam and the relative elevation
                                                                                                                                    of each cell, relative to the cells within a 100 by 100 m area were also
                                                                                                                                    considered, to further identify Sylvinite with the understanding that areas of
                                                                                                                                    very low dip are more likely to be of Carnallitite.

                                                                                                                                    4.     Beyond the 2010/2011 seismic data (within the Indicated Mineral
                                                                                                                                    Resource area) the influence of the distance from RDS zones was reduced and
                                                                                                                                    the proximity to the SALT_R and the dip and relative elevation were assigned
                                                                                                                                    greater consideration.

                                                                                                                                    5.     Seam thickness of the USS was determined by gridding the drill-hole
                                                                                                                                    data of the full Sylvinite intersections (excluding those that have a
                                                                                                                                    Carnallitite basal layer or are leached) using Inverse distance squared
                                                                                                                                    ("IDW(2)") and adjusting it to account for the influence of 2 and 3 above. The
                                                                                                                                    Sylvinite thickness was then subtracted from the elevation of the US_R to
                                                                                                                                    create the USS floor ("USS_F"), on the 20m by 20m mesh.

                                                                                                                                    6.     Only the true thickness of drill-hole intersections were used (i.e.
                                                                                                                                    corrections for any dip were made) for the above. As the seam model thickness
                                                                                                                                    developed in a vertical sense, areas of the model with a dip were corrected so
                                                                                                                                    that the true thickness was always honoured.

                                                                                                                                    7.     Even if the USS has zero thickness the surface for the USS_F was
                                                                                                                                    created, overlying exactly that of the US_R to facilitate the creation of DTMs
                                                                                                                                    for each surface.

                                                                                                                                    8.     The same method (effectively the inverse) was applied to create the
                                                                                                                                    US Carnallitite model ("USC") below the USS. The roof of the USC ("USC_R") is
                                                                                                                                    the same surface as the USS_F.

                                                                                                                                    9.     A number of iterations of the model were produced and assessed. The
                                                                                                                                    selected model was the one that produced a result that ties well with the
                                                                                                                                    drill-hole data and honours the proportional abundance of Sylvinite as
                                                                                                                                    intersected in the drill-holes.

                                                                                                                                    The Lower Seam model was created in a similar manner as follows:

                                                                                                                                    1.     The LS is separated by between 2 and 6 metres of barren Rock-salt,
                                                                                                                                    also referred to as the Interburden-halite or IBH. This layer is an important
                                                                                                                                    geotechnical consideration and so care was taken to model it. The IBH
                                                                                                                                    thickness from drill-hole data was 'gridded' in Datamine using IDW(2) into the
                                                                                                                                    20 by 20 cells. This thickness was then subtracted from the elevation of the
                                                                                                                                    US_F to obtain the LS_R elevation from which a DTM was made.

                                                                                                                                    2.     Unlike the USS the LSS is often underlain by a layer of
                                                                                                                                    Carnallitite. For the LSS model the thickness of the LSS from drill-hole data
                                                                                                                                    was gridded using IDW(2) into the 20 x 20 mesh without influence from distance
                                                                                                                                    to the SALT_R or RDS zones. However, based on the geological understanding
                                                                                                                                    that LSS rarely occurs beneath USC the LSS model was cut accordingly, based on
                                                                                                                                    the USC model. Reflecting the model and based on analysis the following rule
                                                                                                                                    was also applied; that if the US is 'full' then the LSS is also full but only
                                                                                                                                    if the LS_R is within 30 m of the SALT_R. Finally, if the US_R is truncated by
                                                                                                                                    the SALT_R, then the remaining LS is modelled as full LSS due to its proximity
                                                                                                                                    to the SALT_R.

                                                                                                                                    For the US and LS Inferred Resources, the distribution of Sylvinite and
                                                                                                                                    Carnallitite was by manual interpretation based on available drill-hole data
                                                                                                                                    and plots of the distance between the seam and the SALT_R. The thickness of
                                                                                                                                    the USS and LSS was determined by gridding all USS drill-hole data. The
                                                                                                                                    Carnallitite was then modelled as the Inverse of the Sylvinite model, in
                                                                                                                                    adherence to the geological model.

