Resolute says Mali mine largely stabilised after disruptions, output to rebound

       DAKAR, Oct 29 (Reuters) - Resolute Mining's  RSG.AX 
flagship Syama gold mine in Mali has largely stabilised after
months of operational disruptions, with production expected to
rebound sharply in the current quarter, company executives said
on Thursday.
    The Syama mine in southwestern Mali is Resolute's largest
asset, accounting for roughly three-quarters of group production
guidance this year. 
    * The Australian miner produced 31,777 ounces at Syama in
the third quarter after explosives shortages, contractor
mobilisation delays and supply-chain disruptions hampered
operations, its third-quarter report showed
    * Chief Operating Officer Gavin Harris told analysts the
Mali operation had "largely stabilized after a turbulent four to
five months", adding that an on-site emulsion plant due to start
operating in November should remove a key bottleneck
    * Resolute expects Syama output to rise to 45,000-50,000
ounces in the fourth quarter as mining and processing
performance improve
    * It also expects grades to recover towards reserve levels
and plant recoveries to improve to around 80% from about 73% in
the third quarter 
    * CEO Chris Eger said the company was maintaining a "very,
very constructive and productive dialogue" with Mali's
government and had seen progress in mining permit renewals


    (Reporting by Maxwell Akalaare Adombila; Editing by Jan
Harvey)