                                                                                                                                    The Hangingwall seam model was created as follows

                                                                                                                                    1.     The distance between the US_R and HWS_R in drill-hole intersection
                                                                                                                                    was gridded using IDW(2) into the 20 by 20 m mesh. This data was then added to
                                                                                                                                    the elevation of the US_R to create a HWS_R.

                                                                                                                                    2.     Being close to the SALT_R (within 30 m in all cases) there is less
                                                                                                                                    variation in domain type; in all areas except for the zone labelled 'A' on
                                                                                                                                    Figure 24 of the announcement (dated 27 Feb 2025) the USS is full Sylvinite
                                                                                                                                    (not underlain by USC). For all HWS outside of zone A the model was created by
                                                                                                                                    gridding the thickness using IDW(2) into the 20 x 20 mesh.

                                                                                                                                    3.     The HWS model was created without input from distance to the SALT_R
                                                                                                                                    or RDS zones for the reasons stated above, by gridding of the drill-hole
                                                                                                                                    intersections.

                                                                                                                                    4.     Within the area labelled 'A' on Figure 24 of the announcement
                                                                                                                                    (dated 27 Feb 2025), the HWSS is underlain by HWSC and so this was
                                                                                                                                    incorporated into the model.

                                                                                                                                    5.     Finally, the HWS was 'pinched' upwards from 4 m below the SALT_R to
                                                                                                                                    reflect the geological observation that close to this surface the seam is
                                                                                                                                    leached.

                                                                                                                                    Modelling of the FWS

                                                                                                                                    1.     A different approach was adopted for the modelling of the FWS as
                                                                                                                                    the mode of occurrence is different to the other seams as described in section
                                                                                                                                    2.3. Only Sylvinite FWSS was modelled as Carnallitite FWS is poorly developed
                                                                                                                                    or absent, and low grade.

                                                                                                                                    2.     Drill-hole and seismic data was used to identify areas of leaching
                                                                                                                                    of the Salt Member based on subsidence of the overlying strata signs of marked
                                                                                                                                    disturbance of the salt, within which FWSS is typically developed. These were
                                                                                                                                    delineated in plan view.

                                                                                                                                    Where possible drill-hole data was used to guide thickness of the FWS, in
                                                                                                                                    other areas the thickness was interpreted using the seismic data. The FWS was
                                                                                                                                    'constructed' from the top of the Cy7B upwards.

                                                                                                                                    As is standard practice in potash mining zones of subsidence which pose a
                                                                                                                                    potential risk to mining were identified using seismic and drill-hole data and
                                                                                                                                    classified from 1 to 3 depending on severity where 3 is highest. Several
                                                                                                                                    drill-holes within or adjacent to these features show that the Salt Member is
                                                                                                                                    intact but has experienced some disturbance and leaching.

                                                                                                                                    The HWS, US and LS Mineral Resource models were 'cookie-cut' by these
                                                                                                                                    anomalies before calculation of the Mineral Resource estimate. The FWSS model
                                                                                                                                    was not cut as that Sylvinite is considered the product of potassium
                                                                                                                                    precipitation below the influence of the subsidence anomalies.

                                                                                                                                    Finally, all the potash seams were truncated (cut) by the SALT_R surface (base
                                                                                                                                    of the Anhydrite Member) as it is an unconformity.

                                                                                                                                    Traditional block modelling was employed for estimating %KCl, %Na, %Cl, %Mg,
                                                                                                                                    %S, %Ca and %Insols (insolubles). No assumptions were made regarding
                                                                                                                                    correlation between variables. The block model is orthogonal and rotated by 20
                                                                                                                                    degrees reflecting the orientation of the deposit. The block size chosen was
                                                                                                                                    250m x 250m x 1m to roughly reflect drill hole spacing, seam thickness and to
                                                                                                                                    adequately descretize the deposit without injecting error.

                                                                                                                                    Volumetric solids were created for the individual mineralized zones (i.e.,
                                                                                                                                    Hangingwall Seam, Upper Seam, Lower Seam, Footwall Seam) for both Sylvinite
                                                                                                                                    and Carnallitite using drill hole data and re-processed depth migrated seismic
                                                                                                                                    data. The solids were adjusted by moving the nodes of the triangulated domain
                                                                                                                                    surfaces to exactly honour the drill hole intercepts. Numeric codes denoting
                                                                                                                                    the zones within the drill hole database were manually adjusted to ensure the
                                                                                                                                    accuracy of zonal intercepts. No assay values were edited or altered.

                                                                                                                                    Once the domain solids were created, they were used to code the drill hole
                                                                                                                                    assays and composites for subsequent statistical analysis. These solids or
                                                                                                                                    domains were then used to constrain the interpolation procedure for the
                                                                                                                                    mineral resource model, the solids zones were then used to constrain the block
                                                                                                                                    model by matching composites to those within the zones in a process called
                                                                                                                                    geologic matching. This ensures that only composites that lie within a
                                                                                                                                    particular zone are used to interpolate the blocks within that zone.

                                                                                                                                    Relative elevation interpolation methods were also employed which is helpful
                                                                                                                                    where the grade is layered or banded and is stratigraphically controlled. In
                                                                                                                                    the case of Kola, layering manifests itself as a relatively high-grade band at
                                                                                                                                    the footwall, which gradually decreases toward the hanging wall. Due to the
                                                                                                                                    undulations of the deposit, this estimation process accounts for changes in
                                                                                                                                    dip that are common in layered and stratified deposits.

                                                                                                                                    The estimation plan includes the following:

                                                                                                                                    ·        Store the mineralized zone code and percentage of
                                                                                                                                    mineralization.

                                                                                                                                    ·        Apply the density, based on calculated specific gravity.

                                                                                                                                    ·        Estimate the grades for each of the metals using the relative
                                                                                                                                    elevation method and an inverse distance using three passes. The three
                                                                                                                                    estimation passes were used to estimate the Resource Model because a more
                                                                                                                                    realistic block-by-block estimation can be achieved by using more restrictions
                                                                                                                                    on those blocks that are closer to drill holes, and thus better informed.

                                                                                                                                    ·        Include a minimum of one composite and a maximum of nine,
                                                                                                                                    with a maximum of three from any one drill hole.

                                                                                                                                    The nature and distribution of the Kola Deposit shows uniform distribution of
                                                                                                                                    KCl grades without evidence of multiple populations which would require
                                                                                                                                    special treatment by either grade limiting or cutting. Therefore, it was
                                                                                                                                    determined that no outlier or grade capping was necessary.

                                                                                                                                    The grade models have been developed using inverse distance and anisotropic
                                                                                                                                    search ellipses measure 250 x 150 x 50 m and have been oriented relative to
                                                                                                                                    the main direction of continuity within each domain.  Anisotropic distances
                                                                                                                                    have been included during interpolation; in other words, weighting of a sample
                                                                                                                                    is relative to the range of the ellipse. A sample at a range of 250 m along
                                                                                                                                    the main axis is given the same weight as a sample at 50 m distance located
                                                                                                                                    across the strike of the zone.

                                                                                                                                    A full set of cross-sections, long sections, and plans were used to check the
                                                                                                                                    block model on the computer screen, showing the block grades and the
                                                                                                                                    composite.  There was no evidence that any blocks were wrongly estimated.
                                                                                                                                    It appears that block grades can be explained as a function of: the
                                                                                                                                    surrounding composites, the solids models used, and the estimation plan
                                                                                                                                    applied.  In addition, manual ballpark estimates for tonnage to determine
                                                                                                                                    reasonableness was confirmed along with comparisons against the nearest
                                                                                                                                    neighbor estimate.

                                                                                                                                    As a check on the global tonnage, an estimate was made in Microsoft Excel by
                                                                                                                                    using the average seam thickness and determining a volume based on the
                                                                                                                                    proportion of holes containing Sylvinite versus the total number of holes
                                                                                                                                    (excluding those that did not reach the target depth) then applying the mean
                                                                                                                                    density of 2.1 (t/m(3)) to determine the total tonnes. This was carried out
                                                                                                                                    for the USS and LSS within the Measured and Indicated categories. A deduction
                                                                                                                                    was made to account for loss within subsidence anomalies. The tonnage of this
                                                                                                                                    estimate is within 10% of the tonnage of the reported Mineral Resource.

 3.6 Moisture                                      ·     Whether the tonnages are estimated on a dry basis or with natural          Mineral Resource tonnages are reported on an insitu basis (with natural
                                                   moisture, and the method of determination of the moisture content.               moisture content), Sylvinite containing almost no moisture and Carnallitite
                                                                                                                                    containing significant moisture within its molecular structure. Moisture
                                                                                                                                    content of samples was measured using the 'Loss on Drying' ("LOD") method at
                                                                                                                                    Intertek Genalysis as part of the suite of analyses carried out. Data shows
                                                                                                                                    that for Sylvinite the average moisture content is 0.076 % and the maximum
                                                                                                                                    value was 0.6%. Representative moisture analyses of Carnallitite are difficult
                                                                                                                                    as it is so hygroscopic. 38% of the mass of the mineral carnallite is due to
                                                                                                                                    water (6 H(2)0 groups within its structure). Using the KCl data to work out a
                                                                                                                                    mean carnallite content, the Carnallitite has an average moisture content
                                                                                                                                    approximately 25% insitu. It can be reliably assumed that this amount of
                                                                                                                                    moisture would have been held by the Carnallitite samples at the time of
                                                                                                                                    analysis of potassium, in a temperate atmosphere for the duration that they
                                                                                                                                    were exposed.

 3.7 Cut-off parameters                            ·     The basis of the adopted cut-off grade(s) or quality parameters            For Sylvinite, a CoG of 10% was determined by an analysis of the
                                                   applied.                                                                         Pre-feasibility and 'Phased Implementation study' operating costs analysis and
                                                                                                                                    a review of current potash pricing.  The following operating costs were
                                                                                                                                    determined from previous studies per activity per tonne of MoP (95% KCl)
                                                                                                                                    produced from a 33% KCl ore, with a recovery of 89.5%:

                                                                                                                                    ·      Mining US$30/t

                                                                                                                                    ·      Process US$20/t

                                                                                                                                    ·      Infrastructure US$20/t

                                                                                                                                    ·      Sustaining Capex US$15/t

                                                                                                                                    ·      Royalties US$10/t

                                                                                                                                    ·      Shipping US$15/t

                                                                                                                                    For the purpose of the CoG calculation, it was assumed that infrastructure,
                                                                                                                                    sustaining capex, royalty and shipping do not change with grade (i.e. are
                                                                                                                                    fixed) and that mining and processing costs vary linearly with grade. Using
                                                                                                                                    these assumptions of fixed costs (US$60/t) and variable costs at 33% (US$50/t)
                                                                                                                                    and a potash price of US$250/t, we can calculate a cut-off grade where the
                                                                                                                                    expected cost of operations equals the revenue. This is at a grade of 8.6%
                                                                                                                                    KCl. To allow some margin of safety, a CoG of 10% is therefore proposed. For
                                                                                                                                    Carnallitite, reference was made to the Scoping Study for Dougou which
                                                                                                                                    determined similar operating costs for solution mining of Carnallitite and
                                                                                                                                    with the application of a $250/t potash price a CoG of 10% KCl is determined.

 3.8 Mining factors or assumptions                 ·     Assumptions made regarding possible mining methods, minimum mining         The Kola Sylvinite has been the subject of several scoping studies as well as
                                                   dimensions and internal (or, if applicable, external) mining dilution. It is     a publicly available NI43-101 compliant PFS completed in September 2012 by SRK
                                                   always necessary as part of the process of determining reasonable prospects      Consulting of Denver. The study found that economic extraction of 2 to 5m
                                                   for eventual economic extraction to consider potential mining methods, but the   thick seams with conventional underground mining machines is viable and that
                                                   assumptions made regarding mining methods and parameters when estimating         mining thickness as low as 1.8m can be supported. Globally, potash is mined in
                                                   Mineral Resources may not always be rigorous. Where this is the case, this       similar deposits with seams of similar geometry and form. The PFS determined
                                                   should be reported with an explanation of the basis of the mining assumptions    an overall conversion of resources to reserves of 26%. A Definitive
                                                   made.                                                                            Feasibility Study is underway.

                                                                                                                                    Mining of Carnallitite is not planned at this stage but in the form, grade and
                                                                                                                                    quantity of the Carnallitite does support reasonable ground for eventual
                                                                                                                                    economic extraction. A Scoping Study complete in 2015 for the nearby Dougou
                                                                                                                                    Carnallitite deposit further supports this.

 3.9 Metallurgical factors or assumptions          ·     The basis for assumptions or predictions regarding metallurgical           The Kola Sylvinite ore represents a simple mineralogy, containing only
                                                   amenability. It is always necessary as part of the process of determining        sylvite, halite and minor fragments of other insoluble materials. Sylvinite of
                                                   reasonable prospects for eventual economic extraction to consider potential      this nature is well understood globally and can be readily processed.
                                                   metallurgical methods, but the assumptions regarding metallurgical treatment     Separation of the halite from sylvite by means of flotation has been proven in
                                                   processes and parameters made when reporting Mineral Resources may not always    potash mining districts in Russia and Canadas. Furthermore, metallurgical test
                                                   be rigorous. Where this is the case, this should be reported with an             work was performed on all Sylvinite seams (HWSS, USS, LSS and FWSS) at the SRC
                                                   explanation of the basis of the metallurgical assumptions made.                  which confirmed the viability of processing the Kola ore by conventional
                                                                                                                                    flotation.

 3.10 Environmental factors or assumptions         ·     Assumptions made regarding possible waste and process residue              The Kola deposit is located in a sensitive environmental setting in an area
                                                   disposal options. It is always necessary as part of the process of determining   that abuts the CDNP. Approximately 60% of the deposit is located within the
                                                   reasonable prospects for eventual economic extraction to consider the            economic development zone of the CDNP, while the remainder is within the
                                                   potential environmental impacts of the mining and processing operation. While    buffer zone around the park. The economic development zone does permit mining
                                                   at this stage the determination of potential environmental impacts,              activities if it is shown that impact can be minimised. For these reasons,
                                                   particularly for a greenfields project, may not always be well advanced, the     Sintoukola Potash has focussed its efforts on understanding the environmental
                                                   status of early consideration of these potential environmental impacts should    baseline and the potential impacts that the project will have. Social, water,
                                                   be reported. Where these aspects have not been considered this should be         hydrobiology, cultural, archaeological, biodiversity, noise, traffic and
                                                   reported with an explanation of the environmental assumptions made.              economic baseline studies were undertaken as part of the ESIA process between
                                                                                                                                    2011 and 2013. This led to the preparation of an Equator Principles compliant
                                                                                                                                    ESIA in 2013 and approval of this study by the government in the same year.

                                                                                                                                    Waste management for the project is simplified by the proximity to the ocean,
                                                                                                                                    which acts as a viable receptor for NaCl from the process plant. Impacts on
                                                                                                                                    the forest and fauna are minimised by locating the process plant and employee
                                                                                                                                    facilities at the coast, outside the CDNP. Relationships with the national
                                                                                                                                    parks, other NGO's and community and government stakeholders have been
                                                                                                                                    maintained continuously since 2011 and engagement is continuing for the
                                                                                                                                    ongoing DFS. All stakeholders remain supportive of the project.

 3.11 Bulk density                                 ·     Whether assumed or determined. If assumed, the basis for the               The separation of Carnallitite and Sylvinite (no instances of a mixed ore-type
                                                   assumptions. If determined, the method used, whether wet or dry, the frequency   have been observed) and that these rock types each comprise over 97.5% of only
                                                   of the measurements, the nature, size and representativeness of the samples.     two minerals (Carnallitite of carnallite and halite; Sylvinite of sylvite and

                                                                                halite) means that density is proportional to grade. The mineral sylvite has a
                                                   ·     The bulk density for bulk material must have been measured by              specific gravity of 1.99 and halite of 2.17. Reflecting this, the density of
                                                   methods that adequately account for void spaces (vugs, porosity, etc),           Sylvinite is less if it contains more sylvite. The same is true of
                                                   moisture and differences between rock and alteration zones within the deposit.   Carnallitite, carnallite having a density of 1.60.

                                                   ·     Discuss assumptions for bulk density estimates used in the
                                                   evaluation process of the different materials.

                                                                                                                                    Conventional density measurements using the weight in air and weight in water
                                                                                                                                    method were problematic due to the soluble nature of the core and difficulty
                                                                                                                                    applying wax to salt. As an alternative, gas pycnometer analyses were carried
                                                                                                                                    out (71 on Sylvinite and 37 on Carnallitite samples). Density by pycnometer
                                                                                                                                    was plotted against grade for each and a regression line was plotted, the
                                                                                                                                    formula of which was used in the Mineral Resource model to determine the bulk
                                                                                                                                    density of each block. As a check on the pycnometer data, the theoretical bulk
                                                                                                                                    density (assumes a porosity of nil) was plotted using the relationship between
                                                                                                                                    grade and density described above. As a further check, a 'field density' was
                                                                                                                                    determined for Sylvinite and Carnallitite from EK_49 and EK_51 on whole core,
                                                                                                                                    by weighing the core and measuring the volume using a calliper, before sending
                                                                                                                                    samples for analysis. An average field density of 2.10 was derived from the
                                                                                                                                    Sylvinite samples, with an average grade of 39% KCl, and 1.70 for Carnallitite
                                                                                                                                    with an average grade of 21% KCl, supporting the pycnometer data. The
                                                                                                                                    theoretical and field density data support the approach of determining
                                                                                                                                    bulk-density.

 3.12 Classification                               ·     The basis for the classification of the Mineral Resources into             Drill-hole and seismic data are relied upon in the geological modelling and
                                                   varying confidence categories.                                                   grade estimation. Across the deposit the reliability of the geological and

                                                                                grade data is high. Grade continuity is less reliant on data spacing as within
                                                   ·     Whether appropriate account has been taken of all relevant factors         each domain grade variation is small reflecting the continuity of the
                                                   (i.e. relative confidence in tonnage/grade estimations, reliability of input     depositional environment and 'all or nothing' style of Sylvinite formation.
                                                   data, confidence in continuity of geology and metal values, quality, quantity

                                                   and distribution of the data).

                                                   ·     Whether the result appropriately reflects the Competent Person's           It is the data spacing that is the principal consideration as it determines
                                                   view of the deposit.                                                             the confidence in the interpretation of the seam continuity and therefore
                                                                                                                                    confidence and classification; the further away from seismic and drill-hole
                                                                                                                                    data the lower the confidence in the Mineral Resource classification, as
                                                                                                                                    summarized in Table 13 of the announcement (dated 27 Feb 2025). In the
                                                                                                                                    assigning confidence category, all relevant factors were considered and the
                                                                                                                                    final assignment reflects the Competent Persons view of the deposit.

 3.13 Audits or reviews                            ·     The results of any audits or reviews of Mineral Resource estimates.        No audits or reviews of the Mineral Resource have been carried out other than
                                                                                                                                    those of professionals working with Met-Chem division of DRA Americas Inc., a
                                                                                                                                    subsidiary of the DRA Group as part of the modelling and estimation work.

 3.14 Discussion of relative accuracy/ confidence  ·     Where appropriate a statement of the relative accuracy and                 The Competent Person has a very high degree of confidence in the data and the
                                                   confidence level in the Mineral Resource estimate using an approach or           results of the Mineral Resource Estimate. The use of tightly spaced seismic
                                                   procedure deemed appropriate by the Competent Person. For example, the           that was reprocessed using state-of-the-art techniques combined with high
                                                   application of statistical or geostatistical procedures to quantify the          quality drill data formed the solid basis from which to model the deposit.
                                                   relative accuracy of the resource within stated confidence limits, or, if such   Industry standard best practices were followed throughout and rigorous quality
                                                   an approach is not deemed appropriate, a qualitative discussion of the factors   assurance and quality control procedures were employed at all stages. The
                                                   that could affect the relative accuracy and confidence of the estimate.          Competent Person was provided all information and results without exception

                                                                                and was involved in all aspects of the program leading up to the estimation of
                                                   ·     The statement should specify whether it relates to global or local         resources. The estimation strategy and method accurately depict tonnages and
                                                   estimates, and, if local, state the relevant tonnages, which should be           grades with a high degree of accuracy both locally and globally.
                                                   relevant to technical and economic evaluation. Documentation should include

                                                   assumptions made and the procedures used.

                                                   ·     These statements of relative accuracy and confidence of the                There is no production data from which to base an opinion with respect to
                                                   estimate should be compared with production data, where available.               accuracy and confidence.

 

 

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact
rns@lseg.com (mailto:rns@lseg.com)
 or visit
www.rns.com (http://www.rns.com/)
.

RNS may use your IP address to confirm compliance with the terms and conditions, to analyse how you engage with the information contained in this communication, and to share such analysis on an anonymised basis with others as part of our commercial services. For further information about how RNS and the London Stock Exchange use the personal data you provide us, please see our
Privacy Policy (https://www.lseg.com/privacy-and-cookie-policy)
.   END  MSCPPUMWPUPAUMM

Recent news on Kore Potash

See all